Summer Special Sale - Limited Time 60% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: 575363r9

Welcome To DumpsPedia

PgMP Sample Questions Answers

Questions 4

Eric is the project manager of the NQQ Project and has hired the ZAS Corporation to complete part of the project work for Eric's organization. Due to a change request the ZAS Corporation is no longer needed on the project even though they have completed nearly all of the project work. Is Eric's organization liable to pay the ZAS Corporation for the work they have completed so far on the project?

Options:

A.

It depends on what the outcome of a lawsuit will determine.

B.

No, the ZAS Corporation did not complete all of the work.

C.

It depends on what the termination clause of the contract stipulates.

D.

Yes, the ZAS Corporation did not choose to terminate the contract work.

Buy Now
Questions 5

A new program manager joins a multi-year program that has been underway for almost a year. During interviews, several stakeholders state that they do not understand how the program will help the organization.

At the next stakeholder meeting, what should the program manager present to address their concerns?

Options:

A.

Program charter

B.

Program scope assessment results

C.

Business and program roadmap

D.

Expected program benefits management plan

Buy Now
Questions 6

You are the program manager for the SRQ Program. You have rejected several change requests for the program scope. What must you do with the rejected change requests?

Options:

A.

Communicate why the change request was rejected and record the results in the lessons learned documentation for your program.

B.

Inform the stakeholders that their change requests have been rejected.

C.

Communicate the change request status to the stakeholders and record the results of the change request in the change register.

D.

Inform the stakeholders why their change requests have been rejected.

Buy Now
Questions 7

You are program manager for the HYH Program. Your program governance is requiring you to use earned value management to predict how closely your program is tracking to the cost and schedule baselines and to predict overall program performance. Which earned value management formula can you use to predict how much more will need to be invested in the program based on current program performance?

Options:

A.

EV/AC

B.

EV/PV

C.

BAC/CPI

D.

EAC-AC

Buy Now
Questions 8

Company A recently signed a contract with a strategic business partner, Company B, to jointly roll out a new technology. Company B is excited about the joint marketing opportunity. Company A's component Quality Assurance team has expressed concerns to you, the program manager, that the product is being rolled out prematurely and has identified potential issues with backend support systems. QA, however, assures you that a manual work around is possible, but not ideal. Company B requests an enhancement to the new product. In a meeting with Company B, you determine that additional funding will be required and resources allocated and scheduled.

What is your MOST appropriate next step?

Options:

A.

Secure funding from another project that was cancelled.

B.

Use an integrated change control process.

C.

Use the available management reserve.

D.

Advise Company B that funding and resources are not available.

Buy Now
Questions 9

Robert's program is slipping on its schedule and management has asked that Robert find a method to compress the duration of the program. What approach could Robert take that would not dramatically add risks to program if he added labor to the effort-driven activities within the program?

Options:

A.

Lead time

B.

Crashing

C.

Lag time

D.

Fast tracking

Buy Now
Questions 10

You are the program manager for your organization and are working with your team to identify stakeholders in the program. Where should the identified stakeholders and their information be recorded?

Options:

A.

Stakeholder matrix

B.

Communications management plan

C.

Requirements traceability matrix

D.

Stakeholder registry

Buy Now
Questions 11

You are the program manager for your organization. You're currently creating an accountability matrix starting with yourself, the program manager and the program sponsor. What program management process identifies the program sponsor?

Options:

A.

Pre-program setup phase

B.

Authorization of program processes and projects

C.

Initiate program process

D.

Initiation of the program management team

Buy Now
Questions 12

After an organization initiates a strategic program, several project managers express interest in joining the program team. The program manager’s supervisor recommends a list of project managers to be part of the team.

What should the program manager do to select the project managers?

Options:

A.

Complete a skill set inventory and select the most suitable resource(s)

B.

Ask interested project managers for their CV or résumé and conduct interviews

C.

Accept the recommendation of the program manager’s supervisor

D.

Contact the human resource manager for project managers’ availability

Buy Now
Questions 13

A program is in its execution phase when a component project manager suggests a potential change that could increase the financial benefit of the program. The program manager is hesitant to submit a change

request, as it would extend the program schedule and require a scope change. To whom should the change request be presented?

Options:

A.

The program governance board

B.

The program customer

C.

The program management office (PMO)

D.

The project governance board

Buy Now
Questions 14

What is the other name for critical delivery dates?

Options:

A.

Substantial completion.

B.

Phases.

C.

Flags.

D.

Milestones.

Buy Now
Questions 15

Which of the following increases when one fast tracks the project?

Options:

A.

Resource

B.

Risk

C.

Cost

D.

Communication

Buy Now
Questions 16

What cost estimating approach uses the work breakdown structure to create a cost estimate?

Options:

A.

Analogous

B.

Definitive

C.

Top down

D.

Parametric

Buy Now
Questions 17

A critical program for a company fails to delivers its intended benefits. The CEO and program sponsor are both held accountable and, ultimately, their employment is terminated by the board of directors.

What should the program manager do before formally closing the program?

Options:

A.

Update the benefits register.

B.

Establish a program management information system (PMIS).

C.

Share lessons learned with all program team members.

D.

Transfer all program documentation to the deputy program manager.

Buy Now
Questions 18

Robert is the program manager of the NHQ Program. His team has never worked with one another before this program and he is worried about their abilities to become a team in very short order. He would like to create a team development exercise to facilitate this process. Robert will need all of the following information except for which one to facilitate team development?

Options:

A.

Risk management plan

B.

Program management plan

C.

Personnel records

D.

Training records

Buy Now
Questions 19

A program has a BAC of $1,750,000 and is expected to last two years. The program is currently at the third milestone which represents 35 percent of the program work. As it happens, this program has already spent

$620,000 of the budget. Management is concerned that the program may also be slipping on schedule because the program should be forty percent complete by this time. Based on this information which type of performing is present in this scenario?

Options:

A.

Schedule, because the program's planned value is only $700,000.

B.

Cost, because the program has a cost variance of -7,500

C.

Schedule, because the program has a schedule performance index of .88.

D.

Cost, because the program has an estimate to complete of $1,151,429.

Buy Now
Questions 20

You are the program manager for your organization and are planning the composition of the project team. In your organization resources are used from throughout the company and may serve on more than one project. While you, the program manager, will have most of the authority on the program you want the project managers to have authority over the project decisions. What type of an organizational structure does your organization have?

Options:

A.

Strong Matrix

B.

Functional

C.

Weak Matrix

D.

Projectized

Buy Now
Questions 21

Your program creates a byproduct that you could sell to a client. The cost of the byproduct would offset the cost of the program by nearly $7,500 per month. This is an example of which positive risk response?

Options:

A.

Sharing

B.

Enhance

C.

Exploiting

D.

Accepting

Buy Now
Questions 22

Robert is the program manager for his organization which operates in a matrix structure.

Resources in Robert's program will be utilized on several projects in and out of his program. He wants to be certain that all of the resources will be planned accordingly and that the project managers communicate with one another about when the resources will be needed and utilized in the projects. What plan should Robert create along with the project managers to ensure that the resources are scheduled and managed effectively?

Options:

A.

Resource management plan

B.

Program management calendar

C.

Schedule management plan

D.

Resource calendar

Buy Now
Questions 23

A company implements a transformational business strategy and a program to change its IT infrastructure and service delivery model. While leading a program team from cross-cultural backgrounds and geographies, the program manager notices a varying level of delivery excellence, which they attribute to cultural differences and behavioral tendencies.

To achieve commitment to program goals, what should the program manager do to improve the team's level of engagement?

Options:

A.

Delegate the task of managing team behavior, attitudes, and commitment to team member managers, and ask the managers for regular progress reports.

B.

Organize social events to support the communications enrichment plan, bond the teams, and motivate team members.

C.

Establish a formal mentoring, coaching, and support program to address cultural differences that will enable the team to work collaboratively.

D.

Email all team members mandating that, to deliver program objectives, they must focus on their roles and responsibilities.

Buy Now
Questions 24

A component project manager escalates an issue regarding a key stakeholder to the program manager. The key stakeholder does not respond to emails or phone calls, and the project manager believes this key stakeholder is exhibiting a negative attitude toward the work. The key stakeholder has a significant influence over the component project, which could impact other components if delays occur. The program manager’s attempts to reach the stakeholder via email also fail.

What should the program manager do next?

Options:

A.

Escalate the issue to the stakeholder’s supervisor

B.

Escalate the issue to the program governance board, as delays will impact the program

C.

Update the program risk register to reflect a realized risk and execute the documented risk response

D.

Attempt to call the key stakeholder; if unsuccessful, visit their office to identify potential risks

Buy Now
Questions 25

You are the program manager of HYH Program for your organization. Your program is to create a new sports arena for your city within 12 months. Your program has seven projects and you've worked with all of the project managers before. Even though you've worked with the project managers before you still need to define the authority of the project managers and their projects. What document names the project manager for the project?

Options:

A.

Project charter for each project

B.

Program human resource management plan

C.

Project scope statement

D.

Program management charter

Buy Now
Questions 26

An initiative involves the development of new technology and leverages existing technologies. It is determined critical by the program governance board and the program sponsor that a comprehensive risk management plan be put in place.

In what phase is the risk management plan created?

Options:

A.

Program definition

B.

Program execution management

C.

Program delivery

D.

Program risk management planning

Buy Now
Questions 27

Which of the following tools/techniques keep program managers and executives informed of the program's progress?

Options:

A.

Component analysis

B.

Expert judgment

C.

Review meetings

D.

Capacity planning

Buy Now
Questions 28

Hal is the program manager for his organization. He would like your organization to provide his program with 4 tons of pea gravel for a construction project in his program. Hal send you a statement of work and an IFB. What document should you provide to Hal?

Options:

A.

Invoice

B.

Proposal

C.

Bid

D.

Quote

Buy Now
Questions 29

You are the program manager for your organization and you need to define all of the program resources you'll need for your program. All of the following can be considered a program resource except for which one?

Options:

A.

A forklift

B.

Materials for the installation of a new server

C.

A positive risk response

D.

Gary, an application developer

Buy Now
Questions 30

The risk manager completes risk response planning. The risk manager believes that to effectively address all eventualities, an additional action is required.

What should the program manager do next?

Options:

A.

Transfer a percentage of known risks.

B.

Establish a contingency reserve.

C.

Avoid known critical project threats.

D.

Perform a final review of project scope.

Buy Now
Questions 31

What does RACI stand for?

Options:

A.

Responsible, Account, Confirm, Inform

B.

Responsible, Accountable, Consult, Inform

C.

Roles, Accountable, Confirm, Inform

D.

Roles, Action, Consult, Inform

Buy Now
Questions 32

Identify the term described in the statement given below? "The use of it should be reviewed along with an assessment of their effectiveness. This will aid the program management in determining if risks to the program are being effectively managed. It also provides feedback to the program management on any projects that need to be recovered or terminated."

Options:

A.

Budget

B.

Planned Value

C.

Contingency Reserve

D.

Earned Value

Buy Now
Questions 33

When is the lessons learned document updated?

Options:

A.

At closing phase

B.

At planning phase

C.

Throughout the project lifecycle

D.

At execution phase

Buy Now
Questions 34

A request for proposal (RFP) yields a bid with a better delivery schedule and a lower cost, but originates from a vendor not on the prequalified vendor list. During the final review of the RFPs, the program manager is informed that the new bidder is a relative of the project manager. Although the bid meets all company policies, the program manager is concerned about a conflict of interest.

What should the program manager do?

Options:

A.

Select the best bid from the prequalified vendor list.

B.

Accept the bid from the new vendor and document the decision.

C.

Advise the sponsor of a possible conflict of interest prior to awarding the bid.

D.

Add the new vendor to the prequalified list and replace the project manager.

Buy Now
Questions 35

Company A acquires company B, which leads to a two-year program to integrate the processes and systems. Company B uses a different project management process, and the company’s staff is unhappy about the acquisition. As a result, company B’s project team fails to provide status and cost data in a format that conforms to the program standards.

What should the program manager do first?

Options:

A.

Inform the stakeholders of this issue as soon as possible

B.

Change the program standards, aligning them with the project standards

C.

Work with the reports provided to extract the required information

D.

Remind the project manager of the relevant program standards

Buy Now
Questions 36

Part of your job as the program manager is to coach the project managers on their duties and goals. One of the project managers, Holly, is having trouble discerning the difference between quality assurance and quality control. She understands that she needs both to help you reach the program goals. Which statement best describes quality assurance for a project within your program?

Options:

A.

Quality assurance is an inspection-driven process to keep mistakes out of the project.

B.

Quality assurance is a prevention-driven process to keep mistakes out of the project.

C.

Quality assurance defines quality and sets goals for the project team.

D.

Quality assurance is an organization-wide process to do the work according the organizational goals and metrics.

Buy Now
Questions 37

An organization initiates an innovation program to deliver exceptional performance and benefits. After the program transition plan is in place and the implementation of a benefits sustainment plan starts, the program manager discovers the program may be shut down due to lack of funding.

To ensure continued funding for the program, what should the program manager do next?

Options:

A.

Complete the benefits sustainment plan and update the benefits register

B.

Present a revised ROI to the program sponsors based on the remaining investment

C.

Conduct a cost-benefit analysis to ensure the program sponsors understand the program’s long-term benefits

D.

Review the program business case and the program’s strategic alignment and long-term benefits with the program governance board

Buy Now
Questions 38

You are the program manager for your organization and are working with your team to create the program scope management plan. This plan defines several things in your program except for which one of the following?

Options:

A.

How quality control will be included in the scope

B.

How changes may be allowed to enter the program scope

C.

How the program scope will be created for your program

D.

How the program scope will be controlled

Buy Now
Questions 39

A program is developing a next-generation product line, and one component has been delivered. However, due to a change request, expectations for another component are unmet.

What activity should the program manager perform next?

Options:

A.

Program delivery management

B.

Resource interdependency management

C.

Program performance monitoring and controlling

D.

Benefits sustainment and program transition

Buy Now
Questions 40

You are the program manager for your organization and are working with Tracy, one of the project managers in your program. Tracy is having some trouble understanding the concept of the critical path in her project's network diagram. Which one of the following is the best definition of the critical path?

Options:

A.

It is the path that carries the most risk of project failure.

B.

It is the path that reveals the earliest date the project can finish.

C.

It is the path with the most important activities in the project.

D.

It is the duration of all the project activities if the labor is summed.

Buy Now
Questions 41

Which earned value management formula can help you determine how likely it is that you'll complete the program based on the amount of cash left in the program budget?

Options:

A.

Estimate at completion

B.

Variance at completion

C.

To-complete performance index

D.

Estimate to complete

Buy Now
Questions 42

The new performance financial system is delivered to all business entities on time following a one-year

implementation program. After six months of utilization the global finance department, one of the main beneficiaries of the program, determines that quality and level of granularity of the financial data is not sufficient for them to analyze the key performance indicators (KPIs) defined. Additionally, the global finance department is missing the analytical tools required to understand the causes of discrepancies.

To address these shortcomings, the global finance department submits a request for a follow-up initiative through the process defined by which of the following documents?

Options:

A.

Benefits sustainment plan

B.

Benefits governance plan

C.

Benefits realization report

D.

Benefits transition plan

Buy Now
Questions 43

In which of the following processes is the program charter created?

Options:

A.

Establish Program Financial Framework

B.

Plan Program Scope

C.

Initiate Program

D.

Develop Program Management Plan

Buy Now
Questions 44

You are the program manager for your organization that utilizes vendors from several different organizations. A vendor has submitted an invoice for the work they have completed in your program. You have reviewed the work results and agree with the vendor that their contractual obligation is complete. What should you do next in regard to the vendor's invoice?

Options:

A.

Approve the payment request

B.

Finalize the performance report

C.

Examine the contract

D.

Complete a financial audit of the work

Buy Now
Questions 45

Holly is the program manager for her program. She is creating with her team a plan that will address how the program team will achieve program goals based on who the program will need to interact with in the program. This plan should define all of the people, groups, and other entities the program needs to interact with in order to move the program forward. On what plan is Holly working?

Options:

A.

Stakeholder management plan

B.

Communications management plan

C.

Human resource management plan

D.

Interface management plan

Buy Now
Questions 46

A project manager in your program has estimated the cost of a program to be $145,000. As the project manager's project comes close to completion, the project manager realizes that he has still $27,876 left in his project budget. He decides to add some additional features to the project's deliverables in an effort to use the remaining budget. These additions will add value to the project and the project customer is likely to enjoy these new features. This is an example of what term?

Options:

A.

Gold plating

B.

Errors and omissions

C.

Expert judgment by the project manager

D.

Value added change

Buy Now
Questions 47

Which of the following is not a phase of program life cycle?

Options:

A.

Program Initiation

B.

Program Closure

C.

Program Setup

D.

Program Planning

E.

Delivery of Program Benefits

F.

Pre-program Preparation

Buy Now
Questions 48

Small changes that bypass the organization's change control procedures are called.

Options:

A.

Scope creep

B.

Lag

C.

Scope fault

D.

Gold plating

Buy Now
Questions 49

In the last year, all program phase gate reviews received excellent feedback and exceeded stakeholder expectations. Recently, the customer decides that there is no need to continue phase gate reviews.

What should the program manager do next?

Options:

A.

Ask the stakeholders what they want and proceed with their recommendations.

B.

Agree with the customer and initiate change control procedures.

C.

Continue periodic gate reviews to maintain program effectiveness for benefits realization.

D.

Replace program reviews with periodic communications of the program's status.

Buy Now
Questions 50

You are the program manager for a new software development program. One of the developers has been adding extra fields for information in the software that was not part of the original program scope. While the fields are a good idea, the customer did not ask for the information and some time has been wasted on this work that was not in the program scope. This is an example of which one of the following terms?

Options:

A.

Preventive action

B.

Corrective action

C.

Gold plating

D.

Program scope change

Buy Now
Questions 51

A company hires a program manager to create a healthcare management system. After five months, the program manager identifies an opportunity to integrate an online medical solution, which could provide additional value to the stakeholders. The program sponsor approves the change in scope.

The program manager should ensure that the results obtained by this opportunity are working in tandem with which of the following?

Options:

A.

Critical success factors

B.

Key performance indicators

C.

Benefits management plan

D.

Stakeholder engagement plan

Buy Now
Questions 52

You are the program manager of the NQA Program. In this program you're planning which contract types you'll allow into the program and which ones you will not. One contract type you won't accept is the cost plus percentage of cost contract. Which of the following is a valid reason you would not allow this contract type into your program?

Options:

A.

The contract type requires the vendor to provide a fee for the time invested and the materials used.

B.

The contract type allows the vendor to change the price of the work he's completed.

C.

The contract type allows is the most dangerous for the buyer.

D.

The contract type requires the vendor to provide a fixed price for the work.

Buy Now
Questions 53

Which of the following individual should respond to the risk with the preplanned risk response?

Options:

A.

Key stakeholder

B.

Project manager

C.

Risk owner

D.

Project sponsor

Buy Now
Questions 54

A company CEO issues a mandate to automate a new-client onboarding process to replace manual and paper-based procedures. After the program sponsor and program manager obtain formal acceptance of the program charter, what should be done next?

Options:

A.

Deploy a team to develop the program management plan.

B.

Develop estimates for scope, resources, and cost.

C.

Identify the program management components, and develop the resource management plan.

D.

Review and update the benefits management plan and link it to program outcomes.

Buy Now
Questions 55

Part of program management is to understand how the communication model works in a program. The program manager must be able to effectively communicate with the program team and stakeholders. What component of the communication model is responsible for carrying the message?

Options:

A.

Medium

B.

Sender

C.

Decoder

D.

Encoder

Buy Now
Questions 56

An organization requests that a junior project manager, with no previous experience or training in the industry, take over a complex program component. The program component involves senior subject matter experts and has dependencies with other large projects to deliver key benefits to the organization.

How should the junior project manager respond to this request?

Options:

A.

Accept the assignment, identify the skill gaps, and request training.

B.

Reject the assignment, because of the ethical requirement not to accept work for which the project manager is not qualified.

C.

Accept the assignment as a challenge and an opportunity to acquire new skills and seek advice from a senior project manager.

D.

Reject the assignment because of fear of failure and resulting negative career impact.

Buy Now
Questions 57

Which of the following documents sets the project objectives?

Options:

A.

Project charter

B.

Project schedule

C.

Project scope statement

D.

Project organization chart

Buy Now
Questions 58

A program manager joins a team during its preparation phase.

What should the program manager do to obtain formal sponsor approval to begin the benefits delivery phase?

Options:

A.

Develop the program management plan based on the organization's strategic plan.

B.

Write the program charter, including the program mission statement and stakeholder engagement plan.

C.

Define a high-level program roadmap of milestones and schedules supported by a preliminary estimate.

D.

Identify and document the anticipated program benefits in the benefits management plan.

Buy Now
Questions 59

You are the program manager for your organization and are coaching Bonnie, a project manager, who would like to be a program manager wants to know what a program is. Which one of the following statements best defines what a program is for Bonnie?

Options:

A.

A program is a collection of projects that work together to create one deliverable for the organization

B.

A program is a collection of projects managed to gain benefits for the organization; the organization could not realize the benefits of the project if they were managed independently.

C.

A program is a uniform set of goals that are too large to be managed as one independent project so the project is subdivided into multiple objectives led by multiple project managers and orchestrated by one program manager.

D.

A program is a large collection of projects lead by a single project manager.

Buy Now
Questions 60

You have completed a project for a client at his facility. The project has lasted for 18 months and you have generated many reports, plans, change request forms, and other documents about the project work. What should you do with the project documentation?

Options:

A.

Give it to the client for his information.

B.

Destroy it, as this information is relevant to the client.

C.

Archive it as part of your organization's process assets.

D.

Leave it as is for the client to destroy or archive.

Buy Now
Questions 61

A company CEO meets with key customers to learn how they can be better served. After discovering that

some executive team members disagree with each other, the CEO asks the program management office (PMO) to develop a program to better serve key customers based on their strategic importance to the company’s long-term goals.

What should the program manager do to establish and successfully manage the program’s direction?

Options:

A.

Create a program strategy to obtain the required funding from the portfolio decision team

B.

Develop and foster relationships with stakeholders to improve communication

C.

Conduct stakeholder interviews to address their concerns and expectations

D.

Identify a list of projects, and then assign them suitable project managers

Buy Now
Questions 62

Gina is the program manager for her organization and is reviewing the results of quality control. She would like to create a chart that shows the categories of defects within the program so that she and the program team can address the largest categories in descending order. Which one of the following is the best chart for Gina in this situation?

Options:

A.

Cause and effect chart

B.

Pareto chart

C.

Control chart

D.

Ishikawa chart

Buy Now
Questions 63

You are the program manager for your organization and are working with your program team to create the

program scope. Based on the program requirements you have identified the major deliverables of each phase in your program scope. Management has requested that you plan for cost estimating to happen at each phase of the program before continuing the work. Management may elect to cancel the program at the end of each phase based on past performance of the program. What are the reviews of management called at each phase?

Options:

A.

Phase gate estimates

B.

Murder board

C.

Portfolio review sessions

D.

Kill points

Buy Now
Questions 64

A program completes all component projects and all identified benefits are being delivered. However, the program sponsor is concerned that long-term benefits may not meet organizational performance parameters.

To ensure the realization of long-term benefits, what should the program manager use?

Options:

A.

Benefits register

B.

Benefits sustainment plan

C.

Benefits management plan

D.

Benefits transition plan

Buy Now
Questions 65

Part of your job as the program manager is to coach the project managers on their duties and goals. One of the project managers, Holly, is having trouble discerning the difference between quality assurance and quality control. She understands that she needs both to help you reach the program goals. Which statement best describes quality control for a project within your program?

Options:

A.

Quality control is a management-driven effort to plan the work properly so the work is done according to plan.

B.

Quality control is an inspection-driven process to keep mistakes out of the customers' hands.

C.

Quality control is a management-driven policy to do the work correctly the first time.

D.

Quality control is an inspection-driven process to prove the existence of the requirements.

Buy Now
Questions 66

A program manager for the construction of an international event venue that will impact the local community needs to determine the best approach for communications. One of the conditions of the program is that after the event takes place, a park will be built for the community’s use.

What should the program manager do to ensure community support?

Options:

A.

Review the scope with the program sponsor and community representatives

B.

Organize an advocacy group and facilitate community engagement

C.

Negotiate the program scope with community representatives

D.

Ensure community representatives are part of the steering committee

Buy Now
Questions 67

What should a program manager do when a scope change has been approved that will drastically affect the program costs assuming that the costs will be added to the program budget?

Options:

A.

Adjust the cost baseline

B.

Communicate cost of the change to all stakeholders

C.

Adjust the quality baseline

D.

Communicate the change to all stakeholders

Buy Now
Questions 68

A program delivers incremental benefits, but is far from closure. The company completes an acquisition and defines new strategic objectives.

What should the program manager do next?

Options:

A.

Evaluate the impact of the new strategic objectives through a change request.

B.

Integrate the new acquisition into the program to include the new strategic objectives.

C.

Assess the impact of the new acquisition on the contract management plan.

D.

Review the benefits management plan to assess the continued validity of the program.

Buy Now
Questions 69

A program manager evaluates conflicting stakeholder demands associated with cost, schedule, and intended benefits. The implementation team has a strong interest in cost and schedule, and a limited interest in the benefits being produced. The client is only focused on benefits.

Which of the following actions should the program manager take?

Options:

A.

Focus on the internal stakeholders to ensure cost and schedule objectives are achieved.

B.

Balance stakeholder needs through the use of trade-offs among the stakeholder groups.

C.

Focus on the external stakeholders to ensure the intended benefits are achieved.

D.

Conduct a stakeholder meeting to allow everyone to state their priorities.

Buy Now
Questions 70

You are the program manager of the NHQ Program for your organization. Your program is nearing the completion of one of its major phases and there are several resources that should be released at this time. What program management plan will guide you to release of the program resources and transfer the resources and benefits to operations within the organization?

Options:

A.

Resource management plan

B.

Transition plan

C.

Communications management plan

D.

Benefits management plan

Buy Now
Questions 71

Hans is the program manager for his organization. His current project has seven constituent projects that each will create deliverables for the organization. Who is responsible for the project deliverables in this scenario?

Options:

A.

Project managers

B.

Hans

C.

Program director

D.

Hans and each project manager

Buy Now
Questions 72

You are the program manager for your organization and you're dealing with several issues about the materials used in the program. Right now, the issues have been assigned to issue owners for resolution in ten days. In the interim, what should you do with the issues?

Options:

A.

Nothing - the issue owners will manage all concerns with the issues.

B.

Record the issues in the issue register.

C.

Communicate the issue status with the program sponsor.

D.

Document the issues in the risk register.

Buy Now
Questions 73

Which of the following documents describes the details for each component in the WBS?

Options:

A.

WBS detail

B.

Risk register

C.

WBS dictionary

D.

Project charter

Buy Now
Questions 74

During the execution phase of a program, a stakeholder complains to the program manager that they did not receive critical communications about one of the component projects.

What should the program manager do to address the situation?

Options:

A.

Review and update the detailed stakeholder list.

B.

Review and update the stakeholder engagement plan.

C.

Execute the component project's communications management plan.

D.

Update the risk register.

Buy Now
Questions 75

A program manager is concerned because several change requests in a component project are causing delays to the program's work package milestones. There are insufficient skilled resources within the component project to complete both the change requests and the milestone tasks.

What should the program manager do next to address this risk?

Options:

A.

Prioritize which resources are critical to the project based on an impact analysis of the critical change requests and update the program roadmap.

B.

Prioritize which change requests are critical to the project based on an impact analysis, resource only critical change requests until overdue milestones are achieved, and update the risk register.

C.

Mandate that no component project change requests will be processed until overdue milestones have been completed and update the risk register to reflect this.

D.

Add the lack of skilled resources to facilitate the large number of change requests to the issue log.

Buy Now
Questions 76

What would prevent a program manager from completing program closure once a program has been completed?

Options:

A.

Failure to update the financial management plan

B.

Failure to update the benefits register

C.

Incomplete realization of all program benefits

D.

Failure to obtain program steering committee approval

Buy Now
Questions 77

A program manager assigns project managers to five component projects and continues to develop the program team.

Which of the following represents the program manager's strategy?

Options:

A.

Rotate the responsibility for risk assessment among the program components

B.

Coach the project managers to manage project resources

C.

Cross-train the project managers to share expertise

D.

Prepare the project managers to assume larger roles with more responsibility

Buy Now
Questions 78

The project manager of project A develops a communications management plan. The project manager of project B is new and is uncertain how to develop appropriate communications for the company's staff.

What should the program manager do to ensure communications on the component projects are consistent?

Options:

A.

Request a more experienced project manager to work on project B.

B.

Create a program communications management plan across all component projects.

C.

Direct all projects to use project A's communications management plan as a template.

D.

Rework the communications management plans for all projects to be consistent.

Buy Now
Questions 79

A program manager is appointed to manage a new program. The organization's leadership has specified a list of benefits that the program should deliver and has requested that the program manager determine when incremental benefits can be realized.

What should the program manager do first?

Options:

A.

Develop the benefits sustainment plan.

B.

Develop the program management plan.

C.

Develop the program roadmap.

D.

Develop the component project schedules.

Buy Now
Questions 80

Which of the following risk identification techniques is described in the statement below?

"It is used to gather information where participants don't know each other nor do they have to be present at the same location."

Options:

A.

Brainstorming

B.

Delphi

C.

SWOT analysis

D.

Assumptions analysis

Buy Now
Questions 81

Joan is the program manager for her organization. Throughout the program life cycle there will be several elements, resources, and benefits that can be transitioned from her program to the organization. What document defines how these things can be transferred from the program to the organization?

Options:

A.

Operational transfer alliance plan

B.

Program milestone list

C.

Program transition agreement

D.

Program scope statement

Buy Now
Questions 82

You are the program manager for your organization. Your current program has a budget at completion of

$3,450,000 and is expected to last two years. The program is currently 30 percent complete and has spent ten percent more than what it should have to arrive at this point in the program schedule. Based on this information, what is estimate at completion (EAC) for this program?

Options:

A.

$2,656,500

B.

There is not enough information to know. C. $3,795,000

C.

$1,035,000

Buy Now
Questions 83

A multiyear program is ready to conclude. It has achieved all business objectives and is delivering its intended benefits. However, the program sponsor is not willing to sign the formal program closure acceptance document and the program continues to incur operational costs.

What should the program manager do next?

Options:

A.

Ask the finance department to increase the program budget

B.

Escalate the issue to the program governance board

C.

Ask key stakeholders to influence the program sponsor

D.

Direct component project managers to archive all relevant project documents

Buy Now
Questions 84

You are the program manager for your organization. Your current program is to create a new recreational facility in your city. Franklin, the Chief Executive Officer, is concerned about meeting all of the financial and schedule requirements of the proposed program. Martina, the mayor of your town, wants to make certain the program meets all safety requirements and building codes. Your supervisor, Mary Ann, is the Program Director, and she is concerned about the start date of your program. Another stakeholder, Hal, is worried that your resources may be spread thin on the program as some of the resources are on multiple projects in your program.

To whom will you report to in this program?

Options:

A.

Franklin

B.

Martina

C.

Hal

D.

Mary Ann

Buy Now
Questions 85

The program manager leads a medical billing system integration program for company A, a health services provider. Company A acquires smaller company X, which delivers health services strategically aligned with company A.

Company X uses a different billing approach than company A. Company A's chief information officer (CIO) seeks counsel on which solution would be the better option moving forward, requesting the program manager's assistance.

How should the program manager respond to the CIO's request?

Options:

A.

Document the resources required to implement the recommended solution and demonstrate how this solution will save the company money.

B.

Find similar examples of the preferred approach and ask the project teams to document why the preferred approach is better

C.

Gather the costs and benefits associated with each option and recommend the appropriate solution defining why the selected approach is better.

D.

Conduct a thorough stakeholder analysis and develop a program management plan to implement the appropriate solution for both companies.

Buy Now
Questions 86

Your program has a budget at completion of $1,550,000 and is expected to last one year.

Currently your program is 45 percent complete and has spent $725,000. According to the program schedule you are actually to be fifty percent complete by this time, but due to some vendor delays your program is running just a bit late. Based on this information which is performing worse, the cost or schedule?

Options:

A.

The schedule is performing worse because the SPI is .90

B.

The cost is performing worse because the EAC is $1,611,111.

C.

The schedule is performing worse because the SV is -$27,500.

D.

The cost is performing worse because the CPI is .96.

Buy Now
Questions 87

You are the program manager for the NHQ Program. Your program has a budget of

$4,500,000 and has lasted for two years. Your program has just completed its final

deliverable and you're completing the final program closure processes. What document must the program customer must now sign as part of program closure?

Options:

A.

The customer must now sign the program scope.

B.

The customer must now sign the payment for the program work.

C.

The customer must now sign the certificate of program closure.

D.

The customer must now sign the operational transfer agreement.

Buy Now
Questions 88

A program manager building the world’s largest cruise ship is resolving the conflict between the two main sponsors who cannot agree on the number of food and beverage outlets to have onboard. What should the program manager do?

Options:

A.

Finalize the business case and market analysis with the core program team and present the findings to the chief executive officer for approval.

B.

Work with the core program team to conduct a market analysis and make the decision based on the best return on investment.

C.

Arrange a meeting with both sponsors and the steering committee to present the market analysis and work through the conflict.

D.

Engage the program stakeholders, present the market analysis and findings to facilitate the decision on the best option.

Buy Now
Questions 89

You are the program manager for your organization and your team has reported on a new issue among your program stakeholders. You want to address this issue as soon as possible, but it will need to be studied and reviewed. You recommend that Shirley, one of your program team members, study the issue and present a few solutions in a week's time. What else should you do with the issue?

Options:

A.

Determine the time and cost of researching the issue for resolution.

B.

Record the issue in the issue log.

C.

Document the issue in the lessons learned.

D.

Communicate with the stakeholders that you are addressing the issue.

Buy Now
Questions 90

As a program manager you must also understand the project management lifecycle and the project lifecycle. What is the difference between the two?

Options:

A.

The project management lifecycle and the project lifecycle are the same thing.

B.

The project management lifecycle is comprised of the phases initiating, planning, executing, monitoring and controlling, and closing. The project lifecycle is comprised of phases that are unique to the project work.

C.

The project management lifecycle is unique to each project while the project lifecycle is universal to all projects.

D.

The project management lifecycle is universal to all projects and the project lifecycle is unique to each project.

Buy Now
Questions 91

A program manager concurrently implements a software program at four client locations. The client’s objective is to maintain quality while shortening the software implementation timeline.

What key elements should be included in the benefits register to achieve this goal?

Options:

A.

Plans for tracking and communicating risks associated with the program

B.

Plans for conducting program quality assurance and control on a regular basis

C.

Plans for program schedule control to meet the shorter timeline

D.

Plans for defining metrics and key performance indicators (KPIs), and procedures to measure benefits.

Buy Now
Questions 92

Your program has been selected and its program charter is now being created. The program charter defines all of the following characteristics except for which one?

Options:

A.

Program constraints

B.

Program scope

C.

High-level objectives for the program

D.

Project scope statement for all projects within the program

Buy Now
Questions 93

You are the program manager for your organization. Your program has a budget of $750,000 and is expected to last one year. The program is currently 30 percent complete and has spent $245,000. The program is supposed to be 40 percent at this time. What is the schedule performance index (SPI) for this program?

Options:

A.

Negative ten percent B. .75

B.

$300,000 D. $225,000

Buy Now
Questions 94

A component is scheduled to close at the end of the week.

What should the program manager verify prior to allowing the component to close?

Options:

A.

The component has released resources to meet program objectives

B.

The component has met the quality requirements to meet program objectives

C.

The component has met the schedule requirements to meet program objectives

D.

The component has met the benefits realization criteria to meet program objectives

Buy Now
Questions 95

You are the program manager of the HNG Program. This program has a budget at completion of $2,345,900 and is expected to last two years. The program is currently 30 percent complete and you have spent

$789,000. The program is supposed to be 35 percent complete but do to some delays you're slightly behind schedule. Based on this information, how many pennies is the program losing per dollar invested in the program work?

Options:

A.

17

B.

11

C.

15

D.

14

Buy Now
Questions 96

A company is releasing a new product geared toward a specific geographic area. The program manager has

received the program objectives and developed the program roadmap, which consists of six program components. Approval from the program governance board has been obtained.

What is the program manager’s next step?

Options:

A.

Assign project managers and resources

B.

Classify the program’s benefits

C.

Identify the program sponsor and program stakeholders

D.

Develop the program business case

Buy Now
Questions 97

If a program has a budget of completion of $550,000, is 25 percent complete, and has spent $135,000 what is the cost variance (CV)?

Options:

A.

.99

B.

-$2,500

C.

$2,500

D.

1.02

Buy Now
Questions 98

You are the program manager for your organization. When a project in your program is completed, who will need to sign the certificate of completion?

Options:

A.

The project manager

B.

The program customer

C.

The program stakeholders

D.

The project management team

Buy Now
Questions 99

Which of the following is responsible to sign off on the closure documents of a project?

Options:

A.

Project team members

B.

Project Manager

C.

End user

D.

Sponsor

Buy Now
Questions 100

An organization must accelerate a product to market. The program manager completes the preliminary program steps and holds a kick-off meeting. Project managers submit their preliminary schedules for review.

What should the program manager do next?

Options:

A.

Assign resources to the schedule and report the revised delivery date to the project managers.

B.

Work with the project managers to refine the project schedules and deliverables to align with the program milestones.

C.

Revise the project schedules to meet the program schedule and communicate to stakeholders.

D.

Integrate the project schedules into the program schedule and report the revised delivery date to the project managers.

Buy Now
Questions 101

A program stakeholder is concerned about information they receive about a project. Who is responsible for reviewing the communications management plan to assure adequate information is provided to the stakeholder?

Options:

A.

Program sponsor

B.

Communications manager

C.

Project manager

D.

Program manager

Buy Now
Questions 102

The program manager completed the program's benefits analysis and planning activities.

What will this ensure for the program?

Options:

A.

Information necessary to establish key benefit performance indicators

B.

A transition plan to facilitate the ongoing realization of benefits

C.

A plan to monitor performance due to operational, financial, and benefits changes

D.

A benefits management plan to guide the work through the remainder of the program

Buy Now
Questions 103

An R&D group director approves a major program’s charter. Although the director has a high level of understanding of the program’s scope, they are unsure of how the program manager can be successful in delivering the program’s commitments.

What should the program manager do to align stakeholders with planning and monitoring the program’s progress?

Options:

A.

Establish high-level program milestones

B.

Develop an accountability matrix, and assign program roles and responsibilities

C.

Generate a supplier management plan to identify external stakeholders

D.

Create a communications management plan, and establish reporting formats

Buy Now
Questions 104

A company's marketing department fails an internal compliance audit. To comply with the auditor's remediation plan, the legal department mandates that a content management system (CMS) be implemented. After initiating the program for CMS implementation, the program manager discovers that the marketing department has already preselected which CMS technology will be implemented.

What should the program manager do to ensure the success of the program?

Options:

A.

Meet with the vice president of purchasing to discuss the risks associated with preselecting a solution before the requirements have been gathered

B.

Host a kick-off meeting; request preliminary requirements from the marketing department; conduct a design session; present the steering committee with a solution that meets the requirements; and meet with interested vendors

C.

Ask a senior marketing executive to act as the program sponsor and participate on the steering committee; require steering committee representation from the IT, legal, and other key departments; validate that the chosen solution meets the requirements

D.

Initiate the program and begin a formal request for proposal (RFP) to validate the chosen solution and gain the confidence of the legal department

Buy Now
Questions 105

A program is in its last year of execution. The program manager will receive a performance bonus if executive leadership and the program steering committee determine that the program is a success.

How can the program manager justify receiving a performance bonus upon program closure?

Options:

A.

Update the business case analysis document indicating how each goal was attained.

B.

Prepare a financial framework to show effective financial management and alignment with profit metrics.

C.

Provide a report using the benefits management plan to demonstrate overall benefits realization.

D.

Conduct a customer satisfaction survey to show program success.

Buy Now
Questions 106

Andy is the program manager of the HQN Program. This program is nearing its completion and there is still

$25,000 left in the program budget. Andy has asked the program team to identify some extra deliverables that can be included in the program scope to improve the program deliverable but also to use all of the funds in the budget. What term is assigned to the actions that Andy is trying to do in this instance?

Options:

A.

Value-added change requests

B.

Zero based budgeting

C.

Integrated change control

D.

Gold plating

Buy Now
Questions 107

A program manager needs to establish direction and identify the essential aspects of a program. In addition, they must ensure that the context and framework of the program are properly defined, assessed, and documented.

Which document will be created to support this activity?

Options:

A.

Program resource management plan

B.

Program management plan

C.

Program master schedule

D.

Program scope statement

Buy Now
Questions 108

A program manager has four projects pending approval. Senior management asks the program manager to identify a project for potential elimination based on the return on investment. The program manager has the following information to guide and support the decision:

Which project should the program manager select to be cancelled?

Options:

A.

Project A

B.

Project B

C.

Project C

D.

Project D

Buy Now
Questions 109

Olive is the program manager for her organization. She has created a request for proposal for a large portion of her program. In this work to be procured she has set several requirements for the vendors to participate. The chief among these requirements is a vendor must have at least four licensed electricians in his team. This requirement for four licensed electricians is an example of which one of the following terms?

Options:

A.

Screening system

B.

Scoring model

C.

Vendor analysis requirements

D.

Evaluation criteria

Buy Now
Questions 110

Mary Anne is the program manager for her organization. In her program there are six projects. One of the projects in her program has been performing well. It is on schedule and has no cost or schedule variances. Mary Anne has decided, however, that her program needs to be terminated. Which one of the following is a likely reason why the project should be terminated?

Options:

A.

The program scope has changed.

B.

The scope is not being met as planned due to scope creep.

C.

The project resources are not completing their project tasks as assigned.

D.

The project scope has changed from the original intent of the project

Buy Now
Questions 111

You are trying to determine if you should buy or build a solution for your program. If you build the solution it'll cost you $45,000 to create and $7,000 per month to support. A vendor reports that they can create the solution for you for $1,000 but you'll have to pay them $9,000 per month to support the solution. Should you buy or build this solution?

Options:

A.

Build the solution if you'll use it longer than 22 months.

B.

Buy the solution if you'll use it longer than 24 months.

C.

Buy the solution if you'll use it longer than 22 months.

D.

Build the solution if you'll use it longer than 25 months.

Buy Now
Questions 112

A program manager, who reports to a company's CIO, is responsible for managing a strategic initiative program. During a program review meeting, the CIO informs the program manager about potential budget cuts that would impact program resources, and urges the program manager to begin delivering benefits more quickly to continue the program.

What should the program manager do first?

Options:

A.

Update the benefits management plan, and send it to stakeholders for review.

B.

Document the impact on the program, then present the findings to the steering committee to determine next steps.

C.

Conduct a risk assessment associated with an accelerated schedule, update the risk register, and request steering committee approval.

D.

Revise the program schedule to adapt to an accelerated delivery of benefits, and present it to the steering committee for approval.

Buy Now
Questions 113

During the last steering committee meeting, a program manager presented the benefits register to the program governance board. Since the intended benefits of the program were realized, the program manager was asked to transition the program into operations.

At this stage, what is expected during the post-review session organized by the program manager?

Options:

A.

Earned value (EV) report

B.

Customer sign-off

C.

Benefits register updates

D.

Feedback and lessons learned

Buy Now
Questions 114

A large program consists of several component projects and six project managers. The program governance board requests that all components within the program undergo user acceptance testing before being released to the production environment.

Where should the program manager document this?

Options:

A.

Program governance plan

B.

Program requirements

C.

Component test plan and test cases

D.

Program quality management plan

Buy Now
Questions 115

Which project management meeting allows stakeholders to meet one another and to learn about the project?

Options:

A.

Project scope review

B.

Project authorization meeting

C.

Project status meeting

D.

Project kick-off meeting

Buy Now
Questions 116

Which of the following documents contain a list of all problems, unfavorable events, or situations that occurred so far in the program?

Options:

A.

Program charter

B.

Program risk register

C.

Program issue register

D.

Program scope statement

Buy Now
Questions 117

After meeting with the program sponsor and stakeholders, the program manager is asked by the sponsor to accelerate the program to replace two legacy financial systems. The legacy systems are at risk of premature failure.

What should the program manager do next?

Options:

A.

Accelerate the projects and components of the program that replace the two legacy systems.

B.

Analyze the impact of accelerating the program, and present the pros and cons to the program sponsor.

C.

Identify the parts of the program that need to be accelerated and, if it is cost effective and increases benefits realization, implement the change.

D.

Create several "what-if" scenarios of alternatives to present to the program sponsor.

Buy Now
Questions 118

You are the program manager for your organization. Part of your role as the program manager is to train John, a new program manager, on the program processes within a program. John is confused as to when the program team can be acquired in the program management lifecycle. When will the program team be acquired for a program?

Options:

A.

Planning

B.

Execution

C.

Monitoring and controlling

D.

Initiation

Buy Now
Questions 119

An experienced program manager is leading a development program in a new company. While reviewing company procedures for formulating a program, they discover there is no company practice for managing key suppliers.

What should the program manager do first to obtain program approval?

Options:

A.

Prepare the stakeholder engagement plan for approval by the program steering committee.

B.

Analyze the business environment to identify key stakeholders, and then perform a stakeholder analysis.

C.

Conduct a brainstorming session with the program team to identify and analyze external stakeholders.

D.

Create a project-level stakeholder analysis, and then perform a high-level program stakeholder analysis.

Buy Now
Questions 120

Tom is the program manager for his organization. He has to balance the resources he'll be using in the program with the demand for operations to use the same resources. What program document can Tom reference to determine the availability of certain program resources, such as application developers, engineers, and technical writers?

Options:

A.

Staffing management plan

B.

Resource calendar

C.

Functional management plan

D.

The resource pool description

Buy Now
Questions 121

You are a program manager of a program. You are required to compile performance data of your program. These data will be sent to relevant stakeholders. You are reviewing the status reports of all projects including the costs, schedule, scope, risks, and other performance data.

In which of the following processes are you working on?

Options:

A.

Plan Communication

B.

Distribute Information

C.

Report Program Performance

D.

Monitor and Control Program Performance

Buy Now
Questions 122

You are working with Sam, a project manager on one of the projects within your program. Sam doesn't understand all of the rules and procedures that he's required to do as a project manager in your program. What are the rules and procedures called in project that Sam must abide by?

Options:

A.

Project governance

B.

Process procedures

C.

Enterprise environmental factors

D.

Program governance

Buy Now
Questions 123

A program includes the development and shipping of 12 million product units over the next year. However, one program supplier has a history of overestimating its planned volume, which puts the product launch at risk.

What should the program manager do to monitor and control the supplier?

Options:

A.

Use expert judgment, and update the program procurement plan.

B.

Seek stakeholder approval of program procurement management activities.

C.

Examine performance reports, audits, and inspections.

D.

Review proposal evaluation criteria, risk analyses, and mitigation strategies.

Buy Now
Questions 124

What is the primary purpose of a project kick-off meeting?

Options:

A.

To establish why the project has been initiated.

B.

To establish the direction and purpose of the project management plan.

C.

To establish the roles and responsibilities of the stakeholders.

D.

To establish who the project manager and project sponsor are for the project.

Buy Now
Questions 125

XYZ Company hires you to make its transitioning procedure more effective in meeting close-out requirements. You review XYZ’s transitioning procedures to eliminate any that do not belong in the close-out phase.

Which of the following procedures should you remove?

Options:

A.

Managing the transition from the “As-Is” state to the “To-Be” or Target State

B.

Reviewing the status of benefits with the stakeholders and program sponsor

C.

Managing any required transition to operations

D.

Documenting lessons learned in the organizational database

Buy Now
Questions 126

You are the program manager for your organization. Your program has a budget of $750,000 and is expected to last one year. The program is currently 30 percent complete and has spent $245,000. The program is supposed to be 40 percent at this time. What is the cost performance index for this program?

Options:

A.

.83

B.

-$20,000 C. .91

C.

Negative ten percent

Buy Now
Questions 127

In your program you must adhere to Six Sigma as part of your organization's enterprise environmental factors. There is terminology, reports, and measurements that you are expected to use as part of your program. Six Sigma is an example of what program management process?

Options:

A.

Quality control

B.

Process improvement

C.

Scope verification

D.

Quality assurance

Buy Now
Questions 128

What document should you provide to the vendors if you're only interested for a set fee for their materials?

Options:

A.

IFB

B.

RFP

C.

RFI

D.

SOW

Buy Now
Questions 129

You are the program manager for your organization and management has asked you to be certain to finalize the lessons learned documentation for your program. When will the lessons learned documentation be created?

Options:

A.

Lessons learned are in program execution.

B.

Lessons learned are created at each program deliverable.

C.

Lessons learned are created during the program closure.

D.

Lessons learned are created during the program archive.

Buy Now
Questions 130

An organization is embarking on a new program aligned with its strategic objectives. The new program has a high level of risk due to the rapidly changing technical landscape in which the organization operates. The organization has mature program management capabilities, as measured by its resources, intellectual assets, and management processes.

Given the organization’s history of delivering successful programs, what should the program manager do as part of the planning process?

Options:

A.

Interview the program managers and stakeholders of previous programs to learn from their experiences.

B.

Review the organization’s strategic objectives, risk tolerance, and compliance processes, which may provide knowledge about past programs.

C.

Consult the repository developed as part of the organization’s knowledge management initiative to capture best practices and lessons learned.

D.

Hire independent industry specialists and subject matter experts (SMEs) to provide additional information about market trends and uncertainties in the external environment.

Buy Now
Questions 131

You are the program manager for the JQN Program in your organization. There have been some delays in your schedule and you're about to perform some schedule control activities. Which one of the following will not help you as you perform schedule control?

Options:

A.

Change requests

B.

Performance reports

C.

Forecasts

D.

Earned value management

Buy Now
Questions 132

A biometrics firm has a facial recognition program with multiple components and project managers. The

project manager from the mobile device division escalates a vendor-related risk to the program manager. After assessing the risk, the program manager determines that this risk may impact other projects within the program. However, this risk has a low degree of impact and probability of occurring.

What should the program manager do first?

Options:

A.

Obtain a risk reserve from the executive sponsor, and execute a contingency plan.

B.

Communicate the risk to all project managers to manage at the component level.

C.

Add the risk details and analysis to the program risk register.

D.

Brainstorm with the project manager to develop an appropriate risk response.

Buy Now
Questions 133

What document asks the seller to provide your project with a detailed description of a project solution along with a price to complete the project work?

Options:

A.

Proposal

B.

RFP

C.

Bid

D.

Quote

Buy Now
Questions 134

You are the program manager of the GHY Program in your organization. It has come to your attention that some of the project managers in your program are adding time to each project activity in an effort to pad their durations in case some event happens in their project that will cause delays. What principle should you share with these project managers that counterattack the concept of padding activities with additional time?

Options:

A.

Parkinson's Law

B.

Law of Diminishing Returns

C.

80/20 Law

D.

Pareto's Law

Buy Now
Questions 135

Molly is the program manager for her organization and she is creating a program plan that defines the benefits of the program and how her program and team will create the benefits for the organization. What plan is Molly creating in this scenario?

Options:

A.

Quality management plan

B.

Business case

C.

Program management plan

D.

Benefits management plan

Buy Now
Exam Code: PgMP
Exam Name: Program Management Professional (PgMP)
Last Update: May 15, 2024
Questions: 452
$64  $159.99
$48  $119.99
$40  $99.99
buy now PgMP