Weekend Sale - Limited Time 65% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: 65percent

Welcome To DumpsPedia

Prince2-Foundation Sample Questions Answers

Questions 4

Which principle should ensure that a project remains aligned with the objectives of the investing organizations?

Options:

A.

Focus on products

B.

Manage by exception

C.

Tailor to suit the project

D.

Ensure continued business justification

Buy Now
Questions 5

Which plan is used to organize and control the work when executing a work package?

Options:

A.

team plan

B.

A stage plan

C.

A project plan,

D.

An exception plan

Buy Now
Questions 6

Which is a description of a purpose of the communication management approach?

Options:

A.

To document for stakeholders the future business required to meet project objectives

B.

To document how the project team should control its interactions with stakeholders

C.

To document how to use financial incentives to motivate project team members

D.

To document the responsibilities of project team members for testing whether products are acceptable to users

Buy Now
Questions 7

When should the project baseline be updated in order ta meet the purpose of the 'issues' practice?

Options:

A.

When a request for change is recorded on the issue register

B.

When a business opportunity has been recognized

C.

When the project manager receives a request for change

D.

When a change has been approved by the change authority

Buy Now
Questions 8

Which action contributes to achieving the ‘ensure continued business justification’ principle?

Options:

A.

Producing separate business cases for each customer and supplier involved in the project

B.

Defining the products that the project must produce in order to control change effectively

C.

Establishing limits of authority on the project based on defined tolerances

D.

Adapting PRINCEZ to the scale of investment and the delivery approach

Buy Now
Questions 9

When does the ‘directing a project’ process start?

Options:

A.

When the project manager submits the project brief for approval

B.

When the request to authorize a project is received

C.

After the project has been authorized by the business layer

D.

After the project mandate has been received

Buy Now
Questions 10

Which is an internal factor to consider when tailoring PRINCE??

Options:

A.

The safety legislation

B.

The environmental standards

C.

The industry's regulations

D.

The organization's procedures

Buy Now
Questions 11

Which role is responsible for focusing on the safety and well-being of the project team?

Options:

A.

Project executive

B.

Project board

C.

Project manager

D.

Team manager

Buy Now
Questions 12

Identify the missing word in the following sentence.

An (?) is the result of change, normally affecting real-world behavior and circumstances:

Options:

A.

outcome

B.

exception

C.

output

D.

off-specification

Buy Now
Questions 13

The project manager has proposed that a request for change be implemented, but the change authority has asked for more information.

In which step of the ‘issue management technique should the change authority request this information?

Options:

A.

Deciding on changes

B.

Implementing changes

C.

Assessing issues

D.

Capturing issues

Buy Now
Questions 14

Which plan should only be produced if the project is large and complex enough?

Options:

A.

Project plan

B.

Stags plan

C.

Team plan

D.

Exception plan

Buy Now
Questions 15

Which term is defined as the measurable threshold to represent the tolerable range of outcomes for each objective ‘at risk’?

Options:

A.

Risk tolerance

B.

Risk appetite

C.

Risk event

D.

Risk effect

Buy Now
Questions 16

The project management team heeds t document quality antral events, such as testing

According to the guidance for effective quality management, haw should the events be documented?

Options:

A.

In stage of team plans to allow mare accurate scheduling

B.

As quality tolerances in product descriptions

C.

As acceptance criteria in the project product description

D.

In the quality management approach to plan the testing

Buy Now
Questions 17

What is a temporary organization that is treated for the purpose of delivering Business Products according an-agrees business casa?

Options:

A.

A project

B.

A baselined product

C.

The project scope

D.

The business

Buy Now
Questions 18

What is a description of a leadership activity within a project?

Options:

A.

Understanding and working with different departments outside of the project team

B.

Agreeing a work package with a team manager to deliver products using specific tools

C.

Ensuring that a co-located project team uses the agreed communication methods

D.

Creating a stage plan and product descriptions for the products to be created in the next stage

Buy Now
Questions 19

Which action should the project manager take when reviewing progress to assess the 'health' of a stage?

Options:

A.

Capture lessons that may assist in the monitoring and control of this project

B.

Review the quality of the relationships in the organizational

C.

Increase the frequency of event-driven controls to monitor stage progress

D.

Identify whether issues are resolved in a timely manner or left unmanaged

Buy Now
Questions 20

Which TWO are objectives of the 'managing a stage boundary" process?

1. To confirm to the project board that there are no products outstanding for the stage

2. To ensure that expectations are managed via accurate reporting to the project manager during a stage

3. To ensure that the project management team is not distracted by delivering additional products during the stage

4. To request the project board to approve work to start on the next stage

Options:

A.

1 and 2

B.

2 and 3

C.

3 and 4

D.

1 and 4

Buy Now
Questions 21

Which member of the project management team should secure funding for the project before the project stars?

Options:

A.

Project executive

B.

Project manager

C.

Senior user

D.

senior supplier

Buy Now
Questions 22

Which feature of a stage plan suggests that a project is in danger of scope creep?

Options:

A.

Stage plans are prepared by the project manager as the stage comes to an end

B.

Products identified in a stage plan cannot be traced back to the project plan

C.

The team delivering the stage plan includes staff from different parts of an organization

D.

it is not possible to implement remedial actions for an exception by updating a stage plan

Buy Now
Questions 23

What is a description of a leadership activity within a project?

Options:

A.

Understanding and working with different departments outside of the project team

B.

Agreeing a work package with a tear manager to deliver products using specific tools

C.

Ensuring that a co-located project team uses the agreed communication methods

D.

Creating a stage plan and product descriptions for the products to be created in the next stage

Buy Now
Questions 24

According to the guidance for effective quality management, when should the requirements for a product be captured?

Options:

A.

When the project team realizes that the product is needed

B.

When the project team needs to test the product

C.

When the project team needs to know whether the product has been approved

D.

When the project team needs to know how the product will be delivered

Buy Now
Questions 25

Why is change management important in a project?

Options:

A.

It provides clarity on how the culture of an organization needs to adapt over time

B.

It provides processes and management products to use when requesting a change

C.

It provides confidence that the project can meet is objectives and has continued business Justification

D.

It provides a controlled and bidirectional flow of information to key Influencers

Buy Now
Questions 26

Which is a benefit of using PRINCE2?

Options:

A.

It promotes consistency of project work and the ability to reuse project assets.

B.

It includes techniques for critical path analysis and earned value analysis

C.

It enables a project manager to be accountable for the success of a project

D.

It prevents any changes once the scope of a project has been agreed

Buy Now
Questions 27

Which is a definition of management?

Options:

A.

Directing the execution of project tasks as agreed for the project

B.

Away of working that characterises a group of people

C.

Being accountable to the business for the success of the project

D.

The party responsible for commissioning the project

Buy Now
Questions 28

As part of the 'business case management’ technique, how is the business case maintained during the project lifecycle?

Options:

A.

By linking the outcomes and benefits to the business objectives included in the business case

B.

By updating the business case during each management stage, as actual costs are incurred

C.

By providing a robust justification for the entire project in a detailed business case

D.

By justifying to the project board that the project should be initiated

Buy Now
Questions 29

in the ‘starting up a project’ process, what is the PRINCE? name for a ‘request for proposal’ received by an external supplier?

Options:

A.

Project mandate

B.

Project brief

C.

Work package

D.

Project approach

Buy Now
Questions 30

Which process defines the work to deliver the major products ensuring that an organization uses its resources effectively?

Options:

A.

Initiating a project

B.

Starting up a project

C.

Controlling a stage

D.

Managing product delivery

Buy Now
Questions 31

Which describes a management activity within a project?

Options:

A.

Encouraging a project team to continue working on a particularly challenging product

B.

Discussing project objectives with key stakeholders during a requirements gathering workshop

C.

Agreeing a work package with a team manager to deliver products within agreed tolerances

D.

Seeking feedback from team members to ensure they are still aligned to the project's objectives

Buy Now
Questions 32

Which term is defined as being achieved as a result of the activities undertaken to facilitate the change?

Options:

A.

Outcome

B.

Benefit

C.

output

D.

Request for change

Buy Now
Questions 33

In which step of the risk management’ technique should the organization's environment be considered?

Options:

A.

Identity

B.

Assess

C.

Plan

D.

Implement

Buy Now
Questions 34

The benefits Management approach has been reviewed by the project board to ensure there are sufficient benefit reviews after the project has closed.

Which principle is the project board applying?

Options:

A.

Manage by exception

B.

Manage by stages

C.

Ensure continued business Justification

D.

Focus on products

Buy Now
Questions 35

What 15the purpose of the ‘progress! practice?

Options:

A.

To review whether the use of the products is likely to lead to the expected benefits

B.

To define the roles and responsibilities for monitoring progress

C.

To measure actual achievements against the planned time and cost targets for the project

D.

To control events that could have a positive or negative effect on project objectives

Buy Now
Questions 36

Who is responsible for documenting any tailoring of the business case theme?

Options:

A.

Executive

B.

Business project assurance

C.

Project manager

D.

Corporate management

Buy Now
Questions 37

During the ‘initiating a project’ process, who specifies the required level of management control?

Options:

A.

Corporate, programme management or customer

B.

Project board

C.

Project manager

D.

Project assurance

Buy Now
Questions 38

Which is a purpose of the 'controlling a stage' process?

Options:

A.

To review the success of the project at the end of a management stage

B.

To agree work package acceptance and delivery requirements

C.

To produce regular highlight reports for the project board

D.

To re-plan the current stage and the project when requested

Buy Now
Questions 39

Identify the missing words in the following sentence.

The six aspects of project performance to be managed are [ ? ] costs, timescales and scope.

Options:

A.

benefits, change, risk,

B.

benefits, quality, risk,

C.

change, quality, risk,

D.

benefits, change, quality,

Buy Now
Questions 40

Which report must be used to inform the project board of a predicted deviation from agreed stage limits?

Options:

A.

End stage report

B.

Checkpoint report

C.

Highlight report

D.

Exception report

Buy Now
Questions 41

Which action should the project manager take to ensure effective progress management when a team manager is inexperienced?

Options:

A.

Increase the frequency of checkpoint reports

B.

Allow the team manager more flexibility to exceed cost tolerance

C.

Increase the frequency of event-driven controls

D.

Increase the frequency of escalations by the team manager

Buy Now
Questions 42

What is established during the 'initiating a project' process?

Options:

A.

The agreed protect acceptance criteria

B.

The need for a configuration library

C.

A plan for the work or project initiation

D.

An understanding of the project's funding

Buy Now
Questions 43

How does applying the ‘focus on products’ principle help to ensure that stakeholder expectations are met?

Options:

A.

By providing a common understanding of the products required

B.

By providing the tolerances for the project manager’s objectives

C.

By providing roles descriptions for the project management team

D.

By providing the justification for the project

Buy Now
Questions 44

Which is an objective of the 'controlling a stage' process?

Options:

A.

To review the business justification for the project

B.

To replan the current stage when directed

C.

To develop products to defined quality criteria

D.

To produce a learn plan for the work package

Buy Now
Questions 45

Which action should the project manager take during the 'assessing issues' step?

Options:

A.

Create an exception plan tor project board approval

B.

Gain project board feedback on the Issue priority

C.

Consider the impact of alternative options for resolution

D.

Determine the initial priority of the issue that has been raised

Buy Now
Questions 46

What is a risk actionee responsible for?

Options:

A.

Identifying risks to the project that might occur in their department

B.

Owning and authorizing the use of the risk budget to fund risk responses

C.

Managing, monitoring and controlling of all aspects of an assigned risk

D.

Carrying out a risk response action to respond to a particular risk

Buy Now
Questions 47

What should be implemented using a risk budget?

1. A request for change

2. A contingent plan

3. Actions to avoid a risk from occurring

4. Responses to dis-benefits

Options:

A.

1 and 2

B.

2 and 3

C.

3 and 4

D.

1 and 4

Buy Now
Questions 48

Which is a purpose of the quality theme?

Options:

A.

To check that the project is viable and achievable

B.

To ensure that the project outputs are agreed

C.

To ensure that formal issues are recorded

D.

To enable the project to be managed according to plan

Buy Now
Questions 49

Which is a benefit of applying the ‘tailor to suit the project’ principle?

Options:

A.

Project management becomes less bureaucratic

B.

The capability of leadership is strengthened

C.

The project environment complexity is reduced

D.

The number of outputs is reduced

Buy Now
Questions 50

Which principle helps to ensure that all changes to the outputs are agreed?

Options:

A.

Defined roles and responsibilities

B.

Focus on products

C.

Learn from experience

D.

Manage by exception

Buy Now
Questions 51

What is an advantage of applying the 'learn from experience' principle?

Options:

A.

It allows the project board to delegate cost tolerances to the project manager

B.

It allows the project team to fully understand their roles and responsibilities

C.

It allows the project manager to delegate time tolerances to the team managers

D.

It allows the project team to identify improvements to be made during the project

Buy Now
Questions 52

What must be produced to meet the minimum requirements when applying the change theme?

Options:

A.

A change budget for the analysis of change

B.

Records of the decisions made on all issues

C.

Documents recording the version of each product

D.

Status reports on all products being produced

Buy Now
Questions 53

Which is a purpose of the quality theme?

Options:

A.

To establish how the project will ensure that all products created meet their requirements

B.

To establish baselines against which any changes to products can be assessed

C.

To identify all the products of the project to ensure the scope has been adequately defined

D.

To determine the communication needs of the organization’s quality assurance function

Buy Now
Questions 54

Which statement is CORRECT about the customer and suppliers of a project in a commercial environment?

Options:

A.

Each party may have their own business case for undertaking the project

B.

Both parties must apply the same external governance to the project

C.

The risk appetite should be collaboratively set before the project starts

D.

Management systems need to be unified for successful project delivery

Buy Now
Questions 55

When developing a business case, the project manager reviewed the end project report from & previous similar project that stated had been underestimated on the project.

Which principle is being applied by the project manager when reviewing this information?

Options:

A.

Learn from experience

B.

Tailor ta Suit the project

C.

Manage by stages

D.

Ensure continued business justification

Buy Now
Questions 56

What is an advantage of dividing the project into stages?

Options:

A.

Detailed plans can be prepared closer to the time events will take place

B.

the project board can delegate management of the project to team managers

C.

The project can be authorized by the project manager on a stage by stage basis

D.

The project brief can be updated towards the end of each stage

Buy Now
Questions 57

Which process has the objective of confirming that acceptance criteria have been met?

Options:

A.

Controlling a stage

B.

Directing a project

C.

Managing product delivery

D.

Closing a project

Buy Now
Questions 58

What is documented in the project plan to support the 'manage by exception' principle?

Options:

A.

The project's tolerances for cost and time

B.

A project product's quality criteria

C.

The expected project benefits

D.

Activities to mitigate project risks

Buy Now
Questions 59

The project board needs to confirm that there is enough information to initiate the project.

What should the project board review?

Options:

A.

Project brief

B.

Business case

C.

Benefits management approach

D.

Project plan

Buy Now
Questions 60

What is the result of the change derived from using the project’s product?

Options:

A.

Benefit

B.

Dis-benefit

C.

Outcome

D.

Output

Buy Now
Questions 61

Which are purposes of the 'directing a project' process?

1. To enable the project board to be accountable for a project's success by making key decisions

2. To enable the project board to authorize work packages

3. To enable the project board to prepare the communication management approach

4. To enable the project board to exercise overall control of a project

Options:

A.

1 and 2

B.

2 and 3

C.

3 and 4

D.

1 and 4

Buy Now
Questions 62

Which process provides information for the project board to review an updated project plan?

Options:

A.

Initiating a project

B.

Controlling a stage

C.

Directing a project

D.

Managing a stage boundary

Buy Now
Questions 63

According to the ‘exception management’ technique, when should the team manager raise an issue?

Options:

A.

When the team manager predicts that a product will cause a stage to exceed its time tolerance

B.

When the team manager identifies that a product is going to be delivered late

C.

when the team manager predicts that a product will cause a work package to exceed its time tolerance

D.

when the team manager identifies that the work package has already exceeded its time tolerance

Buy Now
Questions 64

Which TWO are objectives of the ‘controlling a stage process?

1. To focus attention on achieving Work Within) the agree tolerances

2. To create follow on action recommendations for all open issues and risks

3. To understand how the quality required will be achieved

4. To ensure that the stage’s products meet-agreed quality expectations

Options:

A.

1 and 2

B.

2 and 3

C.

3 and 4

D.

1 and 4

Buy Now
Questions 65

According to the 'continued business justification' principle, when is a justifiable reason for a project FIRST needed?

Options:

A.

After the executive has been appointed

B.

When authorized by the corporate, programme management or the customer

C.

Before work to start the project commences

D.

When an organization produces its business plans

Buy Now
Questions 66

Which is an assumption about the PRINCE2 customer/supplier environment?

Options:

A.

The supplier will pay for the project

B.

The customer will provide the resources to deliver the products

C.

The customer will specify the desired result

D.

The supplier will tailor the project's application of PRINCE2

Buy Now
Questions 67

What does the communication management approach define?

1. How versions of products will be described on information sent to interested parties

2. How information should be sent to interested parties

3. How often information should be sent to interested parties

4. How the PRINCE2 roles will be combined during the project

Options:

A.

1 and 2

B.

2 and 3

C.

3 and 4

D.

1 and 4

Buy Now
Questions 68

According to the ‘continued business justification’ principle, what should happen to the funds when a project can no longer be justified?

Options:

A.

They should be returned to corporate, programme management or customer

B.

They should be used to create an alternative business case for the project

C.

They should be transferred back to the project board to reassign

D.

They should be used to deliver a reduction in the scope of the project

Buy Now
Questions 69

Within which integrated element does PRINCE2 set minimum requirements?

Options:

A.

Themes

B.

Processes

C.

Principles

D.

Project environment

Buy Now
Questions 70

Which process is used to define how baselines will be established and controlled?

Options:

A.

Controlling a stage

B.

Directing a project

C.

Initiating a project

D.

Starting up a project

Buy Now
Questions 71

Why is the 'initiating a project' process used?

Options:

A.

To decide which project approach is suitable for the project

B.

To fully understand how the project objectives will be achieved before committing significant resources

C.

To produce the required work packages

D.

To enable corporate or programme management to give authorization to deliver a project

Buy Now
Questions 72

Which role represents the stakeholders who will operate the project's products after the project is complete?

Options:

A.

Executive

B.

Senior user

C.

Senior supplier

D.

Project manager

Buy Now
Questions 73

Which activity takes place within the Managing a Stage Boundary process?

Options:

A.

Produce Highlight Reports

B.

Take corrective action within the limits of a stage's tolerance

C.

Produce an Exception Plan

D.

Authorize a Stage Plan for the next stage

Buy Now
Questions 74

How does the project plan help to support the 'manage by stages' principle?

Options:

A.

By identifying the customer's quality expectations

B.

By defining products to ensure they are fit for purpose

C.

By identifying the major control points and milestones

D.

By estimating the timescales and costs of the project

Buy Now
Questions 75

Which process monitors work that has been assigned to a team manager?

Options:

A.

Controlling a stage

B.

Directing a project

C.

Managing a stage boundary

D.

Managing product delivery

Buy Now
Questions 76

Which is the first task of PRINCE2's recommended approach to 'defining and analyzing the products'?

Options:

A.

Creating a product flow diagram

B.

Writing the product description

C.

Writing a project product description

D.

Documenting the plan

Buy Now
Questions 77

Which is a purpose of the 'initiating a project' process?

Options:

A.

To produce a stage plan for each stage of a multi-stage project

B.

To enable the project board to decide whether it is worthwhile to initiate a project

C.

To provide a fixed point at which acceptance for the project product is confirmed

D.

To enable an organization to understand the work needed to deliver the project's products

Buy Now
Questions 78

Which describes an off-specification?

Options:

A.

An interdependency between products that was previously unidentified

B.

The addition of an improvement to a product description

C.

A prototype demonstrating a possible design solution

D.

The production of more than the defined quantity of a specialist product

E.

That the right people are involved in appropriate roles

Buy Now
Questions 79

What information about benefits management must be documented to meet the minimum requirements for applying the business case theme?

Options:

A.

The senior user's responsibilities for realizing benefits

B.

Statements of actual versus forecast benefits at reviews

C.

The management actions needed to ensure benefits are realized

D.

No specific documents related to benefits are necessary

Buy Now
Questions 80

What action is taken as part of the 'controlling a stage' process?

1. Create an exception plan

2. Authorize work to be done

3. Take corrective action

4. Obtain approvals for completed products

Options:

A.

1 and 2

B.

2 and 3

C.

3 and 4

D.

1 and 4

Buy Now
Questions 81

Which product identifies how often stakeholders require information?

Options:

A.

Communication management approach

B.

Quality management approach

C.

Change control approach

D.

Risk management approach

Buy Now
Questions 82

What should be considered when defining the number of management stages in a project?

Options:

A.

When the team managers are available

B.

When key decisions need to be made

C.

When highlight reports will be submitted

D.

When project support will be available

Buy Now
Questions 83

Which is a minimum requirement for applying the quality theme?

Options:

A.

To define the project's approach to quality control

B.

To undertake independent audits of the project throughout the project

C.

To apply the recommended quality review technique

D.

To define the project's approach to quality assurance

Buy Now
Questions 84

Which describes a risk event?

Options:

A.

The area of uncertainty in terms of the threat or opportunity

B.

The derivation or sources of a potential risk to the project

C.

The achievement of a milestone on the project plan

D.

The sequence of events and actions that will be put in place if a risk occurs

Buy Now
Questions 85

Which PRINCE2 principle ensures that members of the project management team know what they are expected to contribute?

Options:

A.

Manage by exception

B.

Learn from experience

C.

Tailor to suit the project environment

D.

Defined roles and responsibilities

Buy Now
Questions 86

Why can PRINCE2 be applied to any type of project?

Options:

A.

Because it provides the project manager with procedures for managing project risks and issues

B.

Because it allows each member of the project management team to fully understand their role and responsibilities

C.

Because it separates the management of the project from the specialist work needed to deliver the products

D.

Because it provides the project manager with a planning procedure to plan the project more effectively

Buy Now
Questions 87

When should the level of tailoring be defined?

Options:

A.

During the initiation stage

B.

When reviewing what has been learned to date

C.

As a response to issues and risks experienced

D.

Before the project is triggered by the project mandate

Buy Now
Questions 88

Which is a purpose of the Risk theme?

Options:

A.

Establish a procedure to ensure every change is agreed by the relevant authority before it takes place

B.

Establish a cost-effective procedure to identify, assess and control uncertainty

C.

Establish mechanisms to control any unacceptable deviations from plan

D.

Establish mechanisms to manage risks at the corporate or programme level of an organization

Buy Now
Questions 89

Identify the missing words in the following sentence.

The 'directing a project' process starts when [ ? ] and is triggered by the request to initiate a project.

Options:

A.

the 'starting up a project' process is completed

B.

the project mandate has been approved by the project board

C.

the project board has agreed the project strategies

D.

corporate, programme management or the customer have authorized a project

Buy Now
Questions 90

Which process provides information for the project board to review a completed stage and confirm continued business justification?

Options:

A.

Controlling a stage

B.

Closing a project

C.

Directing a project

D.

Managing a stage boundary

Buy Now
Questions 91

Which is a purpose of the Managing a Stage Boundary process?

Options:

A.

Provide the Project Board with sufficient information for approving the next stage

B.

Approve the next Stage Plan

C.

Review and close any risks and issues identified during the previous stage

D.

Control the link between the Project Manager and the Team Manager(s)

Buy Now
Questions 92

Which process ensures that key roles and responsibilities are allocated before a decision is made to initiate a project?

Options:

A.

Managing Product Delivery

B.

Initiating a Project

C.

Managing a Stage Boundary

D.

Starting up a Project

Buy Now
Questions 93

Which process provides the Project Board with sufficient information for it to review the success of a completed stage and confirm continued business justification?

Options:

A.

Controlling a Stage

B.

Closing a Project

C.

Directing a Project

D.

Managing a Stage Boundary

Buy Now
Questions 94

What is a supplier of a PRINCE2 project responsible for?

Options:

A.

Providing the project mandate

B.

Providing resources to deliver the project outputs

C.

Establishing the project's governance

D.

Realizing the benefits from the project

Buy Now
Questions 95

What is performed as part of the recommended risk management procedure?

Options:

A.

A budget to investigate issues is allocated

B.

Risk management practices are reviewed to ensure that they are performed effectively

C.

Information about risks to the projects is sent to project stakeholders

D.

Conflicts between the project and the programme board are resolved

Buy Now
Questions 96

What problem may occur if projects are not aligned with corporate business strategy?

Options:

A.

The control of projects may be poor

B.

The outputs may be of poor quality

C.

The objectives of different projects may overlap

D.

The project management approaches used may differ

Buy Now
Questions 97

Which theme provides all management levels within the project management team with mechanisms for monitoring and control?

Options:

A.

Progress

B.

Change

C.

Organization

D.

Quality

Buy Now
Questions 98

Where should decisions regarding the tailoring of the project be recorded?

Options:

A.

Project brief

B.

Project initiation documentation

C.

Project mandate

D.

Stage plan

Buy Now
Questions 99

Identify the missing words in the following sentence.

When proposed changes [ ? ], the change authority must refer the decision back to the project board.

Options:

A.

are below the agreed change budget

B.

are objected to by team members

C.

are rejected by the change authority

D.

exceed the agreed change budget

Buy Now
Questions 100

Which describes a risk effect?

Options:

A.

The uncertainty expressed as a negative or favourable occurrence

B.

The issue which is affecting the project and has resulted in a risk

C.

The impact(s) on the project objectives should the threat or opportunity occur

D.

The change in the status of a risk in response to actions taken to control it

Buy Now
Questions 101

What is a benefits management approach used to assess?

Options:

A.

How the project's products have performed when in operational use

B.

The effectiveness of the project strategies

C.

How the project has progressed against its plans

D.

The suitability of the project management team structure

Buy Now
Questions 102

What must be included in the risk management approach, as a minimum requirement for applying the risk theme?

Options:

A.

A description of the risk management procedure

B.

An explanation of the company's risk appetite

C.

The names of the assigned actionees for each risk

D.

Estimations of the likelihood and impact of risks

Buy Now
Questions 103

Which statements about quality assurance and project assurance are CORRECT?

1. They are both independent of the project manager

2. They are both the responsibility of the project board

3. They are both independent from the project management team

4. They both assure that applicable standards are being used

Options:

A.

1 and 2

B.

2 and 3

C.

3 and 4

D.

1 and 4

Buy Now
Questions 104

Which is one of the three levels of plan in PRINCE2?

Options:

A.

Benefits Review Plan

B.

Programme Plan

C.

Team Plan

D.

Project Brief

Buy Now
Questions 105

What is an off-specification?

Options:

A.

A new requirement

B.

A quality tolerance

C.

A type of issue

D.

A major risk

Buy Now
Questions 106

Which is an objective of the Initiating a Project process?

Options:

A.

Develop the corporate quality management system as part of the Project Initiation Documentation

B.

Prepare the plans for the subsequent stages

C.

Summarize how the organization's project management method will be tailored for the project

D.

Request authority from corporate management to deliver the project

Buy Now
Questions 107

How many tasks does the product-based planning technique describe?

Options:

A.

One

B.

Two

C.

Three

D.

Four

Buy Now
Questions 108

Which is a recommended quality review team role?

Options:

A.

Project Manager

B.

Assurance

C.

Project Support

D.

Administrator

Buy Now
Questions 109

Identify the missing word in the following sentence. A member of the Project Board is responsible for [ ? ] assurance.

Options:

A.

quality

B.

supplier

C.

risk

D.

product

Buy Now
Questions 110

Which characteristic of a project reflects that there are different perspectives and motivations for customers and suppliers?

Options:

A.

Change

B.

Cross-functional

C.

Unique

D.

Risk

Buy Now
Questions 111

Which risk response type is appropriate to respond to an opportunity?

Options:

A.

Accept

B.

Fallback

C.

Exploit

D.

Transfer

Buy Now
Questions 112

What product is used to maintain a record of those who have an interest in the project and their information requirements?

Options:

A.

Project Plan

B.

Communication Management Strategy

C.

Project Brief

D.

Project Product Description

Buy Now
Questions 113

Which is a true statement about PRINCE2 event-driven controls?

Options:

A.

Event-driven controls take place at predefined periodic intervals

B.

Event-driven controls are produced at the frequency defined in a Work Package

C.

Event-driven controls are used for decision making

D.

Checkpoint Reports are event-driven controls

Buy Now
Questions 114

Which is a purpose of a Lessons Log?

Options:

A.

Note any lessons that are raised in Checkpoint Reports

B.

Record that corrective action is being taken

C.

Escalate lessons to the Project Board

D.

Raise improvements with Project Assurance

Buy Now
Questions 115

Which is part of quality control?

Options:

A.

Document the project's acceptance criteria in the Project Product Description

B.

Define the quality responsibilities of those involved in the production of the products

C.

Produce quality records to show that the planned quality activities have been carried out

D.

Maintain the corporate organization's quality management system

Buy Now
Questions 116

Identify the missing word(s) in the following sentence. PRINCE2 recommends three levels of [ ? ] to reflect the needs of the different levels of management involved in a project.

Options:

A.

Management strategies

B.

Plan

C.

Stakeholder interests

D.

Time-driven controls

Buy Now
Questions 117

Which process covers the work done by external suppliers who may NOT be using PRINCE2?

Options:

A.

Closing a Project

B.

Managing a Stage Boundary

C.

Managing Product Delivery

D.

Directing a Project

Buy Now
Questions 118

Identify the missing word(s) in the following sentence. During a quality review meeting [ ? ] any identified defects.

Options:

A.

a solution should be designed for

B.

an issue should be created for

C.

the agreed actions should be recorded for

D.

the chair will approve the solution to

Buy Now
Questions 119

Why is the Initiating a Project process used?

Options:

A.

To decide which project approach is suitable for the project

B.

To fully understand how the project objectives will be achieved before committing significant resources

C.

To produce the required Work Packages

D.

To enable corporate or programme management to give authorization to deliver a project

Buy Now
Questions 120

Identify the missing words in the following sentence. At the end of a stage, the [ ? ] should be used to check whether there is a requirement to send copies of the End Stage Report to external interested parties.

Options:

A.

Stage Plan

B.

Communication Management Strategy

C.

Follow-on action recommendations

D.

Quality Management Strategy

Buy Now
Questions 121

If the Project Board instructs the Project Manager to implement a request for change, which document would contain details of that change?

Options:

A.

Checkpoint Report

B.

Highlight Report

C.

Issue Report

D.

Product Status Account

Buy Now
Questions 122

Which is NOT a purpose of a Benefits Review Plan?

Options:

A.

Define the period over which the cost-benefit analysis will be based

B.

Describe how to measure the performance of the project's products in operational use

C.

Define the scope, timing and ownership of the benefit reviews required

D.

Describe how to measure and confirm any benefits that are to be realised after the project is closed

Buy Now
Questions 123

Which is a task of product-based planning?

Options:

A.

Identify activities and dependencies

B.

Write the Project Product Description

C.

Prepare the Work Packages

D.

Produce Product Status Accounts

Buy Now
Questions 124

Which is NOT one of the PRINCE2 integrated elements?

Options:

A.

Tailoring PRINCE2 to the project environment

B.

The processes

C.

The products

D.

The themes

Buy Now
Questions 125

Which is a purpose of the Controlling a Stage process?

Options:

A.

Produce a Team Plan for the work to be assigned to a Team Manager

B.

Select and implement actions that will resolve deviations from a plan within tolerance

C.

Obtain approvals for products delivered in a Work Package

D.

Update a Project Plan to incorporate the actuals from a Stage Plan

Buy Now
Questions 126

Which is a purpose of the Controlling a Stage process?

Options:

A.

Assign work to be done and take corrective action to ensure that the stage remains within tolerance

B.

Provide a fixed reference point at which acceptance for the project product is confirmed

C.

Enable the Project Board to be provided with sufficient information to authorize the next stage

D.

Enable the organization to understand the work that needs to be done to deliver the project's products

Buy Now
Questions 127

Which is a benefit of using PRINCE2?

Options:

A.

Is a method specifically designed for technical projects

B.

Provides for the efficient and economic use of management time

C.

Includes many of the proven planning techniques, such as critical path analysis

D.

Can be used to manage both projects and programmes

Buy Now
Questions 128

Identify the missing words in the following sentence. A purpose of the Plans theme is to [ ? ] the project's plans.

Options:

A.

define a coding system to provide a unique identifier for the products within

B.

summarize the results of the quality activities performed on

C.

provide a framework to design, develop and maintain

D.

define the project benefits to be achieved by each of

Buy Now
Questions 129

Who should act as the communication channel between a project and corporate or programme management?

Options:

A.

Project Board

B.

Project Assurance

C.

Project Manager

D.

Project Support

Buy Now
Questions 130

What process ensures focus on the delivery of a stage's products and avoids uncontrolled change?

Options:

A.

Directing a Project

B.

Managing a Stage Boundary

C.

Controlling a Stage

D.

Starting up a Project

Buy Now
Questions 131

Which is a purpose of an End Project Report?

Options:

A.

Identify individuals or groups that need to be told that the project is coming to an end

B.

Review how well the project performed against the Project Initiation Documentation used to authorize it

C.

Identify individuals or groups that are responsible for measuring the expected benefits after the project has closed

D.

Ensure that key project information is archived and made secure

Buy Now
Questions 132

Which is a benefit of using PRINCE2?

Options:

A.

Enables the management of projects as well as of 'business as usual' activities

B.

Can be tailored by leaving out elements of the method for some projects

C.

Can be applied to any type of project

D.

Avoids the need to involve corporate or programme management

Buy Now
Questions 133

What theme provides all management levels within the project management team with mechanisms for monitoring and control?

Options:

A.

Progress

B.

Change

C.

Organization

D.

Quality

Buy Now
Questions 134

Which is a typical core activity within configuration management?

Options:

A.

Issue management

B.

Quality inspection

C.

Identification

D.

Preparation

Buy Now
Questions 135

What is the collective name for individuals or groups who may be affected by a project?

Options:

A.

Customers

B.

Project Support

C.

Stakeholders

D.

Team members

Buy Now
Questions 136

Which is a recommended quality review team role?

Options:

A.

Project Manager

B.

Assurance

C.

Chair

D.

Producer

Buy Now
Questions 137

Which is assumed to be a customer's responsibility in the PRINCE2 customer/supplier environment?

Options:

A.

Specify the desired result

B.

Provide the resources and skills to deliver the desired result

C.

Ensure the technical integrity of a project

D.

Develop a project's products

Buy Now
Questions 138

Which is one of the six aspects of project performance that needs to be managed?

Options:

A.

Progress

B.

Change

C.

Risk

D.

Security

Buy Now
Exam Code: Prince2-Foundation
Exam Name: PRINCE2 7 Foundation written Exam
Last Update: Jul 30, 2025
Questions: 461
$57.75  $164.99
$43.75  $124.99
$36.75  $104.99
buy now Prince2-Foundation