Easter Special Sale - Limited Time 60% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: 575363r9

Welcome To DumpsPedia

PMI-SP Sample Questions Answers

Questions 4

John is a scheduler in ABC Company. He has to plan an activity for the schedule models. Which of the following activities will he use to make the schedule models? . Each correct answer represents a complete solution. Choose all that apply.

Options:

A.

Hammocks

B.

Critical path scheduling

C.

Flags

D.

Tasks

Buy Now
Questions 5

Your organization wants to start a new project. The study shows that the new project will save organization approximately $200,000 per year. Now it is required to move forward with the project. Which of the following documents will define the project justification?

Options:

A.

Feasibility study

B.

Project charter

C.

Work breakdown structure

D.

Project scope

Buy Now
Questions 6

Holly is a new project manager in your organization. She is working with you on the JHG project and she is confused as to why the project needs a schedule management plan and a schedule baseline. What is the difference between the schedule management plan and the schedule baseline?

Options:

A.

The schedule management plan describes how the schedule will be managed and controlled. The schedule baseline is used to compare with actual results to determine if a change, corrective action, or preventive action is needed.

B.

The schedule management plan describes how the schedule will be managed and controlled. The schedule baseline is used to determine how accurate the schedule management plan has been throughout the project execution.

C.

The schedule baseline describes how the schedule will be managed and controlled. The schedule management plan is used to compare with actual results to determine if a change, corrective action, or preventive action is needed.

D.

The schedule management plan describes how the schedule will be created. The schedule baseline is used to compare with actual results with what the project manager intended.

Buy Now
Questions 7

You are working with your project team to identify the project activities within your project. Which of the following is NOT a tool and technique that will be useful in defining the project activities?

Options:

A.

Decomposition

B.

Rolling wave plan

C.

Precedence diagramming method

D.

Templates

Buy Now
Questions 8

Holly is the project manager of the NDS project and she is 85 percent complete with her project though she should be 95 percent complete. Her project has a BAC of $9,850,400 and she has spent $8,011,221 to date. What is Holly's schedule performance index for this project?

Options:

A.

1.07

B.

0.98

C.

0.89

D.

Ten percent

Buy Now
Questions 9

Once the project's WBS has been created what process may happen next?

Options:

A.

Estimate activity resources

B.

Define activities

C.

Estimate activity durations

D.

Sequence activities

Buy Now
Questions 10

Fred is the project manager of a hotel restoration project. The hotel has 456 rooms. All rooms need to be primed and painted. Before each room can be painted, the primer must cure for twenty-four hours. Fred has arranged these tasks with a finish to start relationship between the priming and the painting. What else should Fred do to account for the twenty-four hours of cure time?

Options:

A.

Fred should add twenty-four hours of lead time to each of the 456 rooms painting activity to account for the primer's curing time.

B.

Fred should add twenty-four hours of lag time to each of the 456 rooms painting activity to account for the primer's curing time.

C.

Fred should add an intermediary task with a duration of twenty-four hours.

D.

Fred should schedule all 456 hotels rooms to be primed first and then schedule all 456 rooms to be painted to ensure time for the curing.

Buy Now
Questions 11

Fill in the blank with an appropriate phrase. The ________is defined in terms of either the product or the type of customer or industry sector.

Options:

Buy Now
Questions 12

You are the project manager for your organization. You have been recording the actual results of activity duration for your project. Many of the results are late and this is causing your project to be late on reaching its milestones. What tool and technique can you use as a part of controlling the schedule to help you review various scenarios to bring the schedule into alignment with the plan?

Options:

A.

What-if scenario analysis

B.

Root cause analysis

C.

Schedule analysis

D.

Resource leveling

Buy Now
Questions 13

Jenny is the project manager for her organization. Her project is not doing well on project schedule performance, and management wants her to predict how the project schedule and cost will end. Management has asked Jenny to report and forecast her project's performance based on the Judgmental methods. Which of the following judgmental methods will Jenny use to accomplish the task? Each correct answer represents a complete solution. Choose all that apply.

Options:

A.

Forecast by analogy

B.

Technology forecasting

C.

Autoregressive moving average

D.

Scenario building

Buy Now
Questions 14

In the project time management knowledge area, there are six processes. According to the PMBOK, which project time knowledge area will have the majority of the effort?

Options:

A.

Estimate activity resources

B.

Define activities

C.

Control schedule

D.

Develop schedule

Buy Now
Questions 15

You are the project manager for the NGH project. The figure given below represents the small project you are completing for your organization.

How much float can you use on Activity G if Activity B actually takes eight days to complete?

Options:

A.

Four

B.

Three

C.

Seven

D.

Zero

Buy Now
Questions 16

All of the following statements about the critical path are false except for which one?

Options:

A.

The critical path cannot be crashed.

B.

The critical path is the shortest path in the project network diagram.

C.

The critical path is always one path with the longest duration.

D.

The critical path shows the project's earliest date for completion.

Buy Now
Questions 17

You are the project manager for the GRT Project in your organization. You have created your time duration estimates based on historical information, but the estimates are not holding true in your current project. Unfortunately, many activities are late. You have decided to create a PERT estimate with your project team for each of their activities. What is the formula used for PERT?

Options:

A.

O+M+P

B.

(O+M+P)/3

C.

(O+4M+P)/6

D.

Average of the estimates

Buy Now
Questions 18

Amy works as a project manager for BlueWell Inc. She is working on the SDI project, which has a BAC of $2,816,000. She is currently 20 percent complete with this project, though she should be 25 percent complete with the project work. The project has consumed $495,000 of the project budget to date. Management has asked her the project's Estimate To Complete (ETC) based on the current project performance. What is the ETC for this project?

Options:

A.

$1,312,504

B.

$1,979,952

C.

$1,541,544

D.

$2,474,952

Buy Now
Questions 19

You are the project manager for your organization. You have created the project schedule and have presented it to the management for their approval. Management decides to enforce resource leveling heuristics on your project schedule. What will likely happen to your project now?

Options:

A.

It will require fewer resources due to the cut in the project scope.

B.

It will require additional resources for the additions to the project scope.

C.

It will require additional resources if it is to finish in the same amount of time, as originally predicted.

D.

It will require a new scope baseline to reflect the management change in the project approach.

Buy Now
Questions 20

You are the project manager of the GYG Project. A new scope change is being considered for your project. You are concerned, however, that the scope change may add costs, risks, and adversely affect the project schedule. What project management process is responsible for evaluating the full effect of a proposed scope change on your project?

Options:

A.

Scope change control

B.

Schedule change control

C.

Integrated change control

D.

Change Control Board approval process

Buy Now
Questions 21

You are the project manager for your company. You are currently working with your project team to begin sequencing the activity list. You will need organizational process assets and four other documents as inputs to this process. Which of the following is NOT one of the four documents you will need for activity sequencing?

Options:

A.

Project scope statement

B.

Milestone list

C.

Project schedule network diagrams

D.

Activity list

Buy Now
Questions 22

You are the project manager for your organization. Your project is doing fine on time and cost, but management wants to address the project performance for future accomplishment. Management has asked you to begin reporting and forecasting your project's health based on a moving average, extrapolation, trend estimation, and growth curve. What type of forecasting method is management asking you to use?

Options:

A.

Judgmental methods

B.

Causal/econometric methods

C.

Time series methods

D.

Estimate at completion method

Buy Now
Questions 23

You are the project manager for your project. Your project is scheduled to last for one year and you are currently forty percent complete with the project. Based on your current performance measurements you have an SPI of .95 and a cost variance of -$24,000. You need to report this information to the management, but you will also need a solution to present with the variance information. Which one of the following can you present to the management as a part of the control schedule tools and techniques for variances?

Options:

A.

Work performance measurements

B.

Corrective actions

C.

Trim the project scope

D.

Causes of variances

Buy Now
Questions 24

Which of the following are the outputs to the Determine Budget process? Each correct answer represents a complete solution. Choose all that apply.

Options:

A.

Project document updates

B.

Scope baseline

C.

Cost performance baseline

D.

Project funding requirements

Buy Now
Questions 25

You are the project manager for your organization. You and the project team are developing the project schedule for your current project. This project management process will create four outputs. Which of the following is an output of the Develop Schedule process?

Options:

A.

Work performance information

B.

Schedule baseline

C.

Resource calendars

D.

Activity duration estimates

Buy Now
Questions 26

You are the project manager of the GHQ Project. You have to prioritize activities for the effective management of project. For this, you have created a network diagram to schedule a set of project activities as shown in the figure:

Based on this figure, what is the critical path of this project?

Options:

A.

ABEHJ

B.

ACFIJ

C.

ADGJ

D.

ACFGJ

Buy Now
Questions 27

You are the project manager of the NHL Project for your organization. You are working with your project team to create the schedule baseline for this project. According to you, which of the following statements describes how the schedule baseline is created?

Options:

A.

It is derived from the constraints of the project.

B.

It is assigned to the project by management.

C.

It is created by the stakeholders.

D.

It is developed from the schedule network analysis.

Buy Now
Questions 28

You work as a project manager for BlueWell Inc. You and your project team is undergoing the decision making process for the project. You want to involve key participants to gain acceptance and commitment to make the solution work. Which of the following phases of the decision- making model defines this process of work?

Options:

A.

Ideas to action

B.

Problem definition

C.

Problem solution generation

D.

Solution action planning

Buy Now
Questions 29

You work as the project manager for BlueWell Inc. Mark, a project team member, has some doubts related to the outputs of the control schedule process. Which of the following is an output of the control schedule process?

Options:

A.

Project schedule

B.

Lessons learned

C.

Change request

D.

Activity resource requirement

Buy Now
Questions 30

You are the project manager of the NQQ project. You are working with your project team to create the activity duration estimates for the project. For each reported activity duration, your project team offers you an addition of five percent extra time for risks, errors, or aggressive estimating. What does Parkinson's Law state about this scenario?

Options:

A.

Work expands to fulfill the amount of time allotted to it.

B.

Risks will be allowed into activities in which management creates risk provisions.

C.

Laborers will create errors when time has been allotted for errors to exist.

D.

Errors will be allowed into assignments when management creates error opportunity.

Buy Now
Questions 31

Harry works as a project manager for BlueWell Inc. He is determining the budget of the project. According to the PMBOK, there are seven inputs to this process. Which one of the following is NOT an input to the determine budget process?

Options:

A.

Contract

B.

Reserve analysis

C.

Scope baseline

D.

Project schedule

Buy Now
Questions 32

You are the project manager for your organization. You have recently noted some risks associated with some of the activities in your project. These risks can have schedule and costs impacts on your project and you need to address the risks through qualitative and quantitative analysis to confirm the depth of possible impact. Where should you document the risk information concerning the activities in your project schedule?

Options:

A.

Risk management plan

B.

Schedule management plan

C.

Risk register

D.

Activity attributes

Buy Now
Questions 33

John is the project manager for his organization. Management has asked John to fast track his project in order to reach a particular date for the project completion. When John fast tracks the project what project management component must be updated to reflect this decision? Choose the best answer.

Options:

A.

Organizational process assets

B.

Cost management plan

C.

Resource calendars

D.

Risk register

Buy Now
Questions 34

A project team installs 2,500 light fixtures in a new office building, and each light fixture takes one hour to install. The project manager can predict that it will take 2,500 hours to complete the work. However, which of the following statements most accurately describes this parametric estimate assumption?

Options:

A.

As workers complete the installation, efficiency will increase and durations will decrease.

B.

As workers complete the installation, errors and risks will increase the actual completion.

C.

As workers complete the installation, effort will diminish and efficiency will decrease.

D.

As workers complete the installation, labor will diminish so duration will increase.

Buy Now
Questions 35

You work as a project manager for BlueWell Inc. By referring to the figure given below, you along with your project team is calculating the latest completion of an activity.

What is the latest your project team can complete Activity I?

Options:

A.

Day 29

B.

Day 26

C.

Day 25

D.

Day 30

Buy Now
Questions 36

You work as a stakeholder for ABC Inc. You are on an important feature of a project that appears too difficult to execute. Issues like acceptable type of bugs and number of bugs for user acceptance seem to have affected the project. What is the rate of risk factor in such a situation?

Options:

A.

Risk factors are rated high.

B.

Risk factors are rated low.

C.

Risk factors are rated medium-high.

D.

Risk factors are rated medium.

Buy Now
Questions 37

You are project manager of HHK project. Examine the network diagram given below:

A vendor reports that he will be four days late on the materials you'll need in order to complete Activity E. Based on the project network diagram, how many days can Activity E be delayed?

Options:

A.

Four days

B.

Six days

C.

Five days

D.

Zero, it is on the critical path.

Buy Now
Questions 38

You are the project manager for your organization. You are working with your virtual team to create activity duration estimates for your current project. This virtual team is comprised of team members from around the world. Much of this process will be completed by geographical locations though some conferences will require all the team members to participate and to coordinate the activities that will interact between the different sites. The project manager must consider all of the following when creating the activity duration estimates except for which one?

Options:

A.

Project calendar

B.

Critical path

C.

Resource calendar

D.

Time zone differences

Buy Now
Questions 39

Amy works as a project manager for BlueWell Inc. Her organization wants her to create a new warehouse. Which of the following documents will she create to define the business needs, the project justification, and the current requirements?

Options:

A.

Project scope

B.

Feasibility study

C.

Project charter

D.

Work breakdown structure

Buy Now
Questions 40

Complete this sentence:

_________________________ is the process of collecting and distributing performance information including status reports, progress measurements, and forecasts.

Options:

A.

Corrective action

B.

Report performance

C.

Earned value management

D.

Monitor and control project performance

Buy Now
Questions 41

You are the project manager of a project that has a budget of $875,000 and you have completed 40 percent of the project work. Due to some errors, however, you have actually spent $425,000 of the budget. Management wants to know what the project's cost performance index is. What value do you report?

Options:

A.

-$75,000

B.

$350,000

C.

.82

D.

-$187,500

Buy Now
Questions 42

You work as a project manager for BlueWell Inc. You are going through a project with your project team. Some of your project team members are reporting that their activities are running late because there are lag times between activities that do not need to be there. You examine the schedule and see that the lag times have been incorporated into the project schedule for quality control reviews. You also learn that the quality control reviews are not being completed as planned. What is the best approach in this scenario?

Options:

A.

Since the quality control inspections are not being completed, remove the lag time from the project.

B.

Take corrective action and determine when the quality control inspection has happened so far in the project, perform quality control on the deliverables where the inspection was skipped, and ensure that quality control will happen from this point forward.

C.

Since the quality control inspections are not being completed, take corrective action and ensure that the inspections continue from this point forward.

D.

Discuss with the project team that the lag times should not affect the project schedule because they were built into the project schedule to begin with. Even if the quality control inspections were happening the time was allotted in the schedule for the inspections.

Buy Now
Questions 43

Beth works as a project manager for BlueWell Inc. Which of the following tools and techniques of Administer Procurements process will Beth use to manage contracts, and procurement documentation and records?

Options:

A.

Records Management System

B.

Performance reporting

C.

Inspection and Audit

D.

Payment System

Buy Now
Questions 44

Anna is the project manager of the NHQ project. Her project has 1,500 stakeholders, some of which are external to her organization. In this project, Anna wants to create a method to classify the stakeholders based on their level of authority and their level of concern regarding the project outcomes. This model will help Anna determine the communication demands and when information should be distributed. What does Anna want to create in this instance?

Options:

A.

Power/interest grid

B.

Salience model

C.

Power/influence grid

D.

Communications matrix

Buy Now
Questions 45

You are working with your project team to control the project schedule. You will need five inputs to this process throughout your project. Which one of the following is an output of the project schedule control, and NOT an input?

Options:

A.

Work performance information

B.

Project schedule

C.

Project management plan

D.

Work performance measurements

Buy Now
Questions 46

You are the project manager of the NHQ project. This project is slightly larger than the TR project, in which you also served as the project manager. You decide to use the actual activity duration of the GTR project as a basis for your current NHQ project. This, you reason, will save time for your project, as the previous project has provided the information. Which one of the following terms best describes the action you are doing in this scenario?

Options:

A.

You are creating an analogous estimate.

B.

You are creating a bottom-up estimate.

C.

You are relying on expert judgment.

D.

You are creating a rough order of magnitude estimate.

Buy Now
Questions 47

You are the project manager of the NHQ Project and are trying to determine which seller you should choose for the project. You have received proposals from six vendors and they are all very good proposal, qualified to complete the project work, and the prices are close to the same. You would like to create method of ranking each vendor based and assign a score value to several different categories. Because the project is a high-profile project, you have assigned 25 points to experience and 10 points for all of the other categories to judge the vendors. This is considered what type of source selection process?

Options:

A.

Screening system

B.

Preferred vendor list

C.

Benefits-cost analysis

D.

Weighting system

Buy Now
Questions 48

Frank is the project manager of a construction project. In this project, Frank has elected to allow the interior design phase of the project to overlap with the pool construction phase of the project. Normally, Frank would not allow these two phases to overlap, but for this project, he has elected to do so in order to compress the project schedule. What is this schedule compression technique called?

Options:

A.

Resource leveling heuristic

B.

Lead time

C.

Fast tracking

D.

Crashing

Buy Now
Questions 49

Billy is the project manager of the PQW Project and she has an assigned project budget of $655,000. Currently she is 80 percent complete with the project though she was scheduled to be 100 percent done by this date. She has spent $490,000 to date and other than the project schedule, which was delayed because of a vendor, the project is going well. What should Billy report as her schedule performance index for this project?

Options:

A.

1.23

B.

100 percent because the vendor caused her lateness

C.

.80

D.

$524,000

Buy Now
Questions 50

You are the project manager for your organization. Your project will be utilizing a piece of equipment during its process of completion. There is some concern that your project's use of the equipment may conflict with another project. What document will help you determine when and how long you will use the shared equipment?

Options:

A.

Project schedule

B.

Project scope

C.

Project calendar

D.

Resource calendar

Buy Now
Questions 51

What is the formula to find the schedule performance index?

Options:

A.

EV-PV

B.

EV/AC

C.

EV/PV

D.

EV-AC

Buy Now
Questions 52

You are the project manager of the HQQ Project. Your project is running late by ten percent of where you should be at this time. Management is concerned. Considering that the project has a BAC of $567,899, you are thirty percent complete, and you have spent $179,450. What is this project's to-complete performance index based on the current BAC?

Options:

A.

1.02

B.

0.010

C.

0.75

D.

0.95

Buy Now
Questions 53

Holly is the project manager for her organization. In her project, she has worked with the project team to define when the project team will be utilized in the project, the duration of the project activities, and the sequence in which the project work must be completed. During several phases of her project, the project team will need to work more than fifty hours per week. The project team members have agreed this is necessary and they're willing to do the work to complete the project. Management, however, has not approved Holly's schedule based on the overtime the scheduling will require. They have set a limit on the project schedule of 45 hours per week. What is this limit technically called? Each correct answer represents a complete solution. Choose all that apply.

Options:

A.

Constraint

B.

Assumption

C.

Execution variance analysis

D.

Resource leveling heuristic

Buy Now
Questions 54

You are the project manager of a project that has a budget of $675,000 and you have completed 40 percent of the project work. Your project is supposed to be 60 percent complete but you are actually only 40 percent complete. Due to some errors, however, you have actually spent $335,000 of the budget. Management wants to know what the project's cost performance index (CPI) is. What value do you report?

Options:

A.

-$135,000

B.

.67

C.

.81

D.

-$65,000

Buy Now
Questions 55

You have a project to install 45,900 emergency exit signs throughout a university campus. You have a crew of 45 project team members to install the signs and they are making good progress on the installation but it looks like they'll miss the promised end date. Your project requires all of the signs to be installed one week before classes are scheduled to begin. You elect to crash the project in an effort to shorten the installation duration activity. What does it mean to crash the project?

Options:

A.

Increase the working hours.

B.

Level the project schedule.

C.

Add more workers.

D.

Reduce the project scope.

Buy Now
Questions 56

You are the project manager of the GHY Project. This project is scheduled to last for one year and has a BAC of $4,500,000. You are currently 45 percent complete with this project, though you are supposed to be at your second milestone which accounts for half of the project completion. There have been some errors in the project which has caused you to spend $2,073,654. What is this project's schedule performance index?

Options:

A.

1.02

B.

0.98

C.

0.90

D.

-$108,120

Buy Now
Questions 57

Winnie is the project manager for her company. She has been recording the actual durations of the project work to determine the actual progress of her project. Winnie needs to generate an updated project schedule based on project performance. She is using the supporting schedule data, manual scheduling methods, and her project management software to perform schedule network analysis. What other tool Winnie can use to help and generate an updated project schedule?

Options:

A.

Critical path method

B.

Schedule management plan

C.

Scheduling tool

D.

Critical chain method

Buy Now
Questions 58

You work as a project manager for BlueWell Inc. Management has asked you not to communicate performance unless the CPI is less than 0.96 or the SPI dips below 0.98. What type of report would you create for management, if these instances develop in your project?

Options:

A.

Cost variance report

B.

Exceptions report

C.

Performance management report

D.

Schedule variance report

Buy Now
Questions 59

Tom is the project manager of the GHQ Project for his organization. He is working on recovering the project schedule. As Tom examines his schedule he is especially aware of project activities with soft logic. What is soft logic?

Options:

A.

Soft logic describes activities that do not have particular resources assigned to them.

B.

Soft logic describes activities that can be completed in any order.

C.

Soft logic describes activities that can have lead time added to them.

D.

Soft logic describes activities that can be crashed because they are effort-driven.

Buy Now
Questions 60

Which of the following individuals has a management role in a core business area, such as research and development, design, manufacturing, provisioning, testing, or maintenance?

Options:

A.

Functional manager

B.

Operations manager

C.

Project manager

D.

Seller

Buy Now
Questions 61

You are a project manager in a matrix environment and management is concerned about the utilization of the resources on your project team and when you'll release them. What project management plan will guide how and when project resources will be released from the project team?

Options:

A.

Project Human Resources Management Plan

B.

Project Staffing Management Plan

C.

Project Communications Management Plan

D.

Project Schedule Management Plan

Buy Now
Questions 62

Your project is forty percent complete though it was scheduled to be fifty percent complete as of today. Management has asked that you report on the schedule variance for your project. If your project has a BAC of $650,000 and you've spent $385,000 to date, what is the schedule variance value?

Options:

A.

-$75,500

B.

-$390,000

C.

-$487,500

D.

-$65,000

Buy Now
Questions 63

Holly is the project manager for her organization. She is creating the activity list and would like to tag those activities that are comprised of discrete effort. What is discrete effort?

Options:

A.

It is a term used to describe activities whose effort cannot be directly measured to the project objectives.

B.

It is a term used to describe activities whose effort can be directly measured and linked to the project objectives.

C.

It is a term used to describe activities that are supportive of the project work, but not linked to the project deliverables.

D.

It is a term used to describe activities that are core project management processes, but not core project activities.

Buy Now
Questions 64

Beth is the project manager for her organization. Her current project has many deliverables that have been defined at a high level, but the details of the deliverables are still unknown. In her project, Beth is planning in detail only the activities that are most imminent in the project work. This approach to project management planning is known as what?

Options:

A.

Imminent activity management

B.

Rolling wave planning

C.

Predecessor-only diagramming

D.

Decomposition

Buy Now
Questions 65

You are the project manager for your organization. You are working with your project team to create activity duration estimates using the PERT method. What is the formula for PERT?

Options:

A.

(O+ML+P)

B.

(O+(6M)+P)6

C.

(O+ML+P)/3

D.

(O+(4M)+P)/6

Buy Now
Questions 66

Which of the following are the inputs to the Develop Project Charter process? Each correct answer represents a complete solution. Choose all that apply.

Options:

A.

Procurement document

B.

Contract

C.

Business case

D.

Project statement of work

Buy Now
Questions 67

You are the project manager for your company. You are working with the management regarding the exact end date of your project. Management needs to know what day of the week your project will complete. Assuming that your project will not require any work to be completed over the upcoming weekends and that the remaining project work will commence on a Tuesday, what day of the week will the project end if there are 67 days of project work left to complete?

Options:

A.

Wednesday

B.

Thursday

C.

Monday

D.

Tuesday

Buy Now
Questions 68

You are the project manager of the NHA Project. This project is expected to last one year with quarterly milestones throughout the year. Your project is supposed to be at the third milestone today but you're likely only 60 percent complete. Your project has a BAC of $745,000 and you've spent $440,000 of the budget-to-date. What is your schedule performance index for this project?

Options:

A.

80

B.

1.02

C.

102

D.

0.80

Buy Now
Questions 69

The Define Activities process is the first process in the project time management knowledge are a. The Define Activities process creates just three outputs as a result of decomposition, rolling wave planning, templates, and expert judgment. Which one of the following is not an output of the Define Activities process?

Options:

A.

Activity list

B.

Milestone list

C.

Activity attributes

D.

Project document updates

Buy Now
Questions 70

You are the project manager of the AHQ project. This project is scheduled to last for six months and will require $345,000 to complete. If the project completes earlier than scheduled, your organization will receive a bonus of $5,000 per day of early completion. Management has asked you to develop an aggressive schedule to realize as much of the bonus as possible, but management does not want you to increase the costs of the project beyond $1,000 per day of the bonus realization. Which of the following approaches will likely add costs to the project?

Options:

A.

Adding leads to the project work

B.

Fast tracking

C.

Crashing

D.

Using the critical chain method

Buy Now
Questions 71

Sam is the project manager of the NQQ project. He and the project team have completed the stakeholder identification process for his project. What is the main output of the identify stakeholders process?

Options:

A.

Communications management plan

B.

Stakeholder register

C.

Requirements

D.

Stakeholder management strategy

Buy Now
Questions 72

You are the project manager for your organization. Management has asked you to document the holidays, weekends, and other corporate working hours, which will supersede the project timings for your schedule. Which calendar will communicate to the project stakeholders, when the project work will take place within the organization?

Options:

A.

Project calendar

B.

Resource calendar

C.

Organizational calendar

D.

Company calendar

Buy Now
Questions 73

You are the project manager of the NHT Project. This project has 12,345 office doors to install throughout a campus. Each of the doors costs the project $456 and requires special hardware to electronically lock and open the doors. You've gathered the project team before they begin the installation for a hands-on training. As a group you and the project team install 50 doors following a checklist of instructions so that every door will be installed exactly the same throughout the campus and with minimal waste. This is an example of what project execution technique?

Options:

A.

Preventive action

B.

Defect repair validation

C.

Implemented corrective action

D.

Quality control

Buy Now
Questions 74

You are the project manager of the JKM Project for your organization. Your project is supposed to be 60 percent complete but you are only 45 percent complete. The project has an assigned budget of $765,000 but you have already spent $365,000 to reach this point in the project due to some errors and rework. Management is pressing you on when you'll complete the project and how much the project will likely cost based on the current performance. You need to tell management what the project's current cost performance index (CPI) is. What value should you report to management based on your project's performance?

Options:

A.

$306,000

B.

.94

C.

$344,250

D.

.75

Buy Now
Questions 75

Jim is the project manager for his project. He and his project team are creating their duration estimates for the work packages in the WBS. For each activity, Jim is adding a few hours to the duration estimate in case something goes wrong during the completion of the work activity. Sarah, the project sponsor, does not approve of this and warns Jim of Parkinson's Law. What is Parkinson's Law?

Options:

A.

People will behave based on what their behavior brings them.

B.

As employees do repetitive tasks, duration should decrease.

C.

Work expands to fill the amount of time allotted to it.

D.

An exponential increase labor does not correlate to an exponential decrease in duration.

Buy Now
Questions 76

You work as a project manager for BlueWell Inc. You want to increase the overall duration of the project. If the management elects to use resource leveling, then what will happen to the project duration?

Options:

A.

The duration will increase, but the labor will stay the same.

B.

The duration will decrease as new team members are brought onto the project.

C.

Nothing, new resources will be incorporated into the project team.

D.

The duration will increase, but the labor will decrease.

Buy Now
Questions 77

Holly is the project manager for her organization. In her project, she has worked with the project team to define when the project team will be utilized in the project, the duration of the project activities, and the sequence in which the project work must be completed. During several phases of her project, the project team will need to work more than fifty hours per week. The project team members have agreed this is necessary and they're willing to do the work to complete the project. Management, however, has not approved Holly's schedule based on the overtime the scheduling will require. They have set a limit on the project schedule of 45 hours per week. What is this limit technically called? Each correct answer represents a complete solution. Choose all that apply.

Options:

A.

Constraint

B.

Assumption

C.

Execution variance analysis

D.

Resource leveling heuristic

Buy Now
Questions 78

You are the project manager of the NHG. The following figure represents your project network diagram.

Management has asked that you add some features to the project scope. Through the change control system these changes are approved and they'll affect Activity I. The duration of Activity I, which is on the critical path, will decrease by three days. What affect does this have on the critical path?

Options:

A.

The critical path will now take 26 days.

B.

The critical path will now take 17 days.

C.

The critical path will now take 23 days.

D.

The critical path will now take 20 days.

Buy Now
Questions 79

You have created the project network diagram for the ABC project. You are exploring total float and free float for that project. Martin, a project team member, wants to know the difference between total float and free float. What is the difference between total float and free float?

Options:

A.

Total float is the amount of time an activity can be delayed without delaying any project successors, whereas free float is the amount of time an activity can be delayed without delaying the project completion date.

B.

Total float is the amount of time an activity can be delayed without delaying the project completion date, whereas free float is the amount of time an activity can be delayed without delaying any project successors.

C.

Total float is the amount of time an activity can be delayed without delaying the project completion date, whereas free float is the amount of time an activity can be delayed without delaying any project predecessors.

D.

Total float is the amount of time a non-critical activity can be delayed without delaying any project successors, whereas free float is the amount of time an activity can be delayed without delaying the project completion date.

Buy Now
Questions 80

John works as a project manager for BlueWell Inc. He is working on a high-profile project with 80 stakeholders and he needs to express to his project team and to the management the importance of communication in the project. He would like to show the number of stakeholder communication channels in the project. Based on this information how many communication channels exist within this project?

Options:

A.

3000

B.

79

C.

80

D.

3160

Buy Now
Questions 81

Gary is the project manager for his organization. At each weekly status meeting with his project team, Gary collects information on the work that has been completed and reviews the work that is remaining in the project. Alice, one of Gary's project team members, consistently reports that she's late on her project work. After the meeting, Gary and Alice discuss why the work is late as it is causing other delays in the project. What is the review of the late work commonly called?

Options:

A.

Variance analysis

B.

Leadership

C.

Quality control

D.

Discipline

Buy Now
Questions 82

You work as a Project Manager for Dreams Unlimited Inc. You are looking for performance efficiencies of a project. The related key values are provided in the table below:

MeasurementsValues

BCWP (or EV)325

BCWS (or PV) 300

ACWP (or AC)410

What will be the cost performance index (CPI) of the project at the current point of time?

Options:

A.

0.923

B.

1.083

C.

1.261

D.

0.792

Buy Now
Questions 83

George is the project manager of the NHQ Project and has a budget of $778,000. The project is scheduled to last for one year with an equal amount of work completed each quarter. The second quarter of the project has ended and George has spent $325,000 but has only finished forty percent of the project. Management needs a variance report for the project schedule. What value should George report in this instance?

Options:

A.

.96

B.

-$77,800

C.

$-34,500

D.

-$13,800

Buy Now
Questions 84

You work as a project manager for BlueWell Inc. Your project is falling behind though the project team reports that the actual durations of their work is what they estimated. You investigate the cause and determine that the project team is not starting their assignments early enough to finish their work on time. While the duration of the assignments may be in synchronization with the duration estimates, the completion time is causing the project schedule to slip from the baseline. What can you do to rectify this problem?

Options:

A.

Increase the duration estimates for each activity.

B.

Discipline the project team.

C.

Add management reserve.

D.

Corrective actions.

Buy Now
Questions 85

You are the project manager of the OOI Project and you're forty percent complete with this project. The project has a BAC of $2,345,650 and you have spent $950,000 to date. Based on your aggressive scheduling you should at the 45 percent milestone today, but due to some early delays you're running late. What is the schedule variance of your project?

Options:

A.

-$29,350

B.

-$117,282

C.

-$938,260

D.

-$11,740

Buy Now
Questions 86

You are the project manager for your organization. You have recorded the following duration estimates for an activity in your project: optimistic 20, most likely 45, pessimistic 90. What time will you record for this activity?

Options:

A.

48

B.

20o, 45m, 90p

C.

90

D.

45

Buy Now
Questions 87

John works as the project manager for Honeywell Inc. He is involved in the periodic collection and analysis of baseline versus actual data to understand and communicate the project progress. Which of the following techniques is used in generating performance reports?

Options:

A.

Work performance information

B.

Change requests

C.

Work performance measurements

D.

Forecasting method

Buy Now
Questions 88

You are working as a project manager for BlueWell Inc. Which of the following tools and techniques of the Define Activity process will help you in identifying the typical schedule milestones?

Options:

A.

Expert Judgment

B.

Decomposition

C.

Rolling Wave Planning

D.

Templates

Buy Now
Questions 89

You work as a project manager for BlueWell Inc. Some of the activities in your project are not being completed on time. You review these activities with your project team discovered that the time estimates for the project are much more aggressive than what they are actually experiencing in the completion of the activities. You decide on to create a new schedule for the project. What project management process are you working with when you create a new target schedule?

Options:

A.

Estimate activity durations

B.

Estimate activity resources

C.

Control schedule

D.

Develop schedule

Buy Now
Questions 90

Nancy is the project manager of the JJJ Project. This project has recently been approved by the project customer as complete so Nancy must now finalize the administrative closure. Nancy needs to create the final project report to report the successes and failures in the project. Who should Nancy deliver this final project report to if she is participating in a projectized structure?

Options:

A.

Functional Management

B.

Project sponsor

C.

Whomever the communications management plan directs her to

D.

Project customer

Buy Now
Questions 91

You are the project manager of the GHY Project. This project is scheduled to last for one year and has a BAC of $4,500,000. You are currently 45 percent complete with this project, though you are supposed to be at your second milestone which accounts for half of the project completion. There have been some errors in the project, which has caused you to spend $2,073,654. What is this project's schedule variance?

Options:

A.

-$48,654

B.

13 percent

C.

-$225,000

D.

0.98

Buy Now
Questions 92

You are the project manager of the NHGQ project for your company. You must create and distribute performance reports every week to your key project stakeholders. What communication technique do you normally use to distribute reports?

Options:

A.

Push technique

B.

Many-to-many

C.

One-to-one

D.

Pull technique

Buy Now
Questions 93

Fill in the blank with the appropriate word. ____ management sets the boundaries for the project and is the foundation on which the other project elements are built.

Options:

Buy Now
Questions 94

Harry works as the project manager for his organization. He is creating the activity list and would like to tag those activities that are comprised of apportioned effort. Which of the following is the best example of apportioned effort?

Options:

A.

Adding features to the project's product that is not included in the project scope.

B.

Managing the day-to-day events of a project.

C.

Creating software as defined in the project scope.

D.

Completing project activities as start-to-start events.

Buy Now
Questions 95

Amy is working on a project which is forty percent complete though it was scheduled to be fifty percent complete as of today. Management has asked Amy to report on the schedule variance for her project. If Amy's project has a BAC of $750,000 and she has spent $485,000 to date, what is the schedule variance value?

Options:

A.

-$75,000

B.

-$42,000

C.

-$45,000

D.

-$65,000

Buy Now
Questions 96

What is the term assigned to graphic in the figure given below?

Options:

A.

Communications bull's eye

B.

Performance goals

C.

Earned value management goals

D.

Project exception report

Buy Now
Exam Code: PMI-SP
Exam Name: PMI Scheduling Professional
Last Update: May 15, 2024
Questions: 323
$64  $159.99
$48  $119.99
$40  $99.99
buy now PMI-SP