Summer Special Sale - Limited Time 60% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: 575363r9

Welcome To DumpsPedia

PMI-RMP Sample Questions Answers

Questions 4

Which statement describes the risk portrayed on the risk matrix heat map below?

Options:

A.

The risk has a probability of 60% of occurrence and a medium impact rating.

B.

The risk has a probability of 40% of occurrence and a high impact rating.

C.

The risk has a high impact and probability of occurring.

D.

The risk has a low probability and high impact rating.

Buy Now
Questions 5

An IT project is 40% complete. During the initial analysis, risks A and B were identified for the project. Risk A has a probability of 0.6 and an impact of US$50.000. Risk B has a probability of 0.7 and an impact of USS60.000. After implementing the planned risk response for risk B. the probability of risk B has been reduced is 0.3.

What is the current project risk exposure?

Options:

A.

US$18,000

B.

US$72.000

C.

US$30,000

D.

US$48,000

Buy Now
Questions 6

A project's design has been completed and approved on time. The construction subcontractor should be mobilizing to start construction but does not have the necessary materials in place, causing a delaying in the project. The risk register only contains risks for the design phase of the project.

What should the project manager have done differently?

Options:

A.

Executed the Monte Carlo sensitivity analysis prior to mobilization

B.

Added generic construction risks to the risk register before construction began

C.

Reviewed the assumptions/exclusions register in the project charter

D.

Performed risk identification exercises for the full lifecycle of the project

Buy Now
Questions 7

A highly complex project is about to start Considering that many changes and new information will arise as the work moves forward, key stakeholders are anxious about not addressing risks on time

What should the risk manager do in this situation?

Options:

A.

Establish a formal and upfront risk identification process.

B.

Use a detailed and quantitative risk assessment process.

C.

Create an effective and clear risk communication process.

D.

Adopt a dynamic and frequent risk management process.

Buy Now
Questions 8

During a project meeting, the project sponsor asks to close a project risk. The team does not recommend closing the risk because it is expected to be present in the next phase of the project work.

How should the risk manager address this concern?

Options:

A.

Compare the actual data with the historical data.

B.

Compare the actual data with the subject matter expert (SME) criteria.

C.

Compare the actual data with the risk baseline.

D.

Compare the actual data with the project sponsor's expectation.

Buy Now
Questions 9

A new risk manager has been assigned to a delayed strategic project. The risk manager presented a new plan to get the project back on track using lessons learned and applying risk response strategies. Senior management wants to remove contingency reserves because they want to finish the project earlier.

What should the risk manager do in this scenario?

Options:

A.

Review project schedule estimates.

B.

Change the response strategies.

C.

Reduce the contingency reserves.

D.

Conduct a risk planning workshop.

Buy Now
Questions 10

A project lihat was in the execution phase for the last six months was put on hold and was eventually cancelled after numerous scope related challenges. It was decided to re-plan the scope and divide the project into multiple projects to have better insight into end objectives. As part of the project start up. the project manager is developing the risk planning for the project.

What three artifacts should the project manager consult or review during this process? (Choose three.)

Options:

A.

Project contracts

B.

Lessons learned registers from analogous projects

C.

Risk register

D.

Risk management plan

E.

Code of regulations

Buy Now
Questions 11

A project is In the initiation phase. The project stakeholders are Invited to a meeting to share their thoughts that may impact the project In a positive or negative way.

What will be the main output of this meeting?

Options:

A.

Evaluating the project's probability of success

B.

Identifying threats and opportunities

C.

Evaluating the project's impact

D.

Performing a qualitative analysis

Buy Now
Questions 12

There is confusion among risk action owners on a project about when and under which conditions they should initiate risk responses. Project team members often need to consult with the risk manager to get this conflict resolved.

What should the risk manager do to resolve this recurring situation?

Options:

A.

Review the stakeholders' risk appetite.

B.

Revisit the risk thresholds and triggers.

C.

Update the risk response strategies.

D.

Provide coaching to the risk action owners.

 

Buy Now
Questions 13

During the construction of a housing development, a project team realizes they exceeded their materials budget during the first of three execution stages. The risk manager observed that the team did not notice that the cost of the materials increased due to continuous inflation in the steel market.

What could have been done during project planning to avoid overspending?

Options:

A.

Met weekly with the finance team to monitor the cost

B.

Communicated with the stakeholders that the project costs might increase

C.

Properly documented the triggers and actions for the risk

D.

Engaged with the sponsor to buy the steel in advance of the project

 

Buy Now
Questions 14

A project manager is working on a construction project. Based on past experience, the project manager identifies a risk that a supplier of a critical material may not deliver on time. The project manager has already accounted for this risk in the risk management plan. If this risk materializes, the project manager plans to procure the material from a different supplier. A potential risk in this plan is that there may be differences in the material provided by the first and second supplier.

What type of risk is this?

Options:

A.

Residual risk

B.

Primary risk

C.

Secondary risk

D.

Normal risk

Buy Now
Questions 15

After the initial assessment of a new project, a project manager found that in order to complete the expected results, detailed and exhaustive planning will be required to ensure the product's characteristics and quality. What should the risk manager propose to the project manager what to do?

Options:

A.

Use a predictive approach for the delivery.

B.

Use a hybrid approach for the delivery.

C.

Use an adaptive approach for the delivery.

D.

Use an agile approach for the delivery.

 

Buy Now
Questions 16

A risk manager wants to determine what risk has the biggest impact on project cost. The risk manager identified three risks, which could occur in different phases of the project.

What should the risk manager do first to understand the impact on project cost?

Options:

A.

Conduct a subject matter expert (SME) meeting.

B.

Perform qualitative analysis.

C.

Prioritize after quantitative analysis

D.

Prioritize the stakeholders affected.

Buy Now
Questions 17

In a complex project, individual risks have been identified with the stakeholders. The project sponsor asks the risk manager about the likelihood of project success. Which risk analysis tool(s) should the risk manager use as a basis for their response?

Options:

A.

Probabilistic and quantitative risk analyses to get the overall risk score

B.

Quantitative risk analysis to get the overall risk score

C.

Probabilistic risk analysis to get the overall risk score

D.

Qualitative risk analysis to get the overall risk score

 

Buy Now
Questions 18

A risk manager is preparing risk reports to be included in the monthly status report for project executives. How should the risk manager present the information?

Options:

A.

Earned value management (EVM) variance metrics

B.

A risk burndown chart showing remaining risks

C.

The format established in the risk management plan

D.

An itemized list of remaining risks and their scores

 

Buy Now
Questions 19

A project is at the final development stage. The test lead informs the risk manager that a key feature may not be testable due to changes in the environment

What should the risk manager do?

Options:

A.

Confirm the risk triggers are still valid.

B.

Ask the architect to develop acceptance criteria.

C.

Review the feature with the project team.

D.

Escalate the issue to the project board.

Buy Now
Questions 20

 

A new company initiates a project to incorporate a cybersecurity team. Which three documents should the risk manager analyze first? (Choose 3)

Options:

A.

Industry's standard procedures

B.

Current request for proposal (RFP)

C.

Company's historical financial reports

D.

IT infrastructure, networks, and data information

E.

Government laws and regulations

 

Buy Now
Questions 21

During a meeting with a project team, a project manager asks a risk manager to determine the risk events that could potentially have the most impact on a 2-year project with a budget of US$800 000. Which approach should the risk manager suggest the project manager take?

Options:

A.

Sensitivity analysis

B.

simul-ation analysis

C.

Monte Carlo simul-ation

D.

Quantitative analysis

Buy Now
Questions 22

A project manager works on a long-term and high visibility project at an organization that has a low risk appetite towards this project due to its impact on the company's business. The project sponsors follow up weekly with the project manager, who was just informed by one of the risk owners that the exposure from two high-impact risks are hitting the risk thresholds.

What should the project manager do next?

Options:

A.

Update the project management plan to add contingency.

B.

Perform an assumptions and constraints analysis.

C.

Complete an assessment and confirm the response with the sponsors.

D.

Implement mitigation measures for those risks.

Buy Now
Questions 23

A risk manager on an infrastructure project gathers and analyzes performance data. The risk manager wants to identify which variables will impact the schedule and determine how these factors interact.

Which data analysis tool should the risk manager use to forecast future performance?

Options:

A.

Sensitivity analysis

B.

What-if scenario analysis

C.

Regression analysis

D.

Decision tree analysis

Buy Now
Questions 24

A risk manager is confident that they have identified and quantified the risks and opportunities for a project. When presenting their work to management, on what areas should the risk manager focus? (Choose two.)

Options:

A.

Risks that are tied to the success of the organization

B.

Risks as they apply to the organization's overall risk management philosophy and strategic ambition

C.

Huge opportunities that possibly bring an additional 30% return for 10 projects in the next year

D.

Risks related to cost that will impact the major projects that are currently in the execution phase

E.

Risk mitigation actions that will require work from stakeholders

Buy Now
Questions 25

A core project team is working on unrelated tasks in advance to reduce the risk of delay due to an external team not completing its tasks on time. The core project team has completed all possible unrelated tasks but cannot move forward, because the external team's tasks have yet to be completed.

What should the risk manager do next?

Options:

A.

Start a quantitative analysis to understand the impact.

B.

Crash the schedule to mitigate the risk consequences.

C.

Transfer the risk to the external team.

D.

Ask the risk owners to review the risk response plan.

Buy Now
Questions 26

In a project to promote public health and mitigate health risks, the national health authorities intend to take actions to limit the risks of harmful insects by using pesticides; however, it is expected that some residents will have negative health effects due to the use of the pesticides but according to the assessment completed by the health authorities, not moving forward with this plan will have much more serious consequences on public health rather than following through with the original plan.

How should the project manager address this concern with the health authorities?

Options:

A.

Suspend the project as the secondary risk will negatively impact residents' health which is not acceptable.

B.

Consult with health experts to provide a risk trigger before using pesticides that will impact the residents.

C.

Assess and record associated secondary risks and proceed to treat them as any other risks.

D.

Proceed with the project as normal since a minor number of residents will be effected negatively.

Buy Now
Questions 27

The project manager and the risk manager of a new project to develop an application to support autonomous driving are meeting with the sponsor and key stakeholders to discuss the project. During the meeting, it is identified that the transport authority is discussing new traffic regulations for the industry that could be in place before the project ends.

How should the project manager and the risk manager handle this situation?

Options:

A.

Ensure the project complies with the current traffic regulations and laws.

B.

Send a letter to the traffic authority with the general project information.

C.

Perform inquiries on the website of the traffic authority weekly.

D.

Meet with the traffic authority staff in charge of the new regulation.

Buy Now
Questions 28

A risk manager has been assigned to an upcoming project. A senior risk manager within the organization recently completed a similar project and has provided a lessons learned document to aid planning efforts for the upcoming project. Upon reviewing the document, the risk manager discovers that the completed project was delivered several months behind schedule and several thousands of dollars over budget. The root cause was determined to be an unforeseen risk trigger that caused several items to be reworked, creating cascading schedule delays and depleting management reserves.

What should the risk manager do to mitigate the chance of the same issues reoccurring?

Options:

A.

Ensure that all project stakeholders have a copy of and understand the project's risk management plan.

B.

Increase the management reserves and inform stakeholders of what is available to cover any unexpected expenses

C.

Distribute the lessons learned document to stakeholders knowing that the likelihood of reoccurrence is low.

D.

Document the known risk triggers as the identified cost and schedule risks in the risk register.

 

Buy Now
Questions 29

The project manager leading a company's digital signature initiative for engineering drawings has identified threats and opportunities using a strengths, weaknesses, opportunities, and threats (SWOT) analysis.

What are two potential threats or opportunities under the SWOT analysis? (Choose two.)

Options:

A.

The management team agreeing to include more resource for the digital signature initiative.

B.

The organization's professional engineers having reservations about possible information tampering.

C.

A growing number of competitors with digital signatures.

D.

An elimination of manual steps associated with recording wet signatures

E.

The growing adoption of mobile communications in the industry.

Buy Now
Questions 30

The project risk manager is in the process of identifying risks. The project sponsor has communicated that there is an influential stakeholder who has a senior management position. The other stakeholders do not feel comfortable speaking in front of this stakeholder.

What should the project risk manager do next to identify risks?

Options:

A.

Review the risk breakdown structure to ensure project scope is covered.

B.

Use the brainstorming technique to remove personal bias.

C.

Use expert judgment to remove ego or emotional conflict.

D.

Consider the Delphi technique to gather all stakeholder opinions.

Buy Now
Questions 31

An external vendor needs to be contracted to provide additional capacity and expertise to a project team to reduce the probability of delays in a project. The contracts department is raising a concern about confidentiality risks not addressed in the proposed contract and missing from the risk register.

What should the risk manager do next?

Options:

A.

Assess the identified secondary risk.

B.

Implement the risk response plan.

C.

Implement the risk contingency plan.

D.

Communicate the identified residual risk.

Buy Now
Questions 32

A critical piece of equipment broke during a project execution phase. The risk manager notices this risk in the risk register, and the response is to rent equipment until the critical piece is repaired.

What type of risk response is this?

Options:

A.

Transfer

B.

Accept

C.

Mitigate

D.

Avoid

 

Buy Now
Questions 33

An organization faces immense competition in the market and decides to accelerate a key project. What is the first action for the project risk manager to take?

Options:

A.

Update the risk register

B.

Meet with the project's stakeholders

C.

Revise the risk management plan

D.

Ensure sufficient resources are available

Buy Now
Questions 34

In a large industrial business, an on-going system development project faces a previously identified risk. The risk is adequately managed by the risk manager, however there is still residual risk.

What should the risk manager do?

Options:

A.

Update the risk register accordingly and review it in regular project meetings.

B.

Accept the risk because residual risks are often low.

C.

Ask a subject matter expert (SME) to assess the residual risk and take action.

D.

Assign a risk owner and set it as high priority and high impact.

Buy Now
Questions 35

The project’s customer has stated the project must be completed by a date indicated as the P90 date established on the Monte Carlo analysis. What should the project manager do to ensure the P90 date is met?

Options:

A.

Update the assumptions/exclusions register

B.

Hire more resources and crash the schedule

C.

Perform a qualitative risk analysis for the project

D.

Mitigate risks identified on the sensitivity analysis

Buy Now
Questions 36

An agile project manager has noticed their team's declining morale, mistrust, and isolation over the last 6 months of working on a project. What should the agile project manager do to enhance productivity and create a cohesive team culture?

Options:

A.

Introduce performance standards and evaluation methods.

B.

Clarify project goals and project contract constraints.

C.

Promote cross-training and mentoring among team members.

D.

Develop a reward system related to position and years of experience.

Buy Now
Questions 37

What should the risk owner use as an effective information-gathering technique during the planning session?

Options:

A.

Monte Carlo analysis

B.

Update risk register

C.

Brainstorming

D.

Cost and time estimating

Buy Now
Questions 38

A risk manager documents the causes in the risk register and needs to ensure the risk is adequately described. What is critical for the risk manager to consider when describing the causes?

Options:

A.

Each cause has a degree of uncertainty

B.

Each cause has well defined owner

C.

The causes represent actual conditions

D.

The causes must be validated by the risk owner

Buy Now
Questions 39

A project manager managing a high-risk rating project was just informed that one of the key project resources has decided to leave the organization. The project manager asks the risk manager for their recommendations. The risk manager previously identified this as a risk and had created a transition plan to enable another resource to carry out the same duties. The risk manager was informed that by transitioning the responsibilities to the new resource, new risks to the completion dates of other project-related tasks appear.

What should the risk manager advise the project manager?

Options:

A.

Escalate the new risks immediately to the project stakeholders to ensure proper risk communication is in place.

B.

Address these secondary risks as per the risk management plan

C.

Apply a risk acceptance strategy to the new risks as there is no risk response plan.

D.

Update the risk management plan with the new probabily/impact and change the response.

Buy Now
Questions 40

A risk manager has to inform a project sponsor of the expected duration of an entire project. The project has three mam tasks, each with different probabilities of duration.

Which analytical tool should the risk manager use?

Options:

A.

Probability tree diagram

B.

Ishikawa diagram

C.

Decision tree analysis

D.

Monte Carlo simul-ation

Buy Now
Questions 41

In a highly dynamic project environment, the project manager is known to have project risks as a permanent agenda item in their periodic project progress meetings. How will this help improve the project's risk management activities? (Choose 3)

Options:

A.

By helping to monitor variances and trends frequently throughout the project

B.

By helping to determine the overall project risks

C.

By helping the lessons learned from previous risks to be efficiently utilized

D.

By helping to update the project scope statement document

E.

By helping update the risk register and close out expired risks

 

Buy Now
Questions 42

A project team does not understand why a very low probability risk occurred during project execution. The team was especially vigilant about planning for this type of risk during the risk planning phase. The project has been delayed by 2 months, and the stakeholders are considering canceling the project. The risk manager needs to demonstrate that the project can be concluded.

Which analysis should the risk manager perform to demonstrate this to the stakeholders'?

Options:

A.

Monte Carlo analysis

B.

Pareto analysis

C.

Ishikawa analysis

D.

Qualitative risk analysis

Buy Now
Questions 43

In a large enablement project with strict time lines, risks need to be closely monitored. The risk manager publishes reports comparing planned enablement sessions with actual enablement sessions, which help identify potential risks to be addressed.

Which technique is the risk manager using?

Options:

A.

Variance analysis

B.

Residual impact analysis

C.

Sensitivity analysis

D.

Reserve analysis

 

Buy Now
Questions 44

A certain risk is identified for a major project, and the risk response is planned. However, the analysis reveals a high probability for a secondary risk which will be tolerated based on the organization's risk thresholds. The secondary risk is subsequently registered. During project execution, the primary risk occurs, the planned action is taken, and the secondary risk emerges

What two actions should the risk owner take? (Choose two.)

Options:

A.

Implement the secondary risk response and update the project documents.

B.

Conduct meeting with all stakeholder to agree on post impact solutions.

C.

Set the corresponding trigger conditions to the secondary risk.

D.

Engage the project manager to authorize the secondary risk's response.

E.

Update and communicate assessments of the secondary risk's impact.

Buy Now
Questions 45

A project team working on a large software deployment project for a few months has been able to prevent a technical risk from occurring. However, an incident took place and triggered the technical issue.

What should the risk manager do?

Options:

A.

Execute the risk response plan defined for the risk.

B.

Postpone the software launch to sort out the technical issue.

C.

Assess the impacts and define the response actions with the subject matter experts (SMEs).

D.

Meet with the project manager to revisit the project schedule.

Buy Now
Questions 46

The stakeholders of a building construction project are not comfortable with the project manager's handling of the project as they believe there is a financial risk. The project manager asks the risk manager to assist in demonstrating to the stakeholders that the project risks are under a tolerable threshold.

What should the risk manager do first to demonstrate this to the stakeholders?

Options:

A.

Gather other project risk historical information.

B.

Gather and reconcile project risk report data.

C.

Work with the sponsor to convince the risks are under control.

D.

Work with the team to ensure the project is in good health.

 

Buy Now
Questions 47

At an oil and gas company, a major unified management information system is to be implemented. The project manager noted that risks gathered from the organization's business functions are not properly identified and categorized, making it difficult to develop an effective risk response.

How should the project manager handle this situation?

Options:

A.

Outsource conducting the risk response plan to risk consultants.

B.

Ask functional managers to improve their risk register and process.

C.

Adjust the risk response plans to effectively handle the identified risks.

D.

Coach the functional groups on how to properly conduct the process.

Buy Now
Questions 48

A risk manager has noticed that response actions are not working as expected when a risk occurs, mainly because the risk triggers are not well-defined. Which tool should the risk manager use to facilitate risk trigger identification in the upcoming risk review assessment?

Options:

A.

Risk burndown chart

B.

Ishikawa diagram

C.

Risk breakdown structure (RBS)

D.

Affinity diagram

Buy Now
Questions 49

An organization with a portfolio of unique business functions kicks-off a performance improvement project across the entire organization. There are a large number of stakeholders the project team will need to consider during risk identification.

What three actions should the risk manager ensure the project team performs during risk identification? (Choose 3)

Options:

A.

Develop checklists based on historical information

B.

Conduct interviews, meetings, and focus groups

C.

Assign a different risk manager for each portfolio unit

D.

Employ brainstorming to generate spontaneous ideas

E.

Perform qualitative and quantitative risk analyses

 

Buy Now
Questions 50

An agriculture government agency faces different challenges with farmers and landlords In implementing its ambitious growth strategy. The agency decided to establish an enterprise risk management unit to identify risks, analyze risks, and provide a handbook showing how to handle the surrounding uncertainty.

What should the risk management expert recommend the agency do first to identify risks and develop the handbook?

Options:

A.

Follow standard risk Identification tools dedicated for agriculture and tailor them to the environment.

B.

Hire an agriculture expert who can develop the required handbook and discuss it with the agriculture minister.

C.

Prepare a list of the key resources that will be used to compile a risk management plan.

D.

Conduct meetings, facilitated workshops, and interviews with stakeholders to identify potential risks.

Buy Now
Questions 51

A risk manager was recently hired to assist with a mid-sized infrastructure project. The risk manager becomes aware that they have an inexperienced project team.

What two items should the risk manager have their team review in order to prepare for an upcoming risk identification workshop? (Choose two.)

Options:

A.

Scope of work and requirements

B.

Monte Carlo analysis from a similar project

C.

List of pre-approved contractors

D.

Organization chart for city permit department

E.

Risk management plan

Buy Now
Questions 52

A risk manager administered a pre-workshop risk survey in preparation for the upcoming workshop. The workshop invitees participated in the survey and submitted many risks encompassing all project phases and risk areas. The risk manager sorts risks by similarities and categories for the workshop.

What should the risk manager do next to visually organize the risks?

Options:

A.

Develop an affinity diagram

B.

Perform the analytical hierarchy process

C.

Perform a SWOT analysis

D.

Assign probability and impact

Buy Now
Questions 53

While performing risk identification exercises, the risk manager often encounters biases from the project team. How can the risk manager accurately identify what will trigger a risk?

Options:

A.

Remind the project team to keep an open mind

B.

Review the results with the project manager afterward

C.

Review published operational experience reports

D.

Use the mean answers provided by the project team

 

Buy Now
Questions 54

A risk management professional is in the process of categorizing risks when a subject matter expert (SME) suggests categorizing the risks by their impact to the project objectives. Why should the risk management professional use this approach?

Options:

A.

To enable the team in identifying the specific causes of risks associated with project objectives.

B.

To ensure that project priorities are being appropriately factored into risk response plans.

C.

To determine there more attentive project leadership and organizational involvement is needed.

D.

To assign risks and risk severities to functional discipline and departments effectively.

Buy Now
Questions 55

The project team has correctly identified, assessed, and planned responses for a project's risks. The risk manager is required to prepare a quarterly report on the performance of managing the risks.

What are two options the risk manager should consult for the analysis? (Choose two.)

Options:

A.

Proximity dales for open risks

B.

Backlog of change orders to be submitted to client

C.

Risks that have materialized and the overall risk profile

D.

Number of schedule baseline changes approved

E.

Risks due to the number of claims submitted to the client

Buy Now
Questions 56

Several key stakeholders approach the project manager with concerns. The stakeholders have received feedback from local businesses that have reported a reduction in customers because of construction activities at the worksite, and they plan to submit a claim to the municipality to fine the project manager's company.

How should the project manager address this concern?

Options:

A.

Evaluate the risk with the team and update the issueing

B.

Discuss the concern with the local business owners.

C.

Update the key risks and perform a quantitative risk analysis.

D.

Adjust construction work hours to after business hours.

Buy Now
Questions 57

A risk manager completed risk response planning for a project that is currently in the execution phase. During a periodic review of the risk register, the project manager recognizes that some key secondary risks have not been considered.

Who should the project manager hold accountable for missing the risks?

Options:

A.

The audit team

B.

The risk manager

C.

The risk owners

D.

The discipline engineers

Buy Now
Questions 58

A project manager has been assigned to a project that is just starting. The organization has a very low risk appetite towards this project due to constraints on budget and schedule. The project stakeholders are very engaged on the project and want to ensure that there is clear visibility on the project risks and progress.

How should the project manager handle stakeholder expectations?

Options:

A.

Add buffers to the schedule to accommodate risk.

B.

Ensure the risk register includes all identified risks.

C.

Discuss the risk response strategies with the stakeholders.

D.

Develop a communication plan to share updates on risks.

Buy Now
Questions 59

The risk manager is facilitating risk planning activities with the team. The team is documenting all the check points along the way that might indicate delays on critical deliverables.

What is this an example of?

Options:

A.

Risk responses

B.

Risk triggers

C.

Risk registers

D.

Risk categories

Buy Now
Questions 60

A risk manager recently had to take an unexpected leave of absence. An interim risk manager has been tasked with completing risk planning for a new project. The interim risk manager has been provided with a strength, weaknesses, opportunities, and threats (SWOT) analysis that was completed during a project kickoff meeting several weeks ago.

What should the interim risk manager do to derive actionable risk responses from the SWOT analysis?

Options:

A.

Determine risks from the SWOT analysis and break them down into threats and opportunities.

B.

Work with the project sponsor to understand which items they would prioritize from the SWOT analysis.

C.

Conduct an extensive review with the project team to ensure all SWOT items can be mitigated or eliminated.

D.

Input the items identified on the SWOT analysis into the project's risk register for consideration as-is.

 

Buy Now
Questions 61

Upon reviewing the risk analysis results, the project manager notices several risks that occur more frequently than others. What should the project manager do?

Options:

A.

Reduce the probabilities of those risks on the risk register

B.

Transfer ownership of those risks to the customer

C.

Implement the risk handling strategies for those risks

D.

Request additional management reserve for those risks

Buy Now
Questions 62

A risk manager has been assigned to a new project and learns that stakeholders and project team members are spread across multiple time zones. Furthermore, many project team members have not worked together in the past. These items are identified as potential risks and added to the risk register.

How should the risk manager improve collaboration during risk planning?

Options:

A.

Gather risk information from all parties and compile all submissions into a strength, weaknesses, opportunities, and threats (SWOT) analysis template.

B.

Create a repository for project documents and related artifacts that can be accessed by all parties.

C.

Communicate program metrics to all parties and create a scorecard to measure the effectiveness.

D.

Work with the project manager to develop a start-up workshop and colocate the team if permitted.

 

Buy Now
Questions 63

The project manager reviews project risks with the risk manager to update, monitor, and close risks in the risk register. The project manager determines one of the risks has a residual risk.

How should the risk manager document the impact of the residual risk?

Options:

A.

Utilize change management tools to request a budget increase from the project sponsor and update the risk register.

B.

Change the risk identification and description on the risk register to reflect the fact that the residual risk has materialized.

C.

Close the risk's status on the risk register since the residual risk has now materialized.

D.

Review the impact of the residual risk against the budget reserves and document the update in the risk register.

 

Buy Now
Questions 64

A home solar panel project has many internal and external stakeholders including households, businesses, community groups, electric utility companies, local government officials, landlords, and investors. What should the project manager do when engaging stakeholders?

Options:

A.

Include all stakeholders in the project's governance.

B.

Communicate response strategies to all stakeholders.

C.

Ignore any risks beyond stakeholders' tolerance.

D.

Consider stakeholders' positions and opinions regarding the project’s output.

Buy Now
Questions 65

A newly assigned risk manager realizes that a project has unrealistic funding and low resources. Which document should the risk manager review?

Options:

A.

Risk assessment criteria

B.

Project management plan

C.

Project assumptions

D.

Risk management plan

 

Buy Now
Questions 66

A project team is presenting a delivery plan to a client. Some of the client's experts do not feel comfortable with some activities at a critical stage. The experts ask to change the plan and present a better alternative.

What should the risk manager do first?

Options:

A.

Review and update the project quality management plan.

B.

Conduct a risk assessment process for the critical stage.

C.

Create a more detailed work breakdown structure (WBS).

D.

Add additional time to the delivery plan to cover issues.

 

 

Buy Now
Questions 67

A new risk manager has been assigned to a project experiencing delays, quality issues, low performance, and client complaints. The work is being completed with the

client's vendor, which apparently has been causing all of the issues.

What should the risk manager do first?

Options:

A.

Enhance risk identification.

B.

Review the contingency reserves.

C.

Create a risk response plan.

D.

Review the risk registry.

Buy Now
Questions 68

A project manager has determined that they cannot outsource work nor eliminate the scope. They also discover that they cannot buy insurance or mitigate the risk.

What should the project manager do?

Options:

A.

Avoid the risk

B.

Transfer the risk

C.

Ignore the risk

D.

Accept the risk

Buy Now
Exam Code: PMI-RMP
Exam Name: PMI Risk Management Professional (PMI-RMP) Exam
Last Update: Jun 15, 2025
Questions: 227
$66  $164.99
$50  $124.99
$42  $104.99
buy now PMI-RMP