Summer Special Sale - Limited Time 60% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: 575363r9

Welcome To DumpsPedia

PMI-ACP Sample Questions Answers

Questions 4

A Kanban team is struggling to prioritize and determine which tasks to handle first according to value.

What should the team do to improve this situation?

Options:

A.

Involve their product owner.

B.

Review their work in progress (WIP) limits.

C.

Use class of service.

D.

Measure their lead time.

Buy Now
Questions 5

What should the team do?

Options:

A.

Advise the product owner that the story will have to wait until the next sprint.

B.

Work extra hours to complete the story and satisfy the customer's requirements.

C.

Break down the story into smaller increments and negotiate other stories on the sprint backlog.

D.

Increase the length of the sprint to accommodate the story.

Buy Now
Questions 6

What is the disadvantage of using velocity as a measure of team efficiency in agile approaches?

Options:

A.

Capacity planning will not be accurate.

B.

Inaccurate pressure on customers.

C.

Quality increases while output decreases.

D.

Delivery speed increases while morale decreases.

Buy Now
Questions 7

What should the team have done to prevent this?

Options:

A.

Reprioritized requirements prior to committing to iteration work

B.

Ensured that requirements remained stable during the iteration cycle

C.

Had stakeholders focus on items created after the product backlog was initially built

D.

Worked on features rather than a set of components

Buy Now
Questions 8

A development team is calculating the number of story points they have completed at the end of an iteration. Although quality assurance (QA) passed and successfully demonstrated one feature, it is not being included in the release package.

Should the team add the feature's story points to their burndown chart?

Options:

A.

Yes because the story has been tested and accepted by the business as per the definition of done (Do

B.

Yes, because the development work is complete and quality assurance (QA) and release are external dependencies.

C.

No. any work that is not released cannot be considered complete as per the definition of done (Do

D.

No, because the product owner has not reviewed the release implementation checklist for potential issues.

Buy Now
Questions 9

An agile team has defined their definition of done (DoD) for a sprint. However, during the demo, the product owner is not sure if a user story can be marked as done.

Select the most appropriate sequence of activities that would need to be completed to meet a well-defined, mature definition of done (DoD).

Options:

A.

Code is unit tested, code is peer reviewed, functional testing is passed, business testing is passed, and all acceptance criteria are met.

B.

Code is unit tested, all acceptance criteria are met, business testing passed, code is merged, code is peer reviewed, and documentation is updated.

C.

All acceptance criteria are met, documentation is updated, functional testing is passed, business testing is passed, and code is peer reviewed.

D.

Code is unit tested, all acceptance criteria are met, business testing is passed, functional testing is passed, code is merged, and documentation is updated.

Buy Now
Questions 10

For what is the MoSCoW method used?

Options:

A.

Estimating story size

B.

Prioritizing stories

C.

Validating a product

D.

Tracking progress

Buy Now
Questions 11

What could help eliminate misunderstandings?

Options:

A.

Agree on requirements with all stakeholders

B.

Begin planning every four iterations

C.

Consider previous sprint demo feedback when planning the next sprint

D.

Include the reasons for the project in the contract

Buy Now
Questions 12

A Product Owner new to the role is very enthusiastic about an agile project with an energetic team.

What should be done first to ensure successful delivery of the product?

Options:

A.

Hold a meeting with the team and the Product Owner to develop the team charter, working agreement, guiding principles, and product vision

B.

Ask the Product Owner to create the project vision and charter, and then discuss the guiding principles with the team

C.

Hold a meeting during which the team can present the project charter, high-level project plan, and team values to the Product Owner

D.

Send the Product Owner to formal Product Owner training where the Product Owner can learn how to create a product vision

Buy Now
Questions 13

What should the agile practitioner have done to ensure stakeholder satisfaction?

Options:

A.

Communicated early and often, as outlined in the communications matrix

B.

Ensured engagement among stakeholders and the product owner

C.

Conducted additional stakeholder reviews and demos

D.

Worked with the product owner to prioritize user stories

Buy Now
Questions 14

A servant leader is leading a high-visibility project to deliver a new product. The servant leader has been able to build a cross-functional team and create a team space where the team is collocated. The servant leader started receiving frequent visits from a company director, who continually asks a specific team member questions about project progress. The conversations are distracting the team from their goal.

What should the servant leader do?

Options:

A.

Coach the company director on agile approaches and good practices.

B.

Ask the product owner to speak to the director because their visits are delaying the project.

C.

Ask the director and team member to leave the room so they can have a private conversation.

D.

Coach the team member on how to report progress to directors and executives.

Buy Now
Questions 15

In a project to develop a supply-and-demand scenario planning tool, the team aims to streamline development and rapidly deliver features. Which approach best supports quick feature delivery while maintaining quality? (Refer to An Excerpt from the Quality Management Plan)

Options:

A.

Implementing a systematic approach to automate integration, testing, and deployment activities

B.

Increasing the frequency of stakeholder meetings to gather feedback on feature priorities

C.

Leveraging regular reviews, feedback loops, and lessons learned to adjust at key milestones

D.

Organizing training sessions for end users to ensure effective utilization of the planning tool

Buy Now
Questions 16

During its first sprint, a new Scrum team realizes that it has insufficient team members with test automation skills to effectively complete its stories.

What should the team do?

Options:

A.

Cross-train some members in the automation framework to broaden their capacity with that skill

B.

Ask the product owner to add team members to boost this particular skill set

C.

Send a member to automation framework training when funds are available

D.

Avoid using test automation by swarming on the testing tasks and using manual testing

Buy Now
Questions 17

What should the team do?

Options:

A.

Work longer hours to complete more of the support backlog.

B.

Work support tickets in the order in which they were received.

C.

Place tickets on hold until the team completes an analysis of the backlog to identify and resolve systemic issues.

D.

Add members to the support team.

Buy Now
Questions 18

A globally distributed project team is using email and phone calls as the only way to share information. Delays in resolving issues often occur due to misinterpreted communications, leading to a lower team velocity.

What steps should the project leader take to improve knowledge sharing?

Options:

A.

Meet individually with each team member to identify the issues and relay information to the remaining members through status reports.

B.

Establish a live video feed between the dispersed teams to enable spontaneous engagement and collaboration on issues.

C.

Request that the customer co-locate the team to overcome the communication issues, as this is the only method to ensure agility.

D.

Inform the customer of the challenges and lower velocity of the project to accommodate for the slower delivery pace.

Buy Now
Questions 19

Options:

A.

It trended ahead of schedule and completed everything on time

B.

It took more time than expected and had to be lengthened

C.

It trended behind schedule and did not complete everything on time

D.

It took less time than expected and had to be shortened

Buy Now
Questions 20

An agile team is struggling to achieve their goal during the first release due to an unstable environment beyond the authority of the product owner. Close to the end of the current sprint, the release manager resigns and a new person takes over.

What should the Scrum Master do?

Options:

A.

Report the issue to the product owner and request help.

B.

Let the new release manager participate in the daily standup.

C.

Invite the new release manager to the sprint demo and ask for help.

D.

Send a status report to the release manager highlighting the issue.

Buy Now
Questions 21

Project stakeholders are finding it difficult to know the real-time status of who has been assigned to various stories and the status of each work item.

What should the agile project manager do?

Options:

A.

Use an information radiator to help increase the transparency of work for key stakeholders.

B.

Send status updates whenever the stakeholders request them.

C.

Hold Scrum meetings more frequently to ensure stakeholders are well informed.

D.

Instruct the team to focus on their own assignments rather than the work of others.

Buy Now
Questions 22

A new stakeholder has recently joined a project. During a meeting with the Scrum Master, the new stakeholder tries to understand the status of the project and the remaining tasks for completion.

How should the Scrum Master inform the new stakeholder?

Options:

A.

Show the stakeholder the latest release breakdown for the project.

B.

Invite the stakeholder to attend the next sprint review meeting.

C.

Show the stakeholder the progress radiators for the project.

D.

Invite the stakeholder to attend the next sprint planning meeting.

Buy Now
Questions 23

What should a Scrum Master do when an agile team member is behind on their tasks?

Options:

A.

Ask the team for suggestions.

B.

Move the tasks to another team member who has spare capacity in the sprint.

C.

Hold a one-on-one meeting to encourage the team member to meet task commitments.

D.

Inform key stakeholders.

Buy Now
Questions 24

An agile team is continuously interrupted by stakeholders wanting to ask product backlog questions. Distractions can have a negative impact on value delivery and quality.

Who is responsible for protecting against distractions?

Options:

A.

Product owner

B.

Project manager

C.

Agile leader

D.

Developers

Buy Now
Questions 25

Options:

A.

Establish a common vision and success criteria and involve all the stakeholders in the iteration reviews.

B.

Invite stakeholders for the iteration reviews but do not include new stakeholders which may limit project success.

C.

Involve all the stakeholders in iteration reviews but do not entertain all expectations of all stakeholders.

D.

Communicate issues to all stakeholders via email and only communicate risks to internal stakeholders.

Buy Now
Questions 26

A scrum team is working on an important project with a short deadline. To save time and reduce overhead, the product owner proposes that the regular sprint reviews should be cancelled and replaced with a review of each release according to the release plan.

What should the scrum master do?

Options:

A.

Review the release plan with the product owner and invite the stakeholders to a series of release reviews.

B.

Review the metrics and the process to determine where the overhead could be further reduced to speed up delivery.

C.

Explain to the product owner why the sprint reviews are now replaced by release reviews as inspect and adapt is a key principle in Scrum.

D.

Explain to the product owner that getting feedback early and often from stakeholders is important so necessary changes can be made quickly.

Buy Now
Questions 27

During initial planning, a project team investigates several approaches to building new application software, emphasizing the most valuable deliverables. The team needs to convince stakeholders and win their approval.

How can the project team achieve this?

Options:

A.

Use a successful platform on which several object-oriented products have been developed in the past.

B.

Create a quick mock-up of the product to serve as a visual tool and adjust it until consensus is reached.

C.

Include brief exploratory iterations, proof-of-concept (POC). to reduce project risk at the beginning of every project cycle.

D.

Deliver an iteration planning diagram, allowing a 2-week refactoring period at the end of the project.

Buy Now
Questions 28

What should the project team do next?

Options:

A.

Estimate the project team's capacity.

B.

Determine how much work can be delivered.

C.

Calculate how much work will fit into the next iteration.

D.

Estimate items in the product backlog.

Buy Now
Questions 29

During an agile team retrospective, some junior team members discussed an approach that could improve the overall team performance.

How should the agile practitioner handle the recommendation?

Options:

A.

Record the suggestion to be considered for future projects.

B.

Invite the team to evaluate the suggestion and measure the effectiveness of the implementation.

C.

Let the product owner consider the proposal and decide whether to adopt the suggested practice.

D.

Let the team's senior members decide whether to adopt the suggested practice.

Buy Now
Questions 30

One of the main stakeholders of a project is new to Scrum. The stakeholder asks what to expect in the sprint retrospective.

How should the product owner respond?

Options:

A.

Stakeholders have the opportunity to add features to the sprint.

B.

Team members determine if there are any impediments preventing them from meeting the sprint goal.

C.

The product owner explains which product backlog items have been done and which have not.

D.

Team members identify ways to improve and make plans to implement these improvements.

Buy Now
Questions 31

In an adaptive environment, project managers use their skills and expertise to help the team adapt to changing circumstances and deliver to their stakeholders. While some agile practitioners may argue that the role of a project manager is not needed in self-organizing teams, pragmatic agile practitioners and organizations recognize that project managers can add benefit in many situations. The key difference is that their roles and responsibilities may look somewhat different in an adaptive environment.

What are some of the practices a project manager can bring to an adaptive environment?

Options:

A.

Building a collaborative decision-making environment with key stakeholders, teams, and sponsors.

B.

Ownership of detailed project planning, user histories, retrospectives, showcases and metrics board

C.

Ensuring agile values and principles are adopted by all teams involved in delivery of the project.

D.

Developing the project charter, writing the project plan, and following the achievement of all milestones.

Buy Now
Questions 32

An experienced product owner presents the epics and corresponding stories during a release planning session with the established team. The executive sponsor asks the team when the features will be delivered.

What should the agile team do?

Options:

A.

Evaluate how much can be delivered based on the Scrum Master's estimation

B.

Identify a set of user stories based on the team's velocity

C.

Initiate an estimation session

D.

Consult historical data for project completion

Buy Now
Questions 33

Why should an agile coach model agile principles and behaviors, become self-aware, and be present?

Options:

A.

To better listen, serve, and help the team grow their strengths individually and as a team

B.

To convince people what they need to do

C.

To help better disguise the command and control approach

D.

To understand team dynamics and develop a high performing team

Buy Now
Questions 34

An executive notices a Kanban board in a highly visible location and expresses concerns to the project manager that too many people will see it. What should the project manager do?

Options:

A.

Cover up the Kanban board every time the project team is not actively updating it.

B.

Demonstrate how the Kanban board is necessary for assigning proper ownership for the work that has been done.

C.

Explain that the Kanban board enables the team to complete the work and increases transparency on work that is not done.

D.

Remove the Kanban board immediately and place it in a location where it is not visible.

Buy Now
Questions 35

An agile practitioner is working on a project to migrate data from computer systems to another location. To accomplish this task, they need to run four activities sequentially that different teams are performing. The teams are migrating two systems per day, but the agile practitioner thinks that three systems should be done per day.

What can be done to improve process efficiency?

Options:

A.

Use burndown charts to find gaps. delays, and constraints in the current process and develop a plan to reduce or remove them.

B.

Use value stream mapping to find gaps, delays, and constraints in the current process and develop a plan to reduce or remove them.

C.

Use Pareto analysis to find gaps, delays, and constraints in the current process and develop a plan to reduce or remove them.

D.

Use root cause analysis to find gaps, delays, and constraints in the current process and develop a plan to reduce or remove them.

Buy Now
Questions 36

What should the practitioner do?

Options:

A.

Post and discuss rises in the burndown chart

B.

Adjust story points to account for technical debt

C.

Log technical debt as an impediment

D.

Add refactoring tasks to all stories

Buy Now
Questions 37

A project was delivered in a foreign country for a big customer, but there are a lot of complaints about the way the functionality was implemented. Now there is a new project to fix the defects of the first one.

What strategy should be used to deliver it successfully?

Options:

A.

Talk with the old project manager to learn about the problems they encountered and the lessons learned.

B.

Suggest organizing a meeting in order to analyze the situation and work to find a strategy.

C.

Analyze all defects and change requests carefully to understand their root causes and act accordingly.

D.

Suggest an iterative approach including timely engagement of all key stakeholders and hold regular review meetings.

Buy Now
Questions 38

The lead developer informed the team that they have learned of some possible integration challenges in creating customer dashboards using the architecture the team has chosen.

What should an agile practitioner do?

Options:

A.

Conduct an architectural spike immediately to decide how the functionality will be determined.

B.

Work with the product owner to avoid the risk by determining if their requirements could be met with reporting or a similar functionality.

C.

Continue the priority defined by the product owner on the backlog for the functionality they determined to be the highest priority.

D.

Identify this as a risk, decide on the response, and prioritize spike to determine the solution on the product backlog.

Buy Now
Questions 39

The coach on a new agile team notices that one team member is influencing most of the team's decisions. What should the coach do?

Options:

A.

Replace the team member with a more collaborative individual.

B.

Permit the team member to continue influencing because agile teams are self-organizing.

C.

Ask probing questions to other team members to encourage dissenting viewpoints.

D.

Intervene if the team's velocity drops.

Buy Now
Questions 40

During an interview for an agile team lead for a global company, a candidate is asked: "How do you ensure your project is aligned with the stakeholders' priorities?"

How should the candidate respond?

Options:

A.

Engage the change management team to determine prioritization of the backlog.

B.

Allow the stakeholders to decide on the priority and build the backlog.

C.

The entire team should discuss and prioritize the backlog factoring in stakeholder input.

D.

Only the agile team lead and team need to decide how to prioritize the project deliverables.

Buy Now
Questions 41

Several team members are new to agile and there is a lot of confusion. It seems everyone is coming in with different experiences and following their own agendas. The scrum master decided to hold a presentation on core agile principles and values.

What should the scrum master emphasize to the team during the presentation?

Options:

A.

The value of agile ceremonies and methods

B.

Performance and chain of command

C.

Product deliverables, procedures and features

D.

Collaboration, value delivery and shared mindset

Buy Now
Questions 42

An agile coach has been hired to improve the performance and quality of developed software. The coach performed an analysis of the software and discovered an excessive number of escaped defects, leading to external failures.

How can the agile coach effectively address and correct defects in the software development process while maintaining predictability and keeping workloads within capacity?

Options:

A.

Work with the team to create explicit rules such as coding and quality standards and testing policies.

B.

Discipline the team members and institute status meetings with penalties for any future escaped defects.

C.

Hire more generalized specialists because the current team members cannot keep up with the pace.

D.

Apply work in process (WIP) limits so the developers are not pressured to release code that is problematic.

Buy Now
Questions 43

What should the Scrum Master do?

Options:

A.

Ask the product owner how upper management's comments can be redirected.

B.

Direct the developer team to ignore the phone calls and emails.

C.

Ask the product owner to enter the requests into the product backlog as high priority.

D.

Personally respond to upper management's phone calls and emails.

Buy Now
Questions 44

A backlog for a project has been prioritized and a sprint has begun. A security issue has been revealed that needs to be addressed or large security vulnerabilities will be exposed.

How should the project manager proceed?

Options:

A.

Consult with the product owner to prioritize the new work at a higher level.

B.

Consult with the project sponsor and project team to resolve the issue.

C.

Consult with the project team to rework the existing estimates.

D.

Consult with the product owner and project team.

Buy Now
Questions 45

An agile facilitator is helping a team. The team is taking too long in each daily coordination meeting, and the facilitator is beginning to view the time as unproductive.

What should the agile facilitator do to help the team?

Options:

A.

Reduce the number of participants in the daily coordination meeting so only one representative for each user story or area of expertise can participate each day.

B.

Change the structure of the daily coordination meetings so team members only comment on the blockers they face during the day.

C.

Let team members decide how to execute the meeting because they are self-organized and should know what works for them.

D.

Pay attention to the comments of each team member during the meeting and intervene every time they deviate from the objective of the meeting.

Buy Now
Questions 46

An agile team member from a cross-functional team has been unable to complete assignments due to tasks assigned by the functional manager.

What should the Scrum Master do?

Options:

A.

Dismiss the team member

B.

Discuss the situation with the functional manager

C.

Report the functional manager to the project sponsor

D.

Demand that the functional manager respect the project charter

Buy Now
Questions 47

The systems integrator for an enterprise resource planning (ERP) project has been onboarded. During an iteration planning session, the team determines that the next highest priority item will take longer than expected to complete in the current sprint.

What should the agile practitioner do next?

Options:

A.

Schedule a meeting with the product owner to review the sprint priorities.

B.

Put the high-priority item back into the product backlog.

C.

Extend the sprint end date to accommodate the high-priority item.

D.

Ask the project sponsor to add more resources to ensure timely completion.

Buy Now
Questions 48

An agile project manager is working on a project to develop a customer service website. The project manager is organizing a workshop to plan the next release: To add the feature of receiving and resolving customer complaints. Which two actions should the project manager ask the team members to take before the workshop? (Choose two.)

Options:

A.

Prepare an effort estimation for each story based on their technical expertise.

B.

Compile a list of ideas to improve the velocity of the team so they can plan more story points in the next sprint.

C.

Prepare a list of tasks required to accomplish the goal and the order in which they should be executed.

D.

Read and identify user stories from the backlog that will contribute to accomplishing the goal.

E.

Consider the possible risks of each selected user story and the value they add for the final user.

Buy Now
Questions 49

The productivity of an agile team has fallen significantly in the last sprint. The team members have not mentioned any impediments but seem to be fatigued.

What should the agile practitioner do?

Options:

A.

Discuss the issue with the team at the next daily standup meeting.

B.

Discuss the issue with the team at a special meeting for this purpose.

C.

Discuss the issue with the project stakeholders at a special meeting for this purpose.

D.

Discuss the issue with the team at the next project retrospective.

Buy Now
Questions 50

The first project vision statement meeting for a newly formed team did not achieve its outcome. Lack of participation combined with conflicting views of those who participated led to disagreement on how to proceed.

How can the team improve their collaboration?

Options:

A.

Set clear expectations and allow everyone to contribute.

B.

Prepare the project vision statement and then present it to the team.

C.

Ask senior management to address the situation.

D.

Seek assistance from the scrum master to mediate the conflict.

Buy Now
Questions 51

During a sprint review, the Product Owner identifies a required improvement for a feature’s user interface (UI) delivered during the sprint.

What should the Product Owner do next?

Options:

A.

Create a user story for this new improvement and put it in the product backlog for prioritization and validation by the customer

B.

Create a user story for this new improvement and prioritize it for the next sprint

C.

Document it as a requirement creep

D.

Ask the team to take on additional story points to improve the UI

Buy Now
Questions 52

An employee just received an Agile certification and has been promoted to team leader. They are working on a project that is experiencing issues with late deliverables. After monitoring project progress, they notice that one impediment is continuously repeated at start of each phase, affecting team's productivity.

How should the team leader exhibit servant leadership?

Options:

A.

By being a change agent

B.

By being the authority on processes

C.

By being a coach

D.

By removing impediments

Buy Now
Questions 53

A team is building a product in three-week iterations. During the last retrospective, it was identified that there was a 20% increase from previous iterations in the number of reported defects and change requests.

Since this is causing the product's value to decrease, what should the team do?

Options:

A.

Reevaluate the duration of the cycles, as faster cycles may allow for earlier detection of defects.

B.

Run a sprint to clear all reported defects before taking new stories.

C.

Change the control mechanism so that items are better tested before delivery.

D.

Increase the opportunities to confirm common understanding with the client.

Buy Now
Questions 54

A team member starts discussing a project roadblock during a daily coordination meeting. The team discusses details of the impediment, which takes up most of the meeting time.

What should the agile facilitator do?

Options:

A.

Dismiss the rest of the team from the meeting to focus on the problem reported by the team member

B.

Ask the team member to wait to discuss until the next daily coordination meeting, the team needs to review the current status.

C.

Inform the team that the meeting will be extended so there is time to hear what the team member is reporting

D.

Stop the team politely and suggest scheduling another meeting to discuss this specific matter.

Buy Now
Questions 55

An Agile Project Manager observes that the Scrum team is falling behind on the completion of a particular sprint.

What should the Agile Project Manager do?

Options:

A.

Facilitate by providing directions to the team about how they can get back on track.

B.

Request key stakeholders to extend the sprint to enable the team to complete their tasks on time.

C.

Ask the customers to help the team complete the testing on time to be able to finish their tasks on time.

D.

Understand the impediments and facilitate issue resolution to enable the team to succeed.

Buy Now
Questions 56

Following approval of a business case, a company will introduce a new mobile app for customers to place orders. Time to market is a key concern. The product has entered into the 3rd iteration, but the team is concerned because they feel the technical designs do not meet the agreed-on definition of done (DoD). An agile coach has been hired to help validate product delivery against business requirements.

What should the agile coach do?

Options:

A.

Incorporate quality assurance in the planning stage of product development.

B.

Schedule a dedicated meeting with the product owner to tackle this roadblock.

C.

Conduct a brainstorming exercise to get to the root of the issue and devise action plans.

D.

Conduct a retrospective meeting at the end of the current iteration to identity necessary improvements.

Buy Now
Questions 57

What should the Scrum Master do next?

Options:

A.

Monitor the threats and risks while allowing the team member to multitask on both projects

B.

Assign more resources to the sprints to compensate for the absences of the team member

C.

Ensure that the threats and risks are communicated and addressed

D.

Assign fewer stories to the sprints so that the team member can still meet sprint goals

Buy Now
Questions 58

A key resource is switching between projects to obtain more visibility and acclaim. However, project work has grown and become a burden.

What should the agile project leader do?

Options:

A.

Add more resources to projects to ensure work sharing.

B.

Encourage the resource to undergo time management training.

C.

Ask management to ensure that the resource is available to only one project at a time.

D.

Allow the resource to continue switching between projects to deliver high customer value.

Buy Now
Questions 59

After some iterations, the Agile practitioner observes that the team is self-organizing in small knowledge silos.

Which action should be taken regarding the team's behavior?

Options:

A.

Raise the concern to upper management.

B.

Establish rules for the team to avoid this situation.

C.

Reorganize the team aiming to force the behaviors.

D.

Advise the team of the risks and invite them to change.

Buy Now
Questions 60

A project team developer has been involved in a large corporate initiative that has negatively impacted team productivity on another project to which they have been assigned.

How should the developer have handled this situation?

Options:

A.

Worked as planned to meet the team's commitments and participated in other events as time permitted.

B.

Worked extensively on the corporate initiative in order to inform the team of that effort.

C.

Asked to be relieved of project tasks to maintain team velocity.

D.

Have not participated in any initiative that could take focus away from the team's project and goals.

Buy Now
Questions 61

An agile team is having a meeting with a customer to formulate the product requirements for the next iteration. The outcome of the meeting is a set of clear and detailed requirements.

What should the team do next?

Options:

A.

Run automated tests on the legacy functionality.

B.

Ask the customer to write tests that will be used to know when a story has been correctly developed.

C.

Start coding on the selected user stories to meet the requirements.

D.

Write tests that will be used to know when a story has been correctly developed.

Buy Now
Questions 62

An agile leader has been assigned to a project that involves significant technical complexity. What should the agile leader do to set the project up for success?

Options:

A.

Address this impediment by obtaining suitable training for the team.

B.

Address the risks resulting from complexity within sprint zero.

C.

Facilitate team brainstorming of the risks resulting from complexity for the risk register.

D.

Motivate the team to try new technical approaches.

Buy Now
Questions 63

What should the agile team lead do?

Options:

A.

Require the team to try only those ideas that will ensure success.

B.

Allow the team to try ideas, but remind them that results will be reviewed by high-ranking executives.

C.

Associate idea successes and failures with the team's incentive plan to ensure accountability.

D.

Encourage the team to try the ideas, even if failure may be the outcome.

Buy Now
Questions 64

How should the agile practitioner address this?

Options:

A.

Implement a burnup chart and add the issue resolution as a task to the product backlog for the customer to prioritize.

B.

Add the issue to the Kanban board and assign it to the team member who has made the most progress on resolving it.

C.

Conduct a root-cause analysis on the issue and identify related risks and risk response owners at the next retrospective.

D.

Document all project issues in a common space and ask the team members to decide on task allocation principles.

Buy Now
Questions 65

A project team member expresses frustration about the length of time it takes to make decisions for a complex project. Approvals need to happen at many levels in the company.

What should the team lead do to improve decision quality and reduce the time required to make decisions?

Options:

A.

Make sure the project owner is fully embedded into the project team so that they are readily available to make quick decisions.

B.

Establish collaborative behaviors among all members of the organization through a group decision-making process.

C.

Ensure all decisions are routed as quickly as possible to the project sponsor and have the rules of engagement visibly posted.

D.

Reduce the number of required approvals and expand the decision-control limits to the scrum master.

Buy Now
Questions 66

An agile team lead is assigned to a project that must ensure data security. What should the team lead do to guarantee that security, as a non-functional requirement, is managed throughout the project?

Options:

A.

Include security concerns on the agenda for every meeting.

B.

Request that a security expert be added to the team.

C.

Add security as a non-functional requirement to the risk register, and review regularly.

D.

Ensure that planning and prioritizing includes consideration of security requirements.

Buy Now
Questions 67

One of the senior stakeholders on a project did not want to be engaged on a daily basis. During the iteration, the team encounters complexities but are convinced these issues can be resolved in time for the demo.

What should the agile practitioner do?

Options:

A.

Be transparent with all the stakeholders and make them aware of the issues encountered and the current project's status.

B.

Ensure the agile leader documents a risk in the risk register and communicates the risk to the project sponsor.

C.

Support the team's decision, and since the team is confident about being able to resolve the issues in time, do not raise the issues as risks with the stakeholders.

D.

Ask the product owner to make a decision as to whether or not all the stakeholders should be kept informed about the current project's status.

Buy Now
Questions 68

The risk profile of a project has increased beyond the upper threshold of tolerance. The product owner and project leader meet to discuss an approach for dealing with this. What should the team do next?

Options:

A.

Add risk mitigation tasks to the backlog, then prioritize in current and upcoming sprints

B.

Add risk mitigation time to each requirement

C.

Apply the 80/20 rule, reserving 20 percent of each sprint’s capacity for risk mitigation

D.

Hold all risks until they become issues, then add issue resolution tasks to the product backlog

Buy Now
Questions 69

Due to its complexity, a new team member struggles with developing a concise user story.

What advice should the agile practitioner give to assist with developing the story?

Options:

A.

Hand the story over to a more experienced team member

B.

Break the story up and focus on the most valuable parts

C.

Discuss the story at the next retrospective

D.

Pick another story from the product backlog

Buy Now
Questions 70

A product owner needs to elaborate on a product roadmap. How can the product owner collaborate with stakeholders to identify the features that offer maximum value?

Options:

A.

Identify the product users and their high-level key activities to get their perspective because the product is intended for them.

B.

Obtain the project sponsor's perspective to get an initial idea of the features they believe the product should have to guide the development team.

C.

Analyze the development team's capacity and skills because these will determine which features to include in the roadmap.

D.

Create a draft of the product roadmap that the development team can use as a guide for further guidance.

Buy Now
Questions 71

While planning, what prioritization factors need to be considered for a minimally marketable feature (MMF)?

Options:

A.

How much risk is needed to develop an MMF

B.

How much money the organization will earn or save by having the MMF

C.

How many stakeholders are influencing the MMF

D.

How much time does an organization need to develop an MMF

Buy Now
Questions 72

What should the agile coach do to develop members into a high-performance team?

Options:

A.

Teach the team how to work comfortably in chaos.

B.

Provide strong facilitation and conflict-resolution guidance.

C.

Allow the team to resolve issues on their own.

D.

Observe each team member and advise them on team relationships.

Buy Now
Questions 73

What is a benefit of this meeting?

Options:

A.

The team will learn how its contribution will create product value

B.

It will enable team acceptance of client priorities

C.

It will enable the team to see the entire project in one glance

D.

It will enable the team to ask any questions to the customer upfront

Buy Now
Questions 74

As part of the organizational change, all project teams within the digital channel’s portfolio have been directed to move from 3-week iterations to 2-week iterations. The development team is frustrated as they think there will not be enough time to test. The product owner does not like this change as it will increase the number of ceremonies.

Which two actions should the scrum master take? (Choose two.)

Options:

A.

Proactively engage the resource managers to lead the team and provide the required support.

B.

Request the enterprise coach and human resources support the team with the transition.

C.

Document the pros and cons and review with stakeholders to determine the dependencies.

D.

Protect the team from disruptions and seek an exemption for status quo.

E.

Assess the impacts of the change and brainstorm potential solutions.

Buy Now
Questions 75

During project inception, an agile practitioner engages the stakeholder to ensure alignment on the project's strategy and vision. The stakeholder asks for detailed requirements, design, and delivery plans.

What should the agile practitioner do?

Options:

A.

Provide all information requested by the stakeholder

B.

Set expectations regarding the appropriate level of details requested during this stage

C.

Inform the stakeholder that no detailed documents are provided using agile practices

D.

Ask the team to supply the information to the stakeholder

Buy Now
Questions 76

Options:

A.

Add new security features to the backlog and prioritize.

B.

Execute a spike to research security features for the project.

C.

Ask questions to determine where and how the product owner wants to use the product.

D.

Ask questions to determine if the product owner can define the desired level of security.

Buy Now
Questions 77

Just before a scheduled product launch, the customer declined to accept the final deliverable after seeing the demo. What should the project manager do to prevent this in the future?

Options:

A.

Ensure the teams are working together daily throughout the product development and are keeping the team's progress up to date.

B.

Ensure there is an environment where team members feel comfortable sharing their ideas, concerns, and feedback.

C.

Ensure the customer is provided with regular project status updates and that the meeting minutes are well documented.

D.

Ensure the team is able to release new features and updates frequently so that customers can see the product and provide feedback.

Buy Now
Questions 78

During the advanced stages of implementing a complex design, an agile practitioner realizes that the architecture is not scalable for user requirements. The architect suggests a workaround that is minimally adequate but may cause some performance issues.

What should the agile practitioner do?

Options:

A.

Tell the team that this is unacceptable for the upcoming project.

B.

Implement the workaround since performance issues can be addressed in the next iteration.

C.

Calculate the cost of redoing the architecture and seek management approval.

D.

Brainstorm with the team to identify a solution.

Buy Now
Questions 79

How can a project team effectively work toward a common goal and communicate as they scale and expand to build a new business-critical platform, given that they have been responsible for a small customer-facing product with little complexity over the past 2 years?

Options:

A.

Daily coordination meeting

B.

Instant messaging tools

C.

Web conferencing

D.

Work collaboration platform

Buy Now
Questions 80

During a backlog refinement meeting, the new developer on the team asks the product owner to discuss a new performance threshold requirement and how it impacts the stories in the backlog.

What should the team do?

Options:

A.

Add this threshold requirement request as acceptance criteria in all impacted stories

B.

Create a spike story to analyze the impact of the threshold requirement on current stories

C.

Conduct design planning session to review the performance threshold requirement

D.

Identify the tasks for the new performance threshold requirement

Buy Now
Questions 81

What should the team do?

Options:

A.

Collaborate with the product owner to reprioritize the product backlog, thus ensuring that more features will be completed before the release.

B.

Ask the team lead to calculate the team's target velocity according to the project plan, and assign additional resources to increase capacity.

C.

Focus on velocity and schedule concerns during the retrospective to inspect, adapt, and improve the process and plans.

D.

Reestimate the backlog items from the release, ensuring that contingency is included to set stakeholder expectations.

Buy Now
Questions 82

An agile team discovers a new risk and identifies that its impact may be severe. What should an agile practitioner recommend?

Options:

A.

Add a goal to the current iteration to fully mitigate or control the risk.

B.

Balance risk reduction and value adding activities in the next iteration.

C.

Continue with the current plan to maintain team velocity.

D.

Update the risk register and seek direction from a risk specialist.

Buy Now
Questions 83

When considering impact on a project, to whom should an agile project manager give top priority on the stakeholder list?

Options:

A.

The stakeholder who can prevent the project from delivering within budget

B.

The stakeholder who can prevent the project from achieving its goals

C.

The stakeholder who can delay the project

D.

The stakeholder who can work as a friend and help prepare the stakeholder list

Buy Now
Questions 84

An agile team is in their 2nd iteration planning session. During the session, they are debating on whether regression and integration testing should be part of every iteration or part of the hardening iteration.

What should the agile lead recommend?

Options:

A.

Integration testing with other upstream or downstream applications and all bug fixes should be done as part of the hardening iteration.

B.

Integration testing with other upstream or downstream applications should be done by the team as part of every iteration.

C.

Continuous integration and regression testing should be done by the team as part of every iteration.

D.

Regression testing should not be done by the team as part of every iteration but only as part of the hardening iteration.

Buy Now
Questions 85

A client has provided their requirements and deadline to the project team. The requirements are confusing, and the team is frustrated.

What should the team's servant leader do?

Options:

A.

Try to motivate the team by recounting examples of their past successes.

B.

Ask the team to find user stories from similar projects for this customer.

C.

Ask the team to restate the requirements and review them with the client.

D.

Ask the team to develop user stories and build deliverables based on the requirements.

Buy Now
Questions 86

How can an agile practitioner ensure that all key stakeholders are properly engaged in planning?

Options:

A.

Collect stakeholder requirements

B.

Conduct an iteration planning meeting

C.

Communicate product backlog items to the stakeholders

D.

Facilitate a product development roadmap workshop

Buy Now
Questions 87

A team's technical lead believes that manual testing tasks should be conducted by junior team members below their level. The junior team members think it is unfair and refuse the tasks.

What should the Scrum Master do?

Options:

A.

Tell the technical lead to do the testing

B.

Facilitate an open and focused team discussion that reinforces team agreements

C.

Ask the team manager to advise the technical lead that all tasks are important

D.

Encourage the team to take ownership of the delivery

Buy Now
Questions 88

A project manager is working on a user story about migrating to a new version of a database but is unsure of the dependencies. What can the product owner request from the team to understand the risks?

Options:

A.

Refinement meeting

B.

Daily standup meetings

C.

Retrospective

D.

Spike

Buy Now
Questions 89

During a recent sprint review meeting with stakeholders, the product owner received detailed feedback indicating the critical changes needed for upgrading the legacy system to better align with the latest technologies and user needs. How should the product owner help ensure the product backlog is effectively managed, while helping the team remain focused? (Refer to the Product Backlog Exhibit)

Options:

A.

Prioritize the stakeholder feedback, considering the impact on strategic objectives and current workload, and discuss these priorities with the team in the next sprint planning meeting to collaboratively decide on the next steps.

B.

Implement the changes in the current sprint, reallocating resources and adjusting the sprint goals to accommodate the feedback immediately, regardless of the current workload and potential impact on ongoing tasks.

C.

Update the product backlog immediately without consulting the team, ensuring that the most critical feedback is addressed as soon as possible, even if it disrupts the current workflow.

D.

Disregard the feedback until the next product release, focusing solely on the current sprint commitments to avoid any disruption and maintain the current workflow, even if it means delaying potentially valuable changes.

Buy Now
Questions 90

What should the project leader do?

Options:

A.

Assign the spike to another resource to continue research for the long-term solution

B.

Re-establish the spike; encourage experimentation and collaborate with the team

C.

Stop experimentation and negotiate the short-term solution with the customer

D.

Schedule a root-cause analysis with the development team on the main issues with the spike

Buy Now
Questions 91

The manager of the team is responsible for delivering a specific initiative within the organization. They are preparing for the monthly project review meeting, where they will present the current state of this initiative. The agile project lead sends the manager the following email with the initiative's current status.

Which summaries are correct and will be presented during the monthly project review? (Refer to

the email and exhibits to the Team Manager)

Options:

A.

MVP has 25 remaining story points; MVP will complete at the end of sprint 8; with no otherdeviations, the entire backlog will complete at the end of sprint 15.

B.

MVP has 30 remaining story points; MVP will complete at the end of sprint 8; with no otherdeviations, the entire backlog will complete at the end of sprint 15.

C.

MVP has 25 remaining story points; MVP will complete at the end of sprint 9; with no otherdeviations, the entire backlog will complete at the end of sprint 16.

D.

MVP has 30 remaining story points; MVP will complete at the end of sprint 9; with no otherdeviations, the entire backlog will complete at the end of sprint 16.

Buy Now
Questions 92

A project has several features that will deliver immediate customer value. The product owner needs to determine which features to include in the upcoming iteration.

What should the product owner have the customer review and approve?

Options:

A.

Work breakdown structure

B.

Description of all features' functions and an estimate of their cost

C.

Priority list of desired features and functions

D.

Comprehensive schedule of immediate deliverables

Buy Now
Questions 93

During the review session, the product owner discovers that the user interface has a response time of 10 seconds. The non-functional requirements state that it should respond in less than two seconds. The team complains that this requirement was not communicated to them.

What should have been done to avoid this?

Options:

A.

A comprehensive user story with all non-functional requirements should have been created

B.

Non-functional requirements should have been added to the acceptance criteria

C.

Non-functional requirements should have been added to the definition of done

D.

A team review of the scope of work should have been conducted

Buy Now
Questions 94

An agile team is struggling with an issue. A team member mentions that another team had a similar issue that was resolved, but lessons learned documents are unavailable.

What should the agile practitioner do?

Options:

A.

Suggest that all agile teams share weekly reports on their projects.

B.

Encourage the team to independently find a solution.

C.

Work with the team to create a solution for disseminating team knowledge throughout the company.

D.

Recommend hiring an external expert to advise on the best methods for sharing knowledge among teams.

Buy Now
Questions 95

A team member on a self-directed team is concerned that a feature the customer wants is outside of what the team will be able to deliver. What should the team member do next?

Options:

A.

Escalate the concern to the project sponsor for necessary action

B.

Adjust the feature to make it work as needed

C.

Work directly with the customer to arrive at a suitable compromise

D.

Log this into the risk register and inform the team at the next standup meeting

Buy Now
Questions 96

An executive sponsor asks a team when a specific feature will be ready for release. A team member states the feature will be ready by the end of release 3 because it is not a core feature. The team member directs the sponsor to an information radiator, where the sponsor sees several notes grouped by release numbers and posted on the wall.

What is the sponsor looking at?

Options:

A.

Project management plan

B.

Product backlog

C.

Gantt chart

D.

Product roadmap

Buy Now
Questions 97

A Scrum team is refining product backlog items for the next sprint in a project. The product owner does not agree with the changes.

Can the product owner reject changes to a product backlog?

Options:

A.

Yes, the product owner is part of a Scrum team and can reject any changes on the product backlog.

B.

Yes, because the product owner is the decision maker for product backlog changes.

C.

No. because this action will create disruption in the Scrum team.

D.

No. because only members of the Scrum team can reject or approve changes.

Buy Now
Questions 98

Iterations last between a couple of weeks to a couple of months, with a preference for the shorter time. What is the goal for each iteration?

Options:

A.

Complete the assigned tasks.

B.

Deliver working software frequently.

C.

Demonstrate the software to the customer.

D.

Provide a high-level timeline.

Buy Now
Questions 99

A healthcare agency has contracted a vendor to provide a financial accountability solution. During a daily coordination meeting, the lead developer reports they cannot complete the stories for this iteration because the project director requested a document detailing all testing planned for the solution. The team lead met with the project director to discuss alternatives but insists they need the detailed plan by the end of that week. The team lead advises the lead developer to continue coding.

What should the team lead do next?

Options:

A.

Negotiate with the project director to reduce the types of tests for which they need details to reduce the impact of this request.

B.

Escalate this as an issue to the executive project sponsor for a decision because it will impact the ability of the team to deliver the product on time.

C.

Ask the test manager to provide a detailed estimate of the time required to write the plan for the solution and their capacity for the remainder of the week.

D.

Ask the team to put their work on hold and collaborate on the documentation because it can be completed quicker if everyone shares the work.

Buy Now
Questions 100

Answer Options:

Options:

A.

The iteration is in jeopardy.

B.

The team has removed scope.

C.

The iteration is ahead of schedule.

D.

The team's velocity is constant.

Buy Now
Questions 101

A team member has made a mistake on a project.

How should the Scrum Master address the mistake?

Options:

A.

Encourage all team members to follow existing processes.

B.

Require team members to complete a peer review of work and deliverables.

C.

Facilitate a retrospective to identify areas of improvement.

D.

Reward those who have the lowest occurrences of mistakes.

Buy Now
Questions 102

A team worked with a customer to estimate all user stories for the must have features. During release planning sessions, the customer indicated they prefer 3-week iterations that begin on Thursdays and end on Wednesdays. The team spent several days determining which stories should be developed for iteration 0 and understanding the customer’s priorities for the remaining stories. The project sponsor attends the Friday meeting and requests a high-level estimate of when they can invite the chief executive officer (CEO) to a demonstration of the minimum viable product (MVP).

What should the team tell the sponsor at this point in the planning process?

Options:

A.

They do not have enough information to estimate a date range yet but can provide the number of 3-week iterations required.

B.

They can provide an anticipated date with the assumption that conditions will be ideal.

C.

They can provide a broad range but cannot realistically set a target release date until the team's velocity stabilizes.

D.

They will send an update when all of the stories are estimated and prioritized in the backlog.

Buy Now
Questions 103

During a sprint, the team encounters a technical problem that becomes an impediment to completing two stories.

What should the Scrum Master do?

Options:

A.

Ask the lead developer to identify a solution, and then share the details with the team

B.

Ask a technical manager or architect to determine a solution to the problem

C.

Work with the product owner to add a spike to the next sprint to identify a solution

D.

Create a collaborative team environment so that the team can explore a solution together

Buy Now
Questions 104

Two similar stories A and B are estimated at 3 story points. Story C is estimated at 8 points. After an iteration in which A and C were completed, it is found that story A took much longer than story C.

What should the agile practitioner do?

Options:

A.

Assign story B more than 8 story points to provide a better estimate

B.

Add points to story B’s iteration to account for the error but keep story B at 3 points

C.

Assign more resources to story B to bring it in line with the estimate

D.

Reestimate all stories including values for A, B, and C

Buy Now
Questions 105

The project lead of a newly created Agile project delivery team realizes that there are gaps in the knowledge of some team members. The lack of specific skills will add risk to the project delivery if the project becomes too dependent on specific resources for complete delivery.

What should the project lead do to address the gaps and develop a high-performing team?

Options:

A.

Ask each team member to document their solutions extensively in a knowledge repository for knowledge exchange between the team.

B.

Pair team members and ensure review of technical deliverables by partners in each sprint before integration of the solution.

C.

Create an environment of continued learning by providing opportunities for team members to develop their skills as generalized specialists.

D.

Replace the team members with highly qualified individuals that have experience in the specific technologies required for completing delivery.

Buy Now
Questions 106

During a review close to a product release, the customer spotted several features that will need to be changed. What caused this to happen?

Options:

A.

Reduced or improper customer collaboration.

B.

Reduced or improper product knowledge by the development team.

C.

Reduced or improper release planning.

D.

Reduced or improper product specification.

Buy Now
Questions 107

What should the agile practitioner do?

Options:

A.

Defer starting the design of item B until the second iteration is being planned

B.

Proceed with the design of item B, since it will hasten the second iteration

C.

Escalate the issue to the customer, and obtain their approval before starting the design of item B

D.

Log the issue in the risk register, and request change control board (CCB) approval

Buy Now
Questions 108

A client is pressed for time and wants to launch a product with three components as soon as possible to gain market share. An agile lead proposes the following agile strategy to gain time: Three teams will work on the design and development of each component. Once all three components are finished, they will be tested and integrated.

Is this agile strategy appropriate?

Options:

A.

Yes, this is a case of sequential development where working in parallel is an accepted strategy in agile to gain time.

B.

Yes, this is a case of hybrid development where a product is divided into components and agile is used for component development and integration.

C.

No, dividing the development team into three separate teams will diminish communication and result in delays.

D.

No the feedback loops are being altered, which can result in big failures and delays

Buy Now
Questions 109

The team underestimated the complexity of a story, resulting in new decomposition of the work to be delivered in the current sprint and items to be returned to the backlog. What should the Scrum Master do next?

Options:

A.

Ask the project manager to work with the product owner to help generate clearer stories in the future.

B.

Develop guidelines to prevent future occurrences.

C.

During the retrospective, discuss the issue and create an action plan to avoid it in the future.

D.

Allow the team to devise a corrective action without external intervention.

Buy Now
Questions 110

Options:

A.

Parametric

B.

One-to-one comparison

C.

Affinity

D.

Planning poker

Buy Now
Questions 111

Business partners are attending a daily standup meeting for a project. The business partners are asking questions about the sprint backlog and delivery timing.

How should the project manager explain why this is not the forum to ask these questions?

Options:

A.

The daily standup meeting provides a status update for the scrum.

B.

The daily standup meeting helps to resolve issues that arise within the backlog.

C.

The daily standup meeting helps the team prioritize the work.

D.

The daily standup meeting helps the team keep and synchronize commitments.

Buy Now
Questions 112

What should the agile coach ensure that developers do?

Options:

A.

Establish pair programming partners, and regularly perform peer reviews.

B.

Perform demos at the end of each iteration.

C.

Send coding to the quality assurance (QA) team upon completion.

D.

Demonstrate each feature to the client as soon as coding is complete.

Buy Now
Questions 113

A development team for a small company experiences long delays between product completion and release for validation and testing. The company is concerned that this will impact its ability to compete in the marketplace.

What analysis should the team use to understand the issues?

Options:

A.

Risk management

B.

Variance and trend

C.

Kano model

D.

Fishbone diagram

Buy Now
Questions 114

A company is planning to launch a new service to improve the customer checkout experience.

What should the project manager do to meet the objective of reducing time to market to gain a competitive advantage in the industry?

Options:

A.

Engage the project stakeholders to assess the best practices to apply and plan the deliverables before implementation.

B.

Recommend an Agile delivery approach and provide information to the stakeholders on Agile values and principles.

C.

Educate the team about Scrum and ensure that all members are aligned to the roles required.

D.

Consult executive leadership for the most appropriate method for delivery using existing organizational practices.

Buy Now
Questions 115

Which of the following allows DevOps to enable and sustain a fast workflow from development into operations?

Options:

A.

A mindset shift to establish controls over all development and operations processes.

B.

Planned incremental iterations and a focus on people over processes.

C.

A culture of collaboration, tools, and processes to support continuous delivery.

D.

New tools that enable teams to continuously build, test, and integrate.

Buy Now
Questions 116

During backlog refinement, the team uses an online planning poker tool for estimation. The junior developers change their number of story points after they see the estimations provided by the developers. The junior developers state that the reason for this is that they do not have enough experience and do not want to be blamed for sizing it wrong.

What should the scrum master do?

Options:

A.

Ask the developers to keep their estimation so that the team is transparent with their level of understanding of work.

B.

Agree with the team to keep their estimation as the final number of story points will be the average of all team members.

C.

Propose to consider the estimations of only senior developers and have the junior developers learn from them.

D.

Encourage the team to keep their estimation as this will help surface different constraints and assumptions that others might have missed.

Buy Now
Questions 117

What should the agile practitioner do?

Options:

A.

Work with the agile team and product owner to agree on the definition of done

B.

Ask the project sponsor to determine whether the product is completed

C.

Plan another review after the product has been tested

D.

Add testing to the backlog, and have the product owner reprioritize

Buy Now
Questions 118

An agile project team has team members with varying technical skills. Due to recent events that adversely impacted customer satisfaction, management mandated that Kaizen should be given more focus to ensure the quality in product delivery.

Kaizen is a prime concept of which agile practices?

Options:

A.

Standup meetings. Extreme Programming (XP), relative estimating

B.

Build quality in, visualize workflow, fail fast

C.

Standup meetings, retrospective meetings, continuous improvement

D.

Collaborate, regular builds, inspections

Buy Now
Questions 119

A project team has a senior subject matter expert (SME) who is comfortable with data integration. The SME is not inclined to perform regression testing because the SME feels that performing regression testing is more of a junior duty.

What should the Scrum Master do?

Options:

A.

Explain to the SME the importance of being a team player, that the tasks are assigned by the Scrum Master, and work should not be refused.

B.

Acknowledge that the SME has a valid point from an efficiency point of view and will perform better staying as a specialist.

C.

Leverage a separate testing team altogether to assist with all testing to ensure consistent results.

D.

Explain to the team the importance of reducing team size by reducing specializations and bottlenecks and that every team member plays an equal part.

Buy Now
Questions 120

A seven-member agile team's composition varies considerably in age, gender, culture, personality type, and professional background. When planning a team-building event, what type of interpersonal skills should the project leader use?

Options:

A.

Networking

B.

Social awareness

C.

Communication

D.

Leadership

Buy Now
Questions 121

What should the agile practitioner do next?

Options:

A.

Identify a team member to do a proof of concept using this framework.

B.

Email the team directing them to immediately begin using this new framework.

C.

Obtain feedback from team members on the new framework, and then suggest that the product owner create a backlog item to do a spike on it.

D.

Discuss this option at the next retrospective.

Buy Now
Questions 122

A Scrum Master would like to provide information to key stakeholders on the daily resource and project activities. Which tool should the Scrum Master use to provide these updates?

Options:

A.

Shared vision statement and sprint goal

B.

Release burnup chart

C.

Velocity metrics

D.

Iteration burndown chart

Buy Now
Questions 123

What information should a project team include in an extended stakeholder report to ensure that all current and future stakeholders are aware of the frequent updates?

Options:

A.

Team capacity and competence profiles

B.

A list of tools used for implementation

C.

A list of open technical issues

D.

Up-to-date project radiators

Buy Now
Questions 124

What should the agile team do?

Options:

A.

Discuss the efficiency at the next iteration retrospective

B.

Review the process value stream to determine potential improvements

C.

Review the value the customer receives from the user story to determine backlog priority

D.

Discuss the performance of the solution at the next sprint review

Buy Now
Questions 125

What is the first thing an agile development team should do when planning an iteration?

Options:

A.

Assign the tasks to one team member.

B.

Separate the stories into tasks.

C.

Estimate the stories' tasks.

D.

Help establish the next sprint's goal.

Buy Now
Questions 126

What should the team do next?

Options:

A.

Use agile estimation techniques to create a shared understanding of when the user stories will be completed.

B.

Agree upon development and testing activities for the user stories.

C.

Complete the user stories, and provide a demo for the product owner and customer.

D.

Complete the user stories, and hold a retrospective to discuss them.

Buy Now
Questions 127

What should the agile project manager do?

Options:

A.

Discuss and address this in the iteration retrospective

B.

Let the product owner know it is the project manager's responsibility to drive a team's tasks

C.

Discuss the roles and responsibilities of the project team with the product owner

D.

Ask the product owner to work extra hours to answer the team's questions

Buy Now
Questions 128

An agile leader notices that a team member is becoming very quiet and disengaged in meetings. What should the agile leader do to identify team members' personalities and motivators?

Options:

A.

Use the DISC framework with each team member.

B.

Use MoSCoW ratings to keep people engaged.

C.

Hire a SAFe coach to provide encouragement.

D.

Employ BDUF to help with providing structure to meetings.

Buy Now
Questions 129

Options:

A.

A team with an average velocity of 50 is twice as efficient as a team with an average velocity of 25.

B.

A team with an average velocity of 50 is equally as efficient as a team with an average velocity of 25.

C.

A team that consistently meets its planned velocity is more efficient than a team that consistently exceeds its planned velocity.

D.

A team that consistently meets its planned velocity is less efficient than a team that constantly exceeds its planned velocity.

Buy Now
Questions 130

During the high-level estimation for a project, the team contacted the product owner about the client’s requirements. The team is seeking guidance as their estimate is too big and there is a risk of not finishing the project in time.

What should the product owner do to help the team?

Options:

A.

Work with the client to ensure that the requirements are clear enough to allow a correct estimation and refine the backlog if needed.

B.

Assist the team with schedule planning to mitigate risks, including the possibility of crashing if needed.

C.

Implement clear measurements to control any deviation and therefore ensure the project's success per client requirements

D.

Recommend that the team skip requirements that are too complex and estimate them later through progressive elaboration.

Buy Now
Questions 131

Midway through a sprint, a team member discovers that the product design fails to adhere to the organization's enterprise architecture standards. Since this required escalation to the architecture team for further analysis and resolution, the team was unable to deliver its sprint goal and the sprint was cancelled.

What should the team have done to avoid this?

Options:

A.

Escalated the issue to management

B.

Ensured the early engagement of key stakeholders

C.

Provided feedback to the architecture team to change the enterprise architecture standards

D.

Raised an exception for non-adherence to the enterprise architecture standards for this product

Buy Now
Questions 132

At an iteration review, the product owner indicated that the work delivered did not meet expectations. The project team is surprised.

How should this situation have been prevented?

Options:

A.

The team should have reviewed the definition of done prior to the iteration review.

B.

The testers should have ensured that test cases accurately reflected the product owner's expectations.

C.

The team should have conducted more demonstrations with the product owner during the iteration.

D.

The product owner should have provided clearer explanations during the planning meeting.

Buy Now
Questions 133

A product owner with experience in a predictive approach wants the team to develop very detailed schedules and cost estimates for the next 10 sprints. What should the Scrum Master do?

Options:

A.

Suggest the product owner start by focusing on the next 2 sprints instead of 10.

B.

Spend the first few sprints to develop detailed schedules and budgets.

C.

Invite the product owner to the retrospective to explain the team's approach to schedule and budget.

D.

Explain that detailed project schedules and budgets are not artifacts in agile projects.

Buy Now
Questions 134

A newly formed Scrum team wants to foster an environment of transparency and experimentation. The team decides to use a Kanban board to record and track encountered impediments. Emphasis is placed on how issues are resolved and the strategies for preventing them in the future. Over time, what will be the result of this approach?

Options:

A.

Kaizen

B.

Specific, measurable, assignable, realistic, and time-based (SMART) goals

C.

Key performance indicators (KPIs)

D.

Muda

Buy Now
Questions 135

An agile coach is working on a digital transformation project. The project team is in the middle of a 5-week sprint. The agile coach notices constant arguing among team members on what should be the preferred technical approach to solve a current business problem. What can the agile coach do to promote collaboration and consensus-building among team members?

Options:

A.

Work with team members to resolve the issue.

B.

Escalate the issue to the product owner.

C.

Allow team members to resolve the issue.

D.

Escalate the issue to senior management.

Buy Now
Questions 136

An agile team has been given a complex project with a basic set of requirements which need further elaboration and review. How should the team iteratively build out the backlog of requirements with the stakeholders?

Options:

A.

Conduct a requirements gathering workshop.

B.

Deliver the basic requirements iteratively.

C.

Have the product owner fill out the requirements backlog.

D.

Have the stakeholders fill out the backlog before starting the project.

Buy Now
Questions 137

During agile training, an aspiring scrum master with experience in predictive projects asks about the differences between the Kanban approach and the agile approach.

How should the agile trainer respond?

Options:

A.

The Kanban approach relies on storyboards.

B.

The Kanban approach focuses on adaptive, simultaneous workflows.

C.

There are no work-in-process limits in the Kanban approach.

D.

Kanban teams employ a pull system.

Buy Now
Questions 138

A project manager was assigned to lead the development of a new application for a company. The application will be widely used by all company employees around the world. During the first meeting with key project stakeholders, the project manager was asked to find a way to determinate all possible types of users who may interact with the application that is going to be developed.

What should the project manager do next?

Options:

A.

Push it back due to the number of users and socialize the idea of developing a standard application and training session for all users.

B.

Identity and create personas that can help the team better understand the needs of the target user base.

C.

Build a minimum viable product (MVP), a standard application for all users, and release the new version (per users/areas).

D.

'Engage the human resources (HR) team to identify the key users and interview all of them accordingly.

Buy Now
Questions 139

A company president is concerned about the impact of a natural disaster on the company. How should management identify areas to apply its resources and mitigate potential impacts?

Options:

A.

Establish and keep an active risk register that includes mitigation strategies and a cost-benefit analysis.

B.

Establish and keep an active risk register based on qualitative risk analysis and expected losses.

C.

Have each development team post the highest risk development items on the information radiator.

D.

Avoid risk by splitting development teams into two locations to ensure knowledge continuity.

Buy Now
Questions 140

Senior management is frustrated at the lack of a detailed implementation plan that shows exactly when the project will end and when all requirements will be met. The team has been using a rolling wave planning approach so far on the project.

How should the agile practitioner explain to senior management the benefits of this approach?

Options:

A.

It ensures a consistent level of detail is available in the project schedule

B.

It prevents a wasteful buildup of requirements inventory that may never be processed

C.

It provides a concrete definition of project scope, cost and duration

D.

It allows the team to lock down the stories to be included in a release

Buy Now
Questions 141

A diverse team can sometimes create misunderstandings and conflict, leading team members to isolate. How can an agile project manager promote effective communication and collaboration among team members with diverse backgrounds and perspectives?

Options:

A.

Reduce emotions by emphasizing areas of agreement rather than areas of difference.

B.

Create a shared vision for the team and use techniques to increase empathy and positive interaction.

C.

Coach the team to focus on areas of agreement and the company's profitability.

D.

Confront the team and follow the formal procedures as described in the project management plan.

Buy Now
Questions 142

What should the agile team do next?

Options:

A.

Ensure that the product owner reviews the acceptance criteria for delivered user stories.

B.

Augment the quality assurance and continuous integration processes for delivery.

C.

Approach the relevant developers and testers regarding quality issues in upcoming iterations.

D.

Ask the product owner to define the entire scope of delivery two to three iterations in advance.

Buy Now
Questions 143

When introducing agile processes to a company, a quality assurance (QA) manager resists and believes that the switch to agile will remove quality controls and documents.

How should the agile practitioner address this concern?

Options:

A.

Educate the QA manager that in agile quality is integrated from the beginning to end of the project

B.

Write backlog items that include QA as part of the description

C.

Ask for the current QA documents and incorporate them into the technical debt backlog

D.

Ask the product owner to write tests and QA controls into the acceptance criteria

Buy Now
Questions 144

How should this be handled?

Options:

A.

The story should be assigned eight story points as per the majority vote

B.

The story should be added to the backlog and reassessed later

C.

The story should be assigned points after a discussion with the fifth team member to see if a consensus can be reached

D.

The decision for the number of story points should be made by the customer

Buy Now
Exam Code: PMI-ACP
Exam Name: PMI Agile Certified Practitioner (PMI-ACP)
Last Update: Jun 15, 2025
Questions: 476
$66  $164.99
$50  $124.99
$42  $104.99
buy now PMI-ACP