In a multiple programme environment, which role may be performed by a ‘corporate portfolio board’?
What role has a focus on designing benefit measures within a programme to track business performance against targets?
Which area of management within programme quality tracks and protects project outputs?
Which of the following statements about the information management plan are true?
1.It describes the techniques to be used to maintain programme information
2.It sets out a timetable for establishing naming conventions
Which of the following statements about the business change manager role are true?
1.It provides a bridge between the programme and business operations
2.It delivers the new capability to business operations
Which role focuses on monitoring the progress of the programme at a strategic level?
Which activity requires the programme office to be independent of the initiatives?
Which role is MOST likely to have a focus on managing the costs of training operational teams during transition?
Which document is updated throughout the programme when new information on benefits and risks becomes available?