Weekend Sale - Limited Time 65% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: 65percent

Welcome To DumpsPedia

IDPX Sample Questions Answers

Questions 4

What deliverables are the responsibility of the interior designer in the design development phase?

Options:

A.

Power and data plans, floor plans with partition types

B.

Floor plans, reflected ceiling plans with HVAC ductwork layout

C.

Reflected ceiling plans with fixture types, floor plans with partition types

D.

Power and data plans, reflected ceiling plans with sprinkler head locations

Buy Now
Questions 5

What is the standard sequence of events for the permit process?

Options:

A.

inspections, permit issued, preliminary review, temporary occupancy

B.

permit issued, preliminary review, temporary occupancy, inspections

C.

preliminary review, permit issued, inspections, temporary occupancy

D.

temporary occupancy, preliminary review, inspections, permit issued

Buy Now
Questions 6

Several employees in an office suffer from pollen allergies. How could their symptoms be reduced while at work?

Options:

A.

Install non-operable windows

B.

Install high-efficiency air filters

C.

Utilize a passive ventilation system

D.

Relocate these employees to internal offices

Buy Now
Questions 7

During construction of a project in another city, what is a common and efficient way for a small firm to manage the progress?

Options:

A.

visit the location of the project on a weekly basis

B.

joint-venture with a design firm local to the project

C.

partner with a prominent company local to the designer

D.

hire one employee that will remain in the city of the project

Buy Now
Questions 8

A designer who is working on a non-profit community center in a historic building has met individually with the project’s benefactor, the community center’s board, the center’s director and staff, local community members, the municipality’s historic preservation committee, and the retained contractor. Which of the following is the designer’s GREATEST challenge?

Options:

A.

Balancing the various stakeholders’ preferences

B.

Working with the contractor towards a unique design

C.

Balancing material and finishes that have historical significance

D.

Working with the community towards a concept that will use the space as desired

Buy Now
Questions 9

Upon completion of a project, what documents would the designer retain for their files?

Options:

A.

Record (as-built) drawings and specifications

B.

Post-occupancy evaluation and specifications

C.

Record (as-built) drawings and inspection report

D.

Post-occupancy evaluation and inspection report

Buy Now
Questions 10

When evaluating a finish material’s impact on indoor air quality, the interior designer requests

Options:

A.

time for climatization

B.

carbon monoxide sensors

C.

material safety data sheets

D.

manufacturer’s specifications

Buy Now
Questions 11

Which space would MOST likely have a dedicated HVAC system?

Options:

A.

an office in a high rise

B.

computer room in a school

C.

lobby of a healthcare center

Buy Now
Questions 12

When reviewing the general contractor’s pay application, the designer should approve the amount for

Options:

A.

Utilities and property taxes

B.

Subcontractors’ travel expenses

C.

Delivered materials stored on-site

Buy Now
Questions 13

What do written specifications define?

Options:

A.

quantity

B.

form

C.

quality

D.

relationship

Buy Now
Questions 14

A design firm located in Utah has been awarded a new construction project located in Toronto. What building code and permit requirements must the design firm comply with when designing the project?

Options:

A.

International Building Code

B.

National Building Code of Canada

C.

The applicable building code in the firm’s local jurisdiction

D.

The applicable building code in the project’s local jurisdiction

Buy Now
Questions 15

The PRIMARY reason for the submittal process during Contract Administration is for the designer to

Options:

A.

Confirm the quantity of material to be ordered

B.

Alter product specifications prior to the final order

C.

Check for conformance with the contract documents

D.

Verify that the dimensions conform to the site conditions

Buy Now
Questions 16

What is the BEST way for a designer to determine whether the payment application of a contractor is consistent with the work completed to date?

Options:

A.

Request a breakdown of the pricing in the payment application to be reviewed by the consultants

B.

Participate in periodic site visits to compare progress onsite to progress claimed in the payment application

C.

Review the project schedule to determine what should be completed by the date of the payment application

D.

Call the subcontractors individually to verify that the work noted on the payment application is indeed complete

Buy Now
Questions 17

A building owner hires a design firm to renovate an existing office suite into a live-work space. What is the FIRST step the designer should take?

Options:

A.

Perform a site visit

B.

Confirm zoning ordinance

C.

Document the project drivers

D.

Verify the building construction type

Buy Now
Questions 18

What should a designer recommend to BEST save on construction costs in a corporate office project with a tight improvement allowance?

Options:

A.

Reuse the existing doors and millwork where possible

B.

Save as many existing nonstructural walls as possible

C.

Maintain the existing water closet and lavatory locations

D.

Design an open-plan for each space without suspended ceilings

Buy Now
Questions 19

In an existing non-sprinklered multi-tenant building, a client will be converting a suite from a bank into a restaurant serving more than 49 persons. What fire rating is REQUIRED between the new tenant and the existing adjacent insurance office?

Options:

A.

0

B.

1

C.

2

D.

3

Buy Now
Questions 20

What is the PRIMARY function of an order acknowledgement?

Options:

A.

Secure written agreement before proceeding with the work

B.

Allow review and correction before an order is manufactured

C.

Prescribe the processes for tracking invoices and accounts receivable

D.

Establish the discount structure to be used for purchases related to a particular project

Buy Now
Questions 21

Which of the following is MOST likely to require a louvered door?

Options:

A.

IT closet

B.

Hotel room

C.

Executive office

D.

Dental exam room

Buy Now
Questions 22

Formaldehyde, PVC, and phthalates are examples of chemicals included in

Options:

A.

The Red List

B.

Class C finishes

C.

Hazardous building types

D.

CAL 133 compliant products

Buy Now
Questions 23

During construction, a designer has been informed that the floor tile specified will delay occupancy. What is the BEST course of action?

Options:

A.

Modify the specifications to an alternate flooring type that is in stock

B.

Change the specifications to an in-stock tile and obtain the client’s agreement

C.

Notify the client and all subtrades that the anticipated schedule will be delayed

D.

Give an estimate of how far behind schedule the project is, with a new completion date

Buy Now
Questions 24

Information regarding product substitutions is found in the

Options:

A.

bid (tender) forms

B.

general requirements

C.

material specifications

Buy Now
Questions 25

Contract documents serve as the legal contract between

Options:

A.

the client and the designer

B.

the client and the contractor

C.

the designer and the contractor

D.

the contractor and the suppliers

Buy Now
Questions 26

A restaurant is designated as which occupancy classification?

Options:

A.

public: group P-3

B.

business: group B

C.

restaurant: group R

D.

assembly: group A-2

Buy Now
Questions 27

What should be evaluated by the design team in advance of a project kickoff with clients and stakeholders?

Options:

A.

Cost analysis and value engineering

B.

Site availability and schedule impacts

C.

System performance and subcontractor availability

Buy Now
Questions 28

At the time of preparing construction documents, the client is undecided about replacing flooring within the scope of work. How would the designer obtain pricing for including the flooring?

Options:

A.

a mock-up

B.

an alternate

C.

an addendum

D.

a change order

Buy Now
Questions 29

What is one way to reduce indoor air pollutants?

Options:

A.

increase humidity levels

B.

install operable windows

C.

use materials with high VOCs

D.

decrease building temperature

Buy Now
Questions 30

What is the MINIMUM fire rating for a door in a 2-hour fire separation wall?

Options:

A.

3/4-hour

B.

1-hour

C.

1 1/2-hours

D.

2-hours

Buy Now
Questions 31

Which wall assembly would produce the highest STC rating?

Options:

A.

2x4 studs at 16" [406 mm] OC, 2 layers of 5/8" [15 mm] gypsum board on each side, full batt insulation

B.

2-1/2" [64 mm] metal studs at 16" [406 mm] OC, 1/2" [13 mm] gypsum board on each side, full batt insulation

C.

3-1/2" [89 mm] metal studs at 16" [406 mm] OC, 5/8" [15 mm] gypsum board on each side, full batt insulation

Buy Now
Questions 32

While on site, the designer notices that the glazing subcontractor is installing the storefront system in the wrong finish. What should the designer do?

Options:

A.

Report the discrepancy in a memo to the contractor and client

B.

Reach out to the glazing supplier to find out which finish was ordered

C.

Explain the issue at the next owner, architect, contractor (OAC) meeting

D.

Tell the subcontractor to stop their work and explain the issue to the contractor

Buy Now
Questions 33

A post-occupancy evaluation indicates that occupants are cold during winter months due to the building’s HVAC system not performing according to design. What would have prevented this situation?

Options:

A.

commissioning

B.

additional diffusers

C.

a punch (deficiency) list

D.

an underfloor distribution system

Buy Now
Questions 34

Which of the following is part of an active system for fire protection?

Options:

A.

Area of refuge

B.

Means of egress

C.

Protected stairwells

D.

Pre-action sprinklers

Buy Now
Questions 35

Which type of mechanical heating system uses pipes or tubing embedded within the ceiling, floor, or wall construction?

Options:

A.

electric

B.

radiant

C.

hot-water

D.

forced-air

Buy Now
Questions 36

In addition to the use of carpet on the floor, which of the following methods is the BEST solution to address the need for acoustical privacy in a conference room?

Options:

A.

Specify interior partitions to the underside of the deck above, add fiberglass insulation to partitions

B.

Specify an acoustical ceiling tile, insulate and caulk joints between partition and ceiling and at electrical receptacles

C.

Specify interior partitions to 6" [152 mm] above an acoustical ceiling, specify batt insulation over the top, 24" [610 mm] each side

D.

Specify metal stud partitions to the underside of the deck above, 5/8" [16 mm] fire-rated gypsum board covered with Type II vinyl wallcovering

Buy Now
Questions 37

What core information should be captured in the design contract to demonstrate a clear understanding of the physical parameters of the project?

Options:

A.

Property address, usable square footage [m²], and projected use

B.

Room name, client, and occupant load

C.

Room measurements, drawing references, and furniture requirements

D.

Occupant load, circulation ratio, and building classification

Buy Now
Questions 38

A project is utilizing existing millwork with new custom countertops. Who is responsible to field verify the existing conditions to generate shop drawings for the new countertops?

Options:

A.

owner

B.

installer

C.

designer

Buy Now
Questions 39

The office manager for a client signed a contract for design services. However, the owner refuses to pay the design fee because the office manager did not have the authority to sign the contract. This is an issue of

Options:

A.

mutual assent

B.

breach of contract

C.

contractual capacity

D.

designer responsible disclaimer

Buy Now
Questions 40

What should be addressed FIRST in a letter of agreement?

Options:

A.

Legal obligations

B.

Scope of services

C.

Amount of retainer

D.

General bid conditions

Buy Now
Questions 41

Earthquakes and the loads caused by winds are examples of

Options:

A.

Live loads

B.

Dead loads

C.

Static loads

D.

Dynamic loads

Buy Now
Questions 42

What is the MOST effective construction method to help mitigate impact noise from high heels on ahard floor surface?

Options:

A.

Higher NRC in the ceiling material

B.

Framed-in upholstered wall panel system

C.

Resilient underlayment in the floor assembly

D.

Blanket insulation between joists and trusses

Buy Now
Questions 43

What is the required clear floor space at an accessible lavatory in a public restroom (washroom)?

Options:

A.

24" x 42" [610 mm x 1067 mm]

B.

24" x 48" [610 mm x 1219 mm]

C.

30" x 36" [762 mm x 914 mm]

D.

30" x 48" [762 mm x 1219 mm]

Buy Now
Questions 44

During a final walk-through, the interior designer notices that a decorative light fixture was not installed on a dimmer as specified. Where should the designer document the issue?

Options:

A.

RFI

B.

Change order

C.

Punch (deficiency) list

Buy Now
Questions 45

A designer is working on a joint venture project with a local engineering firm for a large university project. What drawing system will BEST incorporate coordination of project information?

Options:

A.

Facility condition index (FCI)

B.

Building information modeling (BIM)

C.

Project life cycle management (PLM)

D.

Virtual design and construction project manager (VDC)

Buy Now
Questions 46

A contractor defaults on payments to a mechanical subcontractor. The subcontractor is protected and guaranteed payment by a

Options:

A.

payment bond

B.

mechanic’s lien

C.

performance bond

D.

builder’s risk insurance

Buy Now
Questions 47

Which two functions are allowed with a one-hour fire separation in a fully-sprinklered building?

Options:

A.

a bank and a theater

B.

a car wash and a bank

C.

a theater and a casino gaming floor

D.

a casino gaming floor and a bowling alley

Buy Now
Questions 48

The purpose of shop drawings is to

Options:

A.

Analyze the fabrication method

B.

Approve completeness of the details

C.

Check conformance with the design intent

Buy Now
Questions 49

In a project that includes a home renovation and procurement of new furniture, what is the BEST fee structure?

Options:

A.

Hourly fee method and cost-plus method

B.

Square foot method and fixed fee method

C.

Fixed fee method and square foot method

D.

Value-oriented method and hourly fee method

Buy Now
Questions 50

When completing an analysis of the existing conditions for a two-story commercial building, what are some CRITICAL accessibility items to review?

Options:

A.

entrances, exit signs, and location of accessible parking

B.

exit signs, interior path of travel, and location of accessible parking

C.

entrances, restroom (washroom) facilities, and vertical transportation

D.

interior path of travel, fire protection system, and vertical transportation

Buy Now
Questions 51

During construction, the general contractor notices conflicting information between the construction drawings and the specifications. The FIRST step the contractor should take is to

Options:

A.

issue a change order

B.

make an interpretation

C.

notify the owner of the discrepancy

D.

notify the designer of the discrepancy

Buy Now
Questions 52

What is the MAXIMUM occupant load of a business occupancy with one exit?

Options:

A.

49

B.

50

C.

69

D.

70

Buy Now
Exam Code: IDPX
Exam Name: Interior Design Professional Exam
Last Update: Apr 29, 2025
Questions: 175
$57.75  $164.99
$43.75  $124.99
$36.75  $104.99
buy now IDPX