During the program execution stage the component project manager responsible for testing estimates that budgeted hours may exceed 200 hours. What should the program manager do?
When designing horizontal pathways, the ICT distribution designer should consider the design's ability to (Select two options.)
In a transformational program, all projects are on track and delivering their objective. However stakeholders are hesitant to take on the new processes because performance in the current environment may not be representative of actual performance Stakeholders fear that the program will fail to provide the service required.
To assure positive performance in the current environment, the program manager should do which of the following?
Before working on equipment, what is the FINAL step in the lockout/tagout (LOTO) procedure?
A project is assigned to a qualified project manager by the program manager I he client rejects the project manager due to a lack of proper qualifications to manage such a project
What should the program manager do next?
The project managers for component projects A and B schedule the same resource to perform tasks during the same timeframe, resulting in an over-allocation. The program manager reviews the program resource management plan determine that project. A can wait until the resource becomes available, and assigns the resource to project B.
This is an example of which of the following?
Using an earth ground resistance tester, what is the recommended MAXIMUM value for resistance between any two points along the entire length of a bonding or grounding conductor (not including the earth electrode system)?
Throughout a multiyear program, component projects are transitioned to the customer. During the project acceptance phase, a potential risk is identified and brought to the program team's attention.
What should be done with the identified potential risk?
Company A acquires company B. which leads to a two-year program lo integrate the processes and systems Company B uses a different project management process, and the company's staff is unhappy about the acquisition As a result company B's project team fails to provide status and cost data in a format that conforms to the program standards.
What should the program manager do first?
A program manager notices that one project manager tends to withdraw during important team discussions to avoid conflict. What technique could the program manager use to gam more input from this project manager?
A component project of a program is completed, and will provide the intended incremental benefits. How should the program manager proceed with the component transition?
A program manager has a multiple-project program that is scheduled to be completed by year's end. During the program delivery phases of the protects several mandatory changes are identified that would extend the program's completion date
What is the next step for the program manager?
For a backbone distribution system serving a usable floor space of ≈ 8,920 m2 (96,000 ft2), the MINIMUM slot area to be used for this back bone is
Which of the following terms is often used to describe two parallel paths that have identical conductive terminations to two separate grounding reference points?
The risk manager completes risk response planning. The risk manager believes that to effectively address all eventualities, an additional action is required.
What should the program manager do next?
A newly appointed country manager suggests that the regional program manager use a social media platform to expedite communications and address questions. The new country manager used this social media platform at a previous job.
What should the regional program manager do to address the country manager's request?
A request for proposal (RFP) yields a bid with a better delivery schedule and a lower cost, but originates from a vendor not on the prequalified vendor list During the final review of the RFPs the program manager is informed that the new bidder is a relative of the project manager. Although the bid meets all company policies, the program manager is concerned about a conflict of interest.
What should the program manager do?
An ICT distribution designer is reviewing design documents with the owner to gam approval for an ER design. Which of the following information about the site shall be included?
Coupling with electrical circuits can create inductive interference to telecommunications facilities. Which of the following can decrease the coupling effect?
When designing for horizontal pathways in an environment that requires fire-stopping for penetrating a rated wall, what is the MAXIMUM till ratio for telecommunications cabling in a cable tray?
The number of emerging risks increases in a component project and the program manager tails behind in reviewing) and approving the plans. This Impacts the component project manager's ability to effectively address the risks.
In this situation, what should the program manager change about the risk management plan?
An organization initiates an innovation program to deliver exceptional performance and benefits. After the program transition plan is in place and the implementation of a benefits sustainment plan starts the program manager discovers the program may be shut down due to lack of funding.
To ensure continued funding for the program, what should the program manager do next?
Which of the following two items are examples of items associated with a submittal? (Select two options.)
When preparing an upfront cost estimate, the ICT distribution designer MUST consider which two of the following fees? (Select two options.)
The program manager completed the program's benefits analysis and planning activities. What will this ensure tor the program?
Which two of the following items should be considered for inclusion in a comprehensive working outline of a SoW? (Select two options.)
A company is evaluating the implementation of enterprise resource planning (ERP) software.
The program manager performs an analysis to confirm the program's feasibility
What other important step should the program manager complete^
Which type of protection for electrical power stations provide isolation against a rise in potential of station ground and also provide drainage protection against longitudinally-induced voltages?
A large program consists of several component projects and six project managers. The program governance board requests that all components within the program undergo user acceptance testing before being released to the production environment
Where should the program manager document this?
External resources are required for a program. The program manager receives bids from multiple vendors and presents the top vendor to the program governance board. One program governance board member asks the program manager to select a vendor that was dismissed early in the selection process because they were not on the approved vendor list The program manager learns that this program governance board member has a personal connection to this vendor
What should the program manager do?
A voice over IP network that converges voice capabilities with softphones. Video communications, instant messaging is referred to as
An ICT distribution designer installed a 50/1 ?5 mm/1300 nm fiber optic cable from Building A to identical Building B with a distance of 600 m (1968 ft) At Building B. the designer fusion splice this new cable to an existing identical 50/126 mm fiber optic cable that runs 800 m (2525 ft) to Building C. Both ends are terminated with SC connectors. What is the loss budget for the above fiber link?
An initiative involves the development of new technology and leverages existing technologies It is determined critical by the program governance board and the program sponsor that a comprehensive risk management plan be put in place. In what phase is the nsk management plan created?
Based on the estimated work area size, what is the MAXIMUM number of work areas that a telecommunications enclosure shall serve?
A program manager for the construction of a ship reviews the program management plan with a shipyard representative. The shipyard representative indicates that while 65 percent progress was anticipated only 60 percent has been achieved
What should the program manager do to ensure benefits realization?
The program manager must define the program and understand the organization's target market and customer needs. What should the program manager do first?
When designing a video communications network, which type of video communication link is two-person videoconferencing?
A program receives initial approval from the selection committee to proceed with the program development. What should the program manager do next"?
During bidding the ICT distribution designer should review the bid responses for compliance and completeness. Afterwards, the designer should report the findings and recommendations to the
A program manager prepares the program for review to secure funding by senior management. Which of the following must the program manager identify when creating the program charter?
Which two of the following types of metallic conduit REQUIRE threaded couplings? (Select two options.)