SAFe-RTE Sample Questions Answers

Questions 4

During Pl Planning, who owns the planning of Stories into Iterations?

Options:

A.

Agile Teams

B.

Scrum Master

C.

Product Management

D.

System Architect

Buy Now
Questions 5

Which skill do Release Train Engineers (RTEs) have the opportunity to regularly practice and improve?

Options:

A.

Test-driven development

B.

Return-on-investment (ROI) projections

C.

Continuous Integration

D.

Servant leadership

Buy Now
Questions 6

What should the Release Train Engineer do during the final plan review on Day two of Program Increment (PI) Planning?

Options:

A.

Encourage discussion of each team's product Vision as part of the final plan re-view

B.

Verify that each team's uncommitted objectives have lower business value than the committed PI Objectives in order to reflect proper prioritization

C.

Facilitate the ROAMing of each team's risks

D.

Facilitate all teams when they are presenting their final plans to the entire Agile Release Train

Buy Now
Questions 7

Product Management wants to prioritize a list of Features likely to be planned in the up-coming Program Increment (PI) meeting. What should Product Management use as the denominator of the weighted shortest job first calculation?

Options:

A.

The T-shirt sizes for each of the Features

B.

The actual business value of each Feature

C.

Feature size expressed in story points

D.

Job size based on relative estimation

Buy Now
Questions 8

Release Train Engineers have the opportunity to regularly practice and improve which two skills? (Choose two.)

Options:

A.

Servant leadership

B.

Facilitation

C.

Test-driven development

D.

Return on investment projections

E.

Continuous Integration

Buy Now
Questions 9

What is included in the Inspect and Adapt agenda?

Options:

A.

Program backlog refinement

B.

System Demo

C.

Quantitative and qualitative measurement

Buy Now
Questions 10

Which statement is true about the definition of done (DoD)?

Options:

A.

The DoD is not used by the teams because it is used as a method to manage tech-nical debt across the ART

B.

At the higher levels there is only one DoD for everything that passes through the Agile Release Train to a Solution increment or a release

C.

The teams share one common DoD

D.

The DoD should evolve as system capabilities evolve

Buy Now
Questions 11

Which core competency helps foster faster lead time, faster recovery, fewer defects, and more frequent deployments?

Options:

A.

Lean-Agile Leadership

B.

Enterprise Solution Delivery

C.

Team and Technical Agility

D.

Agile Product Delivery

Buy Now
Questions 12

What is one risk of eliminating an Innovation and Planning (IP) Iteration?

Options:

A.

Bottlenecks can be hard to identify and resolve

B.

Teams have no time for fixing bugs

C.

Delivery can be blocked

D.

Technical debt can grow uncontrollably

Buy Now
Questions 13

Teams are reporting a high level of success through their individual quantitative meas-urements, but the system results say otherwise. What should the Release Train Engineer do to help the teams deliver more value?

Options:

A.

Coach the Scrum Masters on good retrospective techniques and ensure teams are defining and taking a systems view approach to improvements

B.

Share the quantitative measurement results with Product Management and lead-ership and ask for their input

C.

Diagnose the differences between the measurements and the results and suggest improvement items to each team

D.

Work with the team that is struggling the most to discover patterns that can be ap-plied to the other teams

Buy Now
Questions 14

Who provides Agile Release Train context and Vision during Pl Planning?

Options:

A.

Product Owner

B.

Product Management

C.

Release Train Engineer

D.

Business Owner

Buy Now
Questions 15

(What should be measured in a CALMR approach to DevOps?)

Options:

A.

Net Promoter Score (NPS)

B.

Flow through the pipeline

C.

Objectives and Key Results (OKRs)

D.

Code coverage

Buy Now
Questions 16

Which of the following is true of Iteration Goals in SAFe?

Options:

A.

They provide KPIs for tracking progress and value realization

B.

They enable teams to keep aligned with PI objectives

C.

They describe the value of planned Features and Enablers

D.

They provide quantifiable metrics to be used in retrospectives

Buy Now
Questions 17

Enabler Epics are used to advance what in order to support upcoming Business Epics?

Options:

A.

Value Stream(s)

B.

The Continuous Delivery Pipeline

C.

The Architectural Runway

Buy Now
Questions 18

What is a benefit of capacity allocation?

Options:

A.

It enables more effective time tracking

B.

It ensures all value streams in the portfolio are appropriately funded

C.

It ensures different types of backlog items are not compared against one another

Buy Now
Questions 19

Which of the Core Competencies of Business Agility includes aligning strategy with execution?

Options:

A.

Organizational Agility

B.

Lean Portfolio Management

C.

Agile Product Delivery

D.

Lean-Agile Leadership

Buy Now
Questions 20

In the SAFe work item hierarchy, Epics are decomposed into what?

Options:

A.

Features

B.

Stories

C.

Capabilities

Buy Now
Questions 21

Why should an RTE ensure that the SAFe principles are applied appropriately?

Options:

A.

To ensure that the SAFe House of Lean is reflected in standard operating proce-dure

B.

To build an understanding of why the lean-agile practices work

C.

To make sure that no modifications are made by the adopters of SAFe

D.

To maintain a central control of key decision-making

Buy Now
Questions 22

Which tool is typically not used during the problem solving workshop?

Options:

A.

Modified Fibonacci

B.

Fishbone diagram

C.

Dot voting

D.

Pareto analysis

Buy Now
Questions 23

When looking at a program board at the end of program increment (Pl) planning, what does it mean when a feature is placed in a team's swim lane with no strings?

Options:

A.

That the feature can be completed by that team independently

B.

That the team has not broken the feature into stories yet and has not identified dependencies

C.

That it has dependencies on teams in other Agile release trains (ARTs) or Solution Trains

D.

That the team has been assigned, but the feature’ uépendencies have not been identified yet

Buy Now
Questions 24

At which two stages will the Agile Release Train (ART) act as a one-team culture? (Choose two.)

Options:

A.

Performing - Creating a flow of knowledge across the teams and the ART

B.

Norming - Teams begin to form communities

C.

Storming - Fostering continuous improvement

D.

Collaborating - Pairing and sharing across the ART

E.

Forming - The leaders will start to emerge

Buy Now
Questions 25

How often should a system demo occur?

Options:

A.

After the end of each program increment (Pl)

B.

After every other iteration

C.

After every release

D.

After every iteration

Buy Now
Questions 26

Several Scrum Masters seem to be deadlocked in a disagreement on what to do about a shared issue. What is an appropriate coaching technique for the RTE to use?

Options:

A.

Performing an empirical assessment of the problem using metrics

B.

Asking powerful questions to invite creativity and new possibilities

C.

Being the final "decision making authority" once all views have been heard

D.

Bringing fresh emphasis to lean-agile's respect for people and culture

Buy Now
Questions 27

What are two outputs of Iteration Planning? (Choose two.)

Options:

A.

PI Objectives

B.

Iteration goals

C.

Team Backlog

D.

Iteration backlog

E.

Program Backlog

Buy Now
Questions 28

Which two actions can the Release Train Engineer take to facilitate team growth? (Choose two.)

Options:

A.

Provide a team vision

B.

Encourage continuous learning

C.

Encourage skill specialization

D.

Ensure time is allocated for innovation and planning

E.

Facilitate conflict

Buy Now
Questions 29

Which statement is true about nonfunctional requirements?

Options:

A.

They stay in the Portfolio Backlog until implementation capacity is available

B.

They are split into Features and acceptance criteria is established

C.

They operate as constraints on the design of the system

Buy Now
Questions 30

(What is one action the Release Train Engineer (RTE) can take to facilitate team growth?)

Options:

A.

Provide a team Vision

B.

Encourage continuous learning

C.

Encourage skill specialization

D.

Facilitate conflict

Buy Now
Questions 31

Which of the following is true about the ART sync event?

Options:

A.

It is run after PO-sync and Scrum of Scrum events

B.

It is a combination of PO-sync and Scrum of Scrums events

C.

It occurs during the Innovation and Planning iteration

D.

Attendance by the entire ART is important

Buy Now
Questions 32

The ART is near the end of the final Iteration of its first PI. Integration into staging is more challenging

than estimated. The ART adds a week to the Innovation and Planning (IP) Iteration for integration and

testing. Why is this action considered an anti-pattern?

Options:

A.

Overall, train velocity goes up, and the time-to-market goes down

B.

It decreases job satisfaction by removing autonomy and purpose

C.

It reduces the overall predictability established through cadence and synchronization

D.

It substantially decreases the predictability of the Solution Intent

Buy Now
Questions 33

When planning for a distributed PI Planning with a significant difference in time zones, what is a key

preparation and facilitation focus?

Options:

A.

Share the outcomes of preparation meetings with local Scrum Masters/Team Coaches (SM/TCs) so they can arrange local rooms

B.

Split up the PI Planning event per time zone and then have the final plan review, confidence vote, and planning retrospective as one centralized meeting

C.

Have a single Release Train Engineer (RTE) and technical support person that acts as a central point of communication for all locations

D.

Adjust the PI agenda to 2.5-3 days, allowing for overlapping hours

Buy Now
Questions 34

Why is it helpful to communicate newly refined Features and Enablers to the teams dur-ing the current Program Increment (PI)?

Options:

A.

Teams can prepare backlogs, give feedback to the Product Owner/Product Man-agement/System Architect, and begin looking at dependencies, impediments, and knowledge building

B.

Teams can review the Features and Enablers so they have an understanding of the Roadmap for the next PI

C.

Teams can establish face-to-face communication across all team members and stakeholders

D.

Teams can help support overall product integrity and facilitate working agree-merits during PI Planning

Buy Now
Questions 35

Product Management has content authority for the Program Backlog including the Vision, the Roadmap, driving the Pl Objectives, and what else?

Options:

A.

Establishing Features and benefit hypotheses

B.

Managing risk, helping to ensure value delivery, and driving continuous improvement

C.

Working with business stakeholders and Solution and System Architects to implement holistic technology across Value Streams

Buy Now
Questions 36

What are two anti-patterns for the IP Iteration? (Choose two.)

Options:

A.

To minimize lost capacity when people are on vacation or holidays

B.

To plan work for the IP lteration during P Planning

C.

To allow for sufficient capacity in the Program Roadmap

D.

To wait for the IP Iteration to fix defects

E.

To ensure all Stories and teams' Pl plans are completed prior to the IP Iteration

Buy Now
Questions 37

Which statement is true about using a Program Kanban system

Options:

A.

All work is visualized, progress is continually tracked

B.

WIP limits are used to provide any needed buffers

C.

Work is pushed through the Kanban to ensure train capacity is utilized

D.

The board tracks features, dependencies and milestones

Buy Now
Questions 38

What information is covered during the final plan review?

Options:

A.

Team Features, Stories, and team-level Enablers

B.

Planned Features, uncommitted objectives, and ROAMed risks

C.

Changes to capacity and load, final PI Objectives, ART PI Risks, and impediments

D.

Changes to Iteration Goals, measured velocity, and dependencies

Buy Now
Questions 39

How are the 5 Whys used?

Options:

A.

To coach a team through powerful questions

B.

To brainstorm ideas

C.

To define acceptance criteria for a Story

D.

To identify a root cause(s) of a problem

Buy Now
Questions 40

What is an input to the Program Increment Planning process that highlights how Product Management plans to accomplish the Vision?

Options:

A.

Top ten Features

B.

Top 20 Features

C.

Business context

D.

Program board

Buy Now
Questions 41

What is the purpose of Iteration Goals?

Options:

A.

To align the team members and the Product Owner to the mission

B.

To hold the team accountable to their Pl Objectives

C.

To summarize the business outcomes an Agile Team intends to achieve during the Program Increment (PI)

Buy Now
Questions 42

What are personas?

Options:

A.

Descriptions of actual target customers or users

B.

Key end-users the Product Owner leverages for managing the backlog

C.

Fictional representations of target customers or users

Buy Now
Questions 43

Becoming a coach requires a shift from old behaviors to new ones. What are three ex-amples of new coaching behaviors? (Choose three.)

Options:

A.

Facilitate team problem-solving

B.

Focus on business value delivery

C.

Drive toward specific outcomes

D.

Fix problems for the team

E.

Ask the team for the answer

F.

Focus on deadlines

Buy Now
Questions 44

An Agile Release Train (ART) is frequently discovering compatibility issues between the developed Solution and the Enterprise information architecture. What can the Release Train Engineer do to prevent this from occurring?

Options:

A.

Develop more detailed Feature definitions

B.

Add data Architects onto the ART

C.

Confirm attendance of architectural representatives at Program Increment (PI) Planning

D.

Conduct the entire data architecture design upfront

Buy Now
Questions 45

What behavior is an important part of the Release Train Engineer (RTE) role?

Options:

A.

Encourage teams to self-organize

B.

Manage dependencies for teams

C.

Provide teams with answers about Features

D.

Drive teams to specific outcomes

Buy Now
Questions 46

Which statement is true about SAFe Iteration Goals?

Options:

A.

They describe the value of planned Features and Enablers

B.

They provide key performance indicators (KPIs) for tracking progress and value realization

C.

They enable teams to keep aligned with PI Objectives

D.

They provide quantifiable metrics to be used in retrospectives

Buy Now
Questions 47

What is the best way for a Release Train Engineer to support teams having challenges with problem identification and decision making?

Options:

A.

By providing solution ideas

B.

By changing team composition

C.

By listening to the team

D.

By escalating to senior management

Buy Now
Questions 48

Why is it important for the RTE to understand Tuckman's group dynamic stages?

Options:

A.

The Tuckman four stages should be reflected in the design of the Program Kan-ban

B.

Tuckman helps to better understand Team and ART topologies

C.

The Tuckman dynamic nature of the stages requires that we assume variability and preserve options

D.

An ART is a team of teams and will likely also progress through the Tuckman stages

Buy Now
Questions 49

Which type of Enabler does a System Architect review during a System Demo?

Options:

A.

Enabler Epics

B.

Enabler Features

C.

Enabler Capabilities

D.

Enabler Stories

Buy Now
Questions 50

What does an effective Scrum Master help the team with?

Options:

A.

Risk mitigation

B.

Team metrics

C.

Relentless improvement

D.

Deploying work

Buy Now
Questions 51

Which statement describes flow velocity?

Options:

A.

The amount of Architectural Runway items in the backlog

B.

The number of Story points the combined ART plans for within each Iteration

C.

The number of Features committed to during PI Planning

D.

The system throughput

Buy Now
Questions 52

Why is a confidence vote held at the end of program increment (Pl) planning?

Options:

A.

To build shared commitment to the plan

B.

To remove the risks for the Pl

C.

To ensure the business owners accept the plan

D.

To hold the teams accountable if the Agile release train (ART) does not deliver on its commitment

Buy Now
Questions 53

What is one method for developing a sufficient Architectural Runway for the ART?

Options:

A.

Create alignment with the System Architect and Product Management that the first PI is all about Enablers to plan for creating business value in the second PI

B.

Ask the Business Owner which Enablers have high business value

C.

Ask the teams to commit only to Enablers as their PI Objectives during the PI Planning and address Features as uncommitted objectives for the first PI

D.

Work with Product Management and System Architects to identify future Features and determine the Enablers to achieve them

Buy Now
Questions 54

What is one of the questions the Product Management team must answer in order to create a Vision?

Options:

A.

Which themes are on the Roadmap

B.

How many Features have already been released to the Customer

C.

Which problem will the Solution solve

Buy Now
Questions 55

What is a characteristic of an effective Scrum Master?

Options:

A.

Gives open, honest opinions

B.

Removes all conflict

C.

As a technical expert

D.

Understands customer needs

Buy Now
Questions 56

During which part of an Inspect and Adapt event would differences between planned business value and actual business value be presented?

Options:

A.

Retrospective

B.

Problem-solving workshop

C.

Quantitative and qualitative measurement

D.

PI system demo

Buy Now
Questions 57

Program Increment (PI) Objectives should be written in the SMART format. What does the "R" in SMART stand for?

Options:

A.

Realistic

B.

Required

C.

Random

D.

Rationalized

Buy Now
Questions 58

What are three actions to take to support a Continuous Integration (CI) culture? (Choose three.)

Options:

A.

Purchase a CI tool

B.

Ensure fixing a failed integration attempt is always the top priority

C.

Secure senior leadership support before starting CI

D.

Integrate often

E.

Follow up with CI ceremonies

F.

Make integration results visible

Buy Now
Questions 59

What is one way to develop sufficient Architectural Runway for the Agile Release Train?

Options:

A.

Ask the teams to commit only to Enablers as their Program Increment (PI) Objec-tives during the PI Planning event and address Features as uncommitted objec-tives for the first PI

B.

Create alignment with the System Architect and Product Management that the first Program Increment (PI) is all about Enablers in order to plan for creating business value in the second PI

C.

Ask the Business Owner which Enablers have high business value

D.

Work with Product Management and System Architects to identify future Features and determine the Enablers to achieve them

Buy Now
Questions 60

During Program Increment (PI) Planning, a scrum of scrums occurs just before the draft plan review. The Scrum Master from one team raises an issue that one of the Product Managers just showed up to the planning area with a priority wish list of items. These items do not align with the Feature prioritization. What is the most likely planning anti-pattern causing this sudden impediment?

Options:

A.

There is strong alignment between business and marketing

B.

Planning decisions have been centralized

C.

Prioritization by Product Management was performed autonomously not collaboratively

D.

There is no social network that Solution development relies on

Buy Now
Questions 61

During Program Increment (PI) execution, the System Team is unclear about how to test some of the larger Features. What should a Release Train Engineer do?

Options:

A.

Allow the problem to reach a critical point knowing that a minor failure is a tech-nique for learning

B.

Encourage the System Team and Product Management to meet and collaborate on a solution

C.

Escalate the problem to senior management to get the required action

D.

Direct Product Management to define the use cases for the Features

Buy Now
Questions 62

(Which statement is a value from the Agile Manifesto?)

Options:

A.

Individuals and interactions over processes and tools

B.

Customer collaboration over following a plan

C.

Apply systems thinking

D.

Customer collaboration over a constant indefinite pace

Buy Now
Questions 63

Product Management is responsible for which activity?

Options:

A.

Establishing an architectural vision for the Agile Release Release Train

B.

Defining Program Backlog content

C.

Prioritizing the Portfolio Backlog

Buy Now
Questions 64

(What is one tool used to identify bottlenecks?)

Options:

A.

Objectives and Key Results (OKRs)

B.

Kanban Board

C.

Value Stream Mapping

D.

Ishikawa Diagram

Buy Now
Questions 65

What does transparency mean in a scrum environment?

Options:

A.

Development and Operations teams work together

B.

The process is visible to all stakeholders

C.

The team is constantly improving its process

D.

Team members must immediately share any and all feedback with each other

Buy Now
Questions 66

During the management review and problem-solving meeting, one team raises the risk of not finishing a Feature before the end of the Program Increment (PI). How can the man-agement team help ensure they complete the Feature within the PI?

Options:

A.

Use buffer resources as a guard band

B.

Redefine the definition of done for Features

C.

ROAM the risk appropriately

D.

Negotiate a reduction in scope of the Feature

Buy Now
Questions 67

Which two actions can be taken immediately during the management review and prob-lem-solving meeting? (Choose two.)

Options:

A.

Change the business priorities

B.

Recognize the team with the highest velocity

C.

Combine teams to increase velocity

D.

Change the scope

E.

Hire new people

Buy Now